Professional Documents
Culture Documents
LECTURE 07
PERT
2
CPM Calculations
3
Forward and Backward Pass
Forward pass is a technique to move forward
through network diagram. Backward pass is its
opposite.
5
Late Start and Late Finish Steps
Begin at ending event and work
backward
LF = Maximum EF for ending activities
LF is latest finish; EF is earliest finish
LS = LF - Activity time
LS is latest start
LF = Minimum LS of all successors for
non-ending activities
6
Slack Time/Float
Slack Time is the
t amount of time an
activity may be delayed without
affecting the project deadline. This is
also referred as float.
Total Slack Time/Total Float:
Slack Time shared among more than
one activity.
Free Slack Time/Free Float:
Slack Time associated with a single
activity. 7
Critical Activity
An activity having zero slack time is called
critical activity.
9
Explanation of Total Float
Total Float is valid for a chain and not for a
single activity.
11
CPM Calculations
for AON Network
12
Legends
Name
Activity
Earliest Earliest
Start ES EF
Finish
Latest LS Duration LF
Start Activity Latest
Finish
Key 13
Problem 3: General Hospital’s Activities
and Predecessors
14
AON Network for General Hospital
Includes Critical Path
A C FF
0 H 2 2 H 4 4 H 7
0 A 2 2 C4 10 13
2 2 3
Slack=0 E H
Slack=0 4 H 8 Slack=6 13 H 15
0 HStart0 F
0 4 8 13 15
0 4 2
0
BB DD Slack=0 G
Start 0 H 3 3 H 7 8 G Slack=0
H 13
1 4 4 8 8 13
3 4 5
Slack=1 Slack=1 Slack=0
15
Critical Path for General Hospital
F
A C
Start F H
B D G
s s h ow
Arrow dence
prece ships
l a ti on
re
16
Gantt Chart for General Hospital
Early Start and Finish
General Hospital
1 2 3 4 5 6 7 8 9 10 1112 13 1415 16
A Build internal components
B Modify roof and floor
C Construct collection stack
D Pour concrete and install
frame
E Build high-temperature
burner
F Install pollution control
system
G Install air pollution device
H Inspect and test
17
Gantt Chart for General Hospital
Late Start and Finish
General Hospital
1 2 3 4 5 6 7 8 9 10 1112 13 1415 16
A Build internal components
B Modify roof and floor
C Construct collection stack
D Pour concrete and install
frame
E Build high-temperature
burner
F Install pollution control
system
G Install air pollution device
H Inspect and test
18
CPM Calculations
for AOA Network
19
Activity Scheduling
An activity’s early starting time equals
the TE of its beginning event: ES = TE.
20
Problem 04
22
Early Event Time (TE)
23
Finding TE Values
24
Late Event Time (TL)
25
Finding TL Values
26
Critical Path
27
Problem 04
Solution - AOA Method
B - 5
C - 7
D A 8
E B 5
F C 5
G E 4
H F 5
I D 6
J G-H 4
1 A 2 -
2 B 1 A
3 C 6 A
4 D 6 C
5 E 4 B
6 F 2 A
7 G 3 D, E, F, H
8 H 2 -
1/2
Standard deviation = =(V)
Probability
Pr = Φ (D – T) /
Variance V= Va + Vd + Vh
= 1.78+7.11+1.78= 10.67
38
Problem 09 (Pert Solution)
The variance as such does not provide much
practically useful information about
uncertainty. It is used to calculate probability,
which can then be used as a decision
parameter.
39
Problem 09 (Pert Solution)
1/2 1/2
Standard deviation= = (V) = (10.67)
= 3.266
Probability
Pr = Φ (D – T) /
D= deadline / desired completion time=40
T= project completion time=44
Pr = Φ (40 – 44) / 3.266 The chance of
= Φ (-1.23) = 0.11 meeting the
deadline is 11
percent only.40
Problem 09 (Pert Solution)
What deadline project manager should give if
he/she wants 90 percent probability of finishing
on or before the deadline?
If this deadline is D, using the formula
0.90 = Φ (D – 44) / 3.266
D= 48.2
R
E
S In order to have 90 percent
U
L
guarantee against a delay, 41
T the deadline should be 49 days.
Comments on Pert
Program evaluation and review technique (PERT)
allows activity duration with uncertainty. It assumes
that there is no underlying connection leading to
simultaneous duration variation of two or more
activities.
44