Square Bar installation over 380kv GIS Bldg. crane girder/ OHC runway beam in progress.

Square Bar installation over 380kv GIS Bldg. crane girder/OHC runway beam in progress.
Formwork Preparing for BD Wall isolated footing column neck in progress.

Formwork Preparing for BD wall isolated footing column neck in progress.


Formwork for C2 tunnel EM Exit in progress.

Preparing and casting column neck for Control bldg Canopy footing in progress.
Water Test Over control bldg. along grid line 9 to 20 in progress.

Preparing and thermal insulation installation over control bldg along Grid line 1 to 8 in progress.
Tiles installation for Control Bldg Battery Room Flooring in progress.

Preparing and Tiles Installation for Control Bldg Battery Room Flooring in progress.
Formwork for GIB isolated footing column neck in progress.

Formwork for GIB isolated footing column neck in progress.


Waterproofing membrane installation for GT & Reactor Trench wall in progress.

Waterproofing membrane installation for GT & Reactor Trench wall in progress.


Waterproofing membrane installation for GT & Reactor Trench wall in progress.

Waterproofing membrane installation for GT & Reactor Trench wall in progress.


Preparing and Casting P1A tunnel wall in progress.

Preparing and casting P1A tunnel wall in progress.


Excavation & Earth Levelling under P2 tunnel raft foundation in progress.

Excavation and Earth levelling under P2 tunnel raft foundation in progress.


Curing Work for P3 & P4 Tunnel screed concrete in progress. Pouring concrete
was done on 31-3-2016.

Curing Work for P3 & P4 Tunnel screed concrete in progress. Pouring concrete
was done on 31-3-2016.
Curing work for Pump House wall in progress. Pouring concrete was done on 31-3-2016.

Curing work for Pump House wall in progress. Pouring concrete was done on 31-3-2016.