You are on page 1of 5

Last week Activities (07-October-2022 to 13-October-2022)

HV – Civil Activities
1. Final coat of painting works in Plant Manager room (33KV Building)
2. Marble fixing for staircase-1 (33KV Building)
3. Staircase Handrails fixing (33KV Building)
4. Interlock tiles fixing for walkway around (33KV Building)
5. Housekeeping for Combo roof top coat painting works (33KV Building)
6. Fixing of kitchen cabinet (33KV Building)

7. Tapping and jointing works for false ceiling (Visitor center building)
8. Floor tiles fixing in staff room (Visitor center building)
9. Floor tiles fixing in Corridor Area (Visitor center building)
10. Interlock tiles fixing for walkways around (Visitor Center Building)

11. Epoxy painting works on ramp area (Workshop & Storage Area)
12. Tiles fixing in wet areas (workshop building)
13. Interlock tiles fixing for walkways (workshop building)

14. Grid Installation works for false ceiling (Guard House)

15. Placement of chain link fence foundations


16. Coal tar epoxy painting works for foundations (Chain link fence foundations)
17. Epoxy Painting works for Fire Hydrant pipe support foundations
18. Blinding concrete for Kerb stone
19. Placement of Kerb stones
20. Hunching concrete for Kerb stone
21. Sub base layer for asphalt road
22. Roadbase layer for asphalt road
23. MC primer works for Asphalt road
24. Binder Course laying for asphalt road
25. Installation and fixing of lightning rods
26. Epoxy painting works for stormwater and foul water manholes
27. Steel and shuttering works for storm water and foul water manhole covers
28. Concrete casting for manhole covers
29. Gravel Filling in Gravel filling areas
30. Interlock tiles fixing
31. Installation of Car Parking shed
32. Interlock tiles fixing in walkways
33. Installation of Aluminum louvers in chiller yard area

34. Fixing of Shed for (Fuel tank)


35. Fixing of Shed for (DG ROOM)
36. Epoxy painting works (DG Shed, AND FUEL TANK)
37. Steel and shuttering fixing works for Ramp of (DG Shed, AND FUEL TANK)
38. Epoxy Painting works in Trenches between DG Shed and FUEL Tank

39. Removable fence installation (Transformer-1,2 &3)


40. Removable Fence Installation (Earthing Transformer-3 & 4)
41. Chequered plates fixing (Auxillary Transformer)
42. Completion of Gravel filling (Earthing Transformer 3 & 4)
43. Gravel Filling in (Transformer-2)
44. Gravel Filling in (Transformer-3)
45. Gravel Filling in (AIS-1, AIS-2 and AIS-3)

46. Concrete casting for chain link fence Foundations (Capacitor Bank)
47. Placement of precast cover slabs
48. Epoxy painting works on trenches in (Capacitor Bank Extension)
49. concrete for tie beams of chainlink fence (Capacitor Bank)
50. Backfilling works around foundations (Capacitor bank Extension)
51. Fixing of Gates for chainlink fence (Capacitor Bank)
52. Mesh Fixing for Chainlink fence foundations (Capacitor Bank)
53. Gravel filling

MEP Activities:
1. Duct Installation Works in (workshop Building)
2. Cable tray & Trunking (Workshop Building)
3. fire pump room switch & socket fixing
4. HV Area Earthing Works
5. Fire Sealant Works (Visitor center)
6. External Plumbing Works (Storm water/Drainage Etc.)
7. External cable pulling work near capacitor bank area to 33 kv building
8. installation of FAHU at Visitor Building chiller yard
9. Firefighting PIPE INSTALLATION & Supports Installation of final fix (33KV building)
10. Cable pulling for EMERGENCY LIGHT in (Gate house)
11. Glading & termination (Visitor building)
12. fire pump room External wall light fixture
13. installation of FM200 Detector & Nozzle devices in 33 KV switch gear building & admin building
Relay protection room below raised Floor
14. Installation of VESDA system
15. Functionality test & sequence of operation for FM200 system in 33 KV switch gear building & admin
building Relay protection room
16. Cable termination and ducting works (Chiller Yard)
17. Cable termination and ducting works (workshop & Storage Building)
18. installation of Exhaust fan along with ducting, necessary dampers & accessories at Workshop
building roof
19. installation of Exhaust fan at Workshop building roof
20. installation of fan control panel along with cable glanding & termination in Fire pump room roof
21. mock up installation of urinal in 33 kv building male toilet
22. mock up installation of Janitor sink in 33 kv building male toilet
23. mock up installation of WC in 33 kv building male toilet

