GPP 4 Ras Fortnightly Project Progress

Status
(April 14 1st Fortnight)
Present Status
(A)

(B)

(C)

Unit-IX - Priority 1ST (ACC, TG AND AQC-9 Boiler)


AQC-IX Boiler synchronized with TG 21 Feb 2014. Completed.
Insulation and outer casing work under progress.
Unit-IX Priority 2nd (PH-9 Boiler)
PH-IX Boiler synchronized with TG 22 March 2014
Insulation and outer casing work under progress.
Unit-X - Priority -3rd (AQC-10 & PH10 Boiler)
Target Readiness of AQC-X Boiler 21 July 2014
Target Readiness of PH-X Boiler 01 Sept 2014
Present Status- No Delay. Cement plant area constrain for erection
and clearance for balance civil pipe rack footing work.
AQC-X Boiler LP Pressure parts erection completed. HP Pressure parts,
down comer and risers erection under progress.
PH-X Boiler structure ground assembly completed erection under
progress.
PH-X Boiler Riser, down comer and steam piping ground fabrication
under progress.
PH-X Boiler casing expansion bellow ground assembly and welding
work under progress.
PH-X Boiler Pressure parts ground assembly work started.

Major Highlights of Mar 14 (2nd Fortnight)


PH-X Boiler Structure and platform erection start on 01-Apr-2014.
PH-X Boiler Pressure parts ground assembly started.
AQC-X Boiler structure erection completed. Platform and hand railing
erection under completion.
AQC-X Boiler riser and down comer ground assembly completed.
Erection Under progress.

Look Ahead
Fortnight)

Activities

of

Apr

14

AQC-X Boiler Pressure parts erection completion.


AQC-X Boiler down comer and riser erection completion.

(1st

AQC-X Boiler LP module ready for hydro testing.


Civil work for balance pipe rack footings, after cement plant area
clearance.
PH-X Boiler pressure parts erection start.

Project Progress Curves


(A)

Priority Ist Unit 9 (TG, ACC & AQC Boiler)

(B)

Prioirty IInd Unit 9 (PH Boiler)

(C)

Prioirty IIIrd Unit 10 (AQC & PH Boiler)

Encl Site Photographs