The document is a Gantt chart that outlines the schedule and progress for testing and commissioning activities at a substation project. It includes details of over 30 individual tasks related to HVAC and fire protection system testing, with planned start and finish dates ranging from August 1st to November 4th, 2022. The percentage of work completed is also provided for each activity.
The document is a Gantt chart that outlines the schedule and progress for testing and commissioning activities at a substation project. It includes details of over 30 individual tasks related to HVAC and fire protection system testing, with planned start and finish dates ranging from August 1st to November 4th, 2022. The percentage of work completed is also provided for each activity.
The document is a Gantt chart that outlines the schedule and progress for testing and commissioning activities at a substation project. It includes details of over 30 individual tasks related to HVAC and fire protection system testing, with planned start and finish dates ranging from August 1st to November 4th, 2022. The percentage of work completed is also provided for each activity.
HV-400KV PV2 STUP UP SUBSTATION 60 01-Aug-2022 A 4-Nov-22 TESTING & COMMISSIONING 60 01-Aug-2022 A 4-Nov-22 TESTING & COMMISSIONING- HVAC 53 23-Aug-2022 A 4-Nov-22 33kV Switchgear Building 10 23-Aug-2022 A 19-Oct-22 A1240 Air Balancing 5 28-Aug-2022 A 30-Sep-2022 A A1000 Panel Testing 3 23-Aug-2022 A 02-Oct-2022 A A1230 Unit Testing 2 23-Aug-2022 A 19-Oct-22 Visitor Area 12 14-Oct-22 27-Oct-22 A1030 Panel Testing 4 14-Oct-22 18-Oct-22 A1080 Unit Testing 4 19-Oct-22 22-Oct-22 A1090 Air Balancing 4 24-Oct-22 27-Oct-22 Warehouse 8 27-Oct-22 4-Nov-22 A1040 Panel Testing 4 27-Oct-22 31-Oct-22 A1140 Unit Testing 4 1-Nov-22 4-Nov-22 A1150 Air Balancing 4 1-Nov-22 4-Nov-22 Gate House 4 14-Oct-22 18-Oct-22 A1050 HVAC SYSTEM 4 14-Oct-22 18-Oct-22 FIRE PUMP ROOM 5 02-Sep-2022 A 19-Oct-22 A1060 HVAC SYSTEM 5 02-Sep-2022 A 19-Oct-22 TESTING & COMMISSIONING- FPS 57 01-Aug-2022 A 1-Nov-22 33kV Switchgear Building 48 01-Aug-2022 A 1-Nov-22 A1070 Sprinkler pressure Test 1 01-Aug-2022 A 01-Aug-2022 A A1250 FM200 piping pressure Test 1 01-Aug-2022 A 01-Aug-2022 A A1160 Fire Alarm Panel Functional Test 1 29-Aug-2022 A 30-Aug-2022 A A1260 Fire Alarm Device Test 1 29-Aug-2022 A 30-Aug-2022 A A1260. FM200 System Test 4 25-Aug-2022 A 03-Oct-2022 A A1290 Room Integrity Test 4 19-Oct-22 22-Oct-22 A1280 VESDA System 7 19-Oct-2022* 26-Oct-22 A1270 Deluge Test 2 27-Oct-22 28-Oct-22 A1130 LHS Test 5 27-Oct-22 1-Nov-22 Step Up Transformer Room 35 30-Aug-2022 A 17-Oct-22 A1170 Pressure Test 6 30-Aug-2022 A 31-Aug-2022 A A1300 Fire Alarm Test 4 30-Sep-2022 A 02-Oct-2022 A A1100 Deluge Test 4 01-Sep-2022 A 17-Oct-22 Visitor Area 50 14-Aug-2022 A 28-Oct-22 A1180 Sprinkler pressure Test 4 14-Aug-2022 A 16-Aug-2022 A A1110 Fire Alarm Device Test 4 24-Oct-22 28-Oct-22 Warehouse 47 25-Aug-2022 A 31-Oct-22 A1190 Sprinkler pressure Test 4 25-Aug-2022 A 26-Aug-2022 A A1120 Fire Alarm Device Test 4 27-Oct-22 31-Oct-22 Pump Room 17 27-Aug-2022 A 25-Sep-2022 A A1310 Pressure Test 4 27-Aug-2022 A 28-Aug-2022 A A1320 Pump System 2 01-Sep-2022 A 25-Sep-2022 A Grounding Transformer Room 2 01-Oct-2022 A 03-Oct-2022 A A1200 FIRE ALARM TESTING 2 01-Oct-2022 A 03-Oct-2022 A Auxiliary Transformer Room 4 17-Oct-22 20-Oct-22 A1210 FIRE ALARM TESTING 4 17-Oct-22 20-Oct-22 Gate House 4 26-Oct-22 29-Oct-22 A1220 FIRE ALARM TESTING 4 26-Oct-22 29-Oct-22 Labor Units % Complete 57.74% 57.74% 57.74% 52.17% 96.67% 100% 100% 90% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 90% 90% 61.46% 55.56% 100% 100% 100% 100% 100% 0% 0% 0% 0% 93.33% 100% 100% 80% 50% 100% 0% 50% 100% 0% 100% 100% 100% 100% 100% 0% 0% 0% 0%