Construction of intake will be deemed as an adjustable item for its small quantities and
will be carried out until completion of diversion tunnel excavation.
As diversion tunnel excavation completed, earth & rock excavation for intake will
commence immediately. Headrace tunnel excavation is executed after completion of
tunnel portal treatment. The completed headrace tunnel shall be deemed as a construction
access to carry out gate shaft and concrete placement construction. Finally concrete
placement for headrace tunnel and intake structures will be completed.
Auxilary facilities such as water/air pipe and power line for tunnel excavation. A
mobile air compressor with capacity of 20 Cum will be intalled separately at intake and
gate shaft directly to rovide air to the otilizing equipment on site.
The water pipe to joint the main water system will be laid to the intake and gate shaft
construction areas.
The power line will be laid to the tunnel floor above and extends with tunnel excavation
progress. Axial ventilator will be installed for ventilation in tunnel
The tunnel portal will be treated with anchor bolt and shotcrete. Incase the rock around
portal is loose, concrete lining will be carried out to treat the portal.