2. Financial progress: total expenditure incurred till date is Rs. ~ 157 Cr.
including fully utilization of 10% mobilization advance released by NHAI
against total EPC cost of Rs.678.69 Cr (this as per the discussion with EPC
contractor and SPV).
4. Payment status from NHAI (i.e. 40% payment from authority for HAM
projects).
Against Milestone -II i.e. after 30% physical progress- planning to submit
bill for 8% of 40%EPC cost to authority in next week (physical progress till
date ~29%. This is updated by contractor and SPV)
5. Land status: ~86% till date land has been acquired. Remaining will be
available in next 3 months since compensation is pending from authority to
landholders.
7. Structures:
GAD of new ROB has been approved. GFC also have vetted from IIT-
Varanasi. GFC approved by IE and Authority however, approval is
pending from Railway authority and expected to get approval in
one and half months (15 days back drawings have been submitted
for approval).
Existing ROB will be rehabilitated and work has not been started yet.
Flyovers (3 New):
10. Plants (2 base camps + 1 school building i.e. Devaraju Gattu camp hired for
staying).
11. Labs: 2 labs located at each base camp and performing routine tests on daily
basis as standards and specifications.
12. Toll plazas (2nos): Construction of TP1 is in progress. TP2 not started yet
13. Truck lay byes and rest areas- construction has not started yet
14. Resources*:
Manpower: total ~ 400 nos. including staff EPC, SPV and sub-contractors-
Machineries: adequate
Material: Production and stack is adequate.
LA, structure demolitions within ROW along with trees cutting are still
pending (however, Competent Authority for Land Acquisition (CALA) has
instructed to concerned departments to complete this process of pending land
acquisition within 3 months)
Utility shifting work is pending
ROB - all GFC's approvals are pending from railway department.
Bypass length ~ 16Km (part of NH- 565 -Hydrabad Tirupati Road) not in
scope of concessionaire
Proposed Hyderabad Expressway is coming parallel to GV road. LA of
same is in progress