You are on page 1of 4

Activity ID Activity Name Original Duration Start Finish

HV & ESF COMBINED BL 2 SCHEDULE - -14102022UP 60 01-Aug-2022 A 4-Nov-22


HV-400KV PV2 STUP UP SUBSTATION 60 01-Aug-2022 A 4-Nov-22
TESTING & COMMISSIONING 60 01-Aug-2022 A 4-Nov-22
TESTING & COMMISSIONING- HVAC 53 23-Aug-2022 A 4-Nov-22
33kV Switchgear Building 10 23-Aug-2022 A 19-Oct-22
A1240 Air Balancing 5 28-Aug-2022 A 30-Sep-2022 A
A1000 Panel Testing 3 23-Aug-2022 A 02-Oct-2022 A
A1230 Unit Testing 2 23-Aug-2022 A 19-Oct-22
Visitor Area 12 14-Oct-22 27-Oct-22
A1030 Panel Testing 4 14-Oct-22 18-Oct-22
A1080 Unit Testing 4 19-Oct-22 22-Oct-22
A1090 Air Balancing 4 24-Oct-22 27-Oct-22
Warehouse 8 27-Oct-22 4-Nov-22
A1040 Panel Testing 4 27-Oct-22 31-Oct-22
A1140 Unit Testing 4 1-Nov-22 4-Nov-22
A1150 Air Balancing 4 1-Nov-22 4-Nov-22
Gate House 4 14-Oct-22 18-Oct-22
A1050 HVAC SYSTEM 4 14-Oct-22 18-Oct-22
FIRE PUMP ROOM 5 02-Sep-2022 A 19-Oct-22
A1060 HVAC SYSTEM 5 02-Sep-2022 A 19-Oct-22
TESTING & COMMISSIONING- FPS 57 01-Aug-2022 A 1-Nov-22
33kV Switchgear Building 48 01-Aug-2022 A 1-Nov-22
A1070 Sprinkler pressure Test 1 01-Aug-2022 A 01-Aug-2022 A
A1250 FM200 piping pressure Test 1 01-Aug-2022 A 01-Aug-2022 A
A1160 Fire Alarm Panel Functional Test 1 29-Aug-2022 A 30-Aug-2022 A
A1260 Fire Alarm Device Test 1 29-Aug-2022 A 30-Aug-2022 A
A1260. FM200 System Test 4 25-Aug-2022 A 03-Oct-2022 A
A1290 Room Integrity Test 4 19-Oct-22 22-Oct-22
A1280 VESDA System 7 19-Oct-2022* 26-Oct-22
A1270 Deluge Test 2 27-Oct-22 28-Oct-22
A1130 LHS Test 5 27-Oct-22 1-Nov-22
Step Up Transformer Room 35 30-Aug-2022 A 17-Oct-22
A1170 Pressure Test 6 30-Aug-2022 A 31-Aug-2022 A
A1300 Fire Alarm Test 4 30-Sep-2022 A 02-Oct-2022 A
A1100 Deluge Test 4 01-Sep-2022 A 17-Oct-22
Visitor Area 50 14-Aug-2022 A 28-Oct-22
A1180 Sprinkler pressure Test 4 14-Aug-2022 A 16-Aug-2022 A
A1110 Fire Alarm Device Test 4 24-Oct-22 28-Oct-22
Warehouse 47 25-Aug-2022 A 31-Oct-22
A1190 Sprinkler pressure Test 4 25-Aug-2022 A 26-Aug-2022 A
A1120 Fire Alarm Device Test 4 27-Oct-22 31-Oct-22
Pump Room 17 27-Aug-2022 A 25-Sep-2022 A
A1310 Pressure Test 4 27-Aug-2022 A 28-Aug-2022 A
A1320 Pump System 2 01-Sep-2022 A 25-Sep-2022 A
Grounding Transformer Room 2 01-Oct-2022 A 03-Oct-2022 A
A1200 FIRE ALARM TESTING 2 01-Oct-2022 A 03-Oct-2022 A
Auxiliary Transformer Room 4 17-Oct-22 20-Oct-22
A1210 FIRE ALARM TESTING 4 17-Oct-22 20-Oct-22
Gate House 4 26-Oct-22 29-Oct-22
A1220 FIRE ALARM TESTING 4 26-Oct-22 29-Oct-22
Labor Units % Complete
57.74%
57.74%
57.74%
52.17%
96.67%
100%
100%
90%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
90%
90%
61.46%
55.56%
100%
100%
100%
100%
100%
0%
0%
0%
0%
93.33%
100%
100%
80%
50%
100%
0%
50%
100%
0%
100%
100%
100%
100%
100%
0%
0%
0%
0%

You might also like