Professional Documents
Culture Documents
عنوان التقرير
) (Network Analysis
Network Analysis
Introduction
Network scheduling is a technique used for planning, and scheduling large projects in the field of
construction, maintenance, fabrication, purchasing computer system etc. The technique is a method
of minimizing the trouble spots such as production, delays and interruptions, by determining critical
factors and coordinating various parts of the overall job. There are two basic planning and control
technique that utilize a network to complete a predetermined project or schedule. These are
Program Evaluation and Review Technique (PERT) and Critical Path Method (CPM). A project is
defined as a combination of interrelated activities all of which must be executed in a certain order
for its completion
Activity: These are the portions of a project/operation that consume time or resources and have
definable start and end. Commonly used synonyms are “Task”, and “Job”. Activities are graphically
represented by arrows with arrow heads showing the direction.
Event: The beginning and ending points of activities are called events. Theoretically any event is
an instantaneous point in time. Commonly used synonyms are “Node”, and “Connector”. Events
are graphically represented by numbered circles, although any geometric figure will serve the
purpose
Merge and Burst Events: If an event represents the joint completion of more than one
activity, it is called a “merge” event. If an event represents the joint initiation of more than one
activity, it is called a “burst” event..
c C
SOLUTION:
The resulting arrow diagram is shown below. The diagram shows that the dummy activities
D1and D2 are used to establish correct precedence relationships. D3 is used to identify activities
E and H with unique end events. The event of the project are numbered such that their ascending
order indicates the direction of progress in the project
D K
7
3
7 L
J
A
D1 4 D3
H I
9
B E
1 2
5
F D2
C G
6
EXAMPLE- 2
Construct a network for the project whose activities and their precedence relationships are as
given in Table I:
Activity A B C D E F G H I
Predecessor __ A A __ D B,C,E F D G,H
Activity
SOLUTION:
From the given constraints, it is clear that A, D are the starting activity and I the terminal activity.
B. C are starting with the same event and are both the predecessors of the activity F. Also E has to
be the predecessor of F. Hence, we have to introduce a dummy activity
B
4
2
A D1
C
F G I
1
5 6 7 8
D E
3
H
EXAMPLE- 3
Construct a network for the project whose activities and their precedence relationships are as
given in Table 2.
TABLE2
Activity A B C D E F G H I J K
Predecessor - - - A C B,D B,D E,F A G,H E,F
Activity
SOLUTION:
2 I
A
D
G
6 J
B
F
1 4
H
7
K
C 3 E 5
EXAMPLE- 4
Construct the network for the project whose activities, their durations and their precedence
relationships are as given in Table 3:
TABLE 3
A - 2
B A 6
C B 6
D B 1
E A 3
F E,D 3
G C,F 2
SOLUTION:
3
C
B
6
6
1 D
A G
1 2 5 6
E
2 F
2
3 3
4
References
-Dr. Mahmoud Al-Naimi-Network analysis, https://www.slideshare.net/DrMahmoudAlNaimi1?
utm_campaign=profiletracking&utm_medium=sssite&utm_source=ssslideview,pages 05 ,(Published on
Oct 24, 2016 )
-Wikipedia, https://en.wikipedia.org/wiki/Weighted_correlation_network_analysis