1.Supply of Transformers
Matter most urgent. Ordering to be done immediately to meet start up power requirements.
(Transformers in LMB Scope =87nos.: Oil Type – 81nos; Dry Type – 6nos)
LMB has been asked to order the transformers by May-22 in last MRM dtd 06.05.22.
2.Manpower
LMB last commitment 1480 Nos. vs present Man power 1300 Nos.
Urgent requirement
-LMB need to immediately increase No. of Welders to 20 to achieve PP joint targets without backlog.
Total Total Total sub Total Resub Due Total Cat III Overall
drawings submitted Due ( CAT II,III,IVR) Approved Eng Sub
2722 1984 729 264 1891 55 72.8%
4. Boiler# 1
Complete staircase on both sides, floor grating, handrails, lift approach to boiler top etc. to be
expediated. LHS stair case completed however RHS stair and balance grating materials are still to be
expedited.
5. Boiler#2
Supply of 01 primary column in 6 th tier and K-K1 columns beyond tier3 is pending.
Supply of secondary structures, gratings, handrails and staircase beyond tier-4 etc is to be
expediated.
6. ESP-1
Major concern as LMB informed that KCC backed off to work with the project to supply ESP material.
Supply of balance casing & casing structure, roof girders and structures to be expediated for
ensuring material supply for meeting BLU requirement.
7. ESP-02
Only 620 MT received at site out of 8200 MT, Supply of balance structures needs to be expediated.
9. FGD
Erection in only 03 tanks is in progress, erection in balance tanks also needs to be resumed.
10. AHP
11. CHP
- Chimney concrete lifts to be resumed which is in stand still for 1 month due to severe honey comb.
AHP control room & Switchgear room, Gypsum dewatering Building and Ball mill building(super
structure): Release of RFC drawing & early commencement of works - dwg to be released
Roads, Drains and culvert almost standstill. LMB to submit PO of new vendor and Works to be
resumed immediately so as to complete it before upcoming monsoon to avoid water logging and
stoppage of works.