SRI VAIBHAVA SAI HOMES PVT LTD

Sr No Schedule & Scope of Work


A Structure Part
1 Site Surveying (Company's Scope)
2 Marking & Grid lines Fixing (Company' scope)
3 Excavation Work & Dressing work (Company's Scope)
4 Anti Termite Treatment before Footing
5 PCC for Footings
6 Marking for Columns
7 Footings Barbinding, Shuttering & Concrete work
8 Column Marking with Starter laying above Footings/Pedastaals
9 Columns upto Plinth Beam Bottam work
10 Back filling & Soil compaction work(Company's Scope)
11 Anti Termite Treatment Chemical Laying on Bottam of Plinth PCC
12 Plinth beam PCC & Beams Marking , Form work, Concrete work
13 Back filling & (Company's Scope)
Soil compaction work inside of Plinth Beams company scope
14 Plinth Floor PCC work
15 Columns upto Staircase Midlanding level & Staircase waist slab completion
16 Columns Upto GF Beam bottam level
17 Remainig Typical Columns & Slabs for all Floors(With includes Shuttering, Barbinding & Concrete work)
18 Cleaning and maintaining material which was shifted by contractor for construction purpose only, not for entire site
Scaffolding works
Above Terrace Slab Structure Part work
19 Staircase Headroom Columns & Slabs as per Drawing
20 Lift Head room Columns & Slabs as per Drawing
21 Water Tanks Columns upto Bottam Slab, Tank Bottam Slab, 9'' RCC Walls & Top Covered Slabs. Which is additional cost
22 Embedded Items like GI Flaunges, Sleeves fixing in Watertanks
B Super Structure Part
1 Hacking & Ceiling Plaster Work
2 Brick work Layout & Brick work with 02 No of RCC Beds which is for half brick only
3 Door Frames fixing along with Brick Work laying
4 Wall Electrical Conduits Packing with Chicken Mesh
5 Columns, Beams & Brick work Joining areas Chicken Mesh fixing work.
6 Bull Mark Laying & Internal Plaster with Spone Finish
7 Windows Edges finishing as per Template with accurate 90 deg. Angles at all four corners
8 RCC: Kitchen Platforms,Cup Boards Loft Slabs
9 Cup Boards inside RCC Planks with Finishing work
10 Cleaning & Maintain the Wooden Door Frames is Completely Contractors scope only.
11 External Plaster with 02 Coats Sponge/Smooth finish including Chicken Mesh fixing in Vertical & Horizantol at Beam & Columns junctions.
12 External Plaster Purpose wooden Scaffolding / Paranja Contractors Scope Only
13 Plumbing & Electrical Embedded items packing & Patch works
14 Toilet inside Ledge Wall Brick work & Plaster for Concealed Flush Tank (It will be Depend As per Plan)
15 Elevation Masonry works As per Drawing.
16 Flooring Touch Ups, Granite Counters Packings at Kitchen Platforms, Ledge walls & Staircase Waist Slabs Granite side Finishing work
17 Water Curing For Structure , Super Structure & Tiling Related Completely Contractor's Scope.
C Cellar Level Works
18 Septic Tanks as per Drawing
19 Water Sumps as per Drawing
20 Compound Wall : PCC, RR Masonry, Beam Laying at Plinth Level , Brick Work & 02 Coats Plaster
21 Plumbing Related Manholes, Chambers Masonry Works.
22 Security Rooms, Power Rooms, DG Beds Making & Toilet Rooms as per Drawing which is at ground floor slab
23 Transformer Yard Related Civil works As per Drawing which is extra cost
24 Main Gates Fixing Related all Civil Works
25 Compound wall Out Side Drain Brick Work & Plastering work with Cover Slabs which is extra cost
26 Planter Boxes & Kerb Walls Civil Masonry works as per Drawing.
27 Project Entrance Ramps, Staircases works As per Drawings
28 Cellar & Drive ways finishing with Parking Tiles as per Drawing. (Which would be Applicable at the time of Execution)
D Terrace Level Works
29 Parapit Wall Brick Work & Plaster
30 Staircase Head Room Civil Masonry Works
31 Lift Head room Civil Masonry Works
32 Water Tank Internal Water