You are on page 1of 8

Project: Date: 27-May-2023

Construction works For the Upgrade of WWTPs at AL Shuwaib and Ghantoot.


Contract No. O-14902.1
“Ghantoot Site Report”
GHANTOOT SITE LAYOUT

Contract Duration:
Commencement Date: 12th, October-2021.
Project Duration: 34-Months.
Completion Date: 11th, August-2024
SITE ACTIVITIES
SITE ACTIVITY (Ghantoot Site)

F. F Slab in progress (Electrical Works) and Waiting for authority


Substation:
approval.

Workshop: Construction of Roof Slab in progress, (Formworks).

MCC & Blower Construction of foundation is done, (Trench wall and short
Room: column reinforcement in progress)

All Structural activities are finished rest. Internal wall grinding


Aeration Tank
and repairing.

Clarifier 01: FC Coating in progress.

Clarifier 02: SC Coating in progress.

Lift Station: Waiting for approval.

Spill Collection Trial Pit has finished, and Manual excavation is ongoing for the
Tray pipeline.

Ras-SAS inside Wall Fixing short pipe puddle flange in progress

Slug Thickener Weir wall formwork and reinforcement in progress.


OHS DOCUMENTS & SITE STATUS.
OHS documents are maintained and site requirements are compiled as
mentioned below,
• OHS-CMP file is ready.
• Recent work-related approved MS/RAs are ready and copies are placed at
site.
• Work permits are maintained and keep closed off all the previous work
permits.
• Training and tool box talk record are updated as per plan.
• Emergency contact numbers and services provider’s posters are posted at
the designated area.
• PPE Compliance is ensured.
• Plan Drill is conducted.
• Competency training certification is ensured.
• Work at height is protected.
• Scaffolding is inspected and inspection tags are provided.
• Housekeeping and material management in progress.
• Temporary storage barricading is in progress.
• Dust control is maintained.
• Site access is maintained.
• Contractor HSE Team (Site HSE Manager, Officer and assistant officer) are
available and controlling the site.

SITE RECENT PHOTOS


Handrail fixed to all the constructed stairs

Handrail fixed to all the constructed stairs


Workshop building construction, roof is
protected with handrails.

Rest area with bench and table


DMT Alert communication

1st Aid Drill conducted as plan.


Substation is waiting for approval

MCC building construction,


Office Corridor

Updated Notice Board