Testing & Commissioning:


1. Gravity Tests for external drainage/Storm water pipeline Works
2. Fire Fighting pressure tests (visitor center building and Transformer-1 & 2)
3. Energization of Sprinkler system
4. Testing of emergency light system
5. Light function test
6. Air Balancing
7. Fire Alarm
8. Testing & commissioning for air balancing for Exhaust in 33 kV building male toilet, female toilet &
male shower
9. Functionality test & sequence of operation for Light fixture in fire pump room

10. Next week activities


54. Combo roof final painting works (33KV Building)
55. Roadbase layer for walkway
56. Interlock tiles fixing for walkway
57. Skirting fixing in LVAC ROOM
58. Hand rails fixing in Staircase area
59. Ramp Construction

60. Tapping and jointing for false ceiling system (Visitor center Building)
61. Floor Tiles fixing in conference room (Visitor center building)
62. Painting works on walls (Visitor center building)
63. Floor tiles fixing in VIP Lounge and corridor area (Visitor center building)
64. Painting works on walls (Visitor center building)

65. Epoxy painting works on ramp areas (Workshop & Storage Building)
66. Tiles fixing works in (workshop & Storage Building)

67. Completion of grid installation for false ceiling works (Guard House)

68. Placement of Kerb stones


69. Hunching concrete for Kerb stone
70. Roadbase layer for asphalt road
71. MC primer works for Asphalt road
72. Installation and fixing of lightning rods
73. Steel and shuttering works for stormwater and foulwater manhole covers
74. Concrete casting for manhole covers
75. Gravel Filling in Gravel filling areas
76. Interlock tiles fixing
77. Interlock tiles fixing in walkways
78. Binder course laying for asphalt road

79. removable fence installation (Transformer-3,2 & earthing transformer-3 & )


80. Removable Fence Installation (Earthing Transformer-5 & 6)
81. Gravel Filling in (Transformer-2)
82. Gravel filling in (transformer 3)
83. Gravel filling in (Earthing Transformer 5 & 6)

84. Placement of precast cover slabs


85. Concrete for tie beams of chainlink fence (Capacitor Bank)
86. Backfilling works around foundations (Capacitor bank Extension)
87. Fixing of Gates for chainlink fence (Capacitor Bank)
88. Mesh Fixing for Chainlink fence foundations (Capacitor Bank).
89. Coal Tar Epoxy Painting works (Capacitor Bank)
90. Gravel Filling (Capacitor Bank)

MEP Activities:
11. Installation of portable water tank (Near Pump Room)
12. Cable tray & Trunking (Visitor center & Workshop Building)
13. Main cable Pulling for HVAC (Visitor Center & Workshop Building)
14. Conduiting & Box Fixing (Workshop & Storage Building)
15. HV Area Earthing Works
16. Fire Sealant Works (33KV Building & visitor center building)
17. External Plumbing Works (Storm water/Drainage Etc.)
18. Fire Alarm Works (Transformer-3)
19. Installation of GRP water tank (Gate House)

Testing & Commissioning:


20. Gravity Tests for external drainage/Storm water pipeline Works
21. Fire Fighting pressure tests (workshop Building)
22. Water supply Pressure test
23. Firefighting flushing tests.
24. Lighting function test.
25. Gravity Tests for external drainage/Storm water pipeline Works
26. Fire Fighting pressure tests (visitor center building and Transformer-1 & 2)
27. Energization of Sprinkler system
28. Testing of emergency light system
29. Light function test
30. Air Balancing
31. Fire Alarm
32. Testing & commissioning for air balancing for Exhaust in 33 kV building male toilet, female toilet &
male shower
33. Functionality test & sequence of operation for Light fixture in fire pump room

You might also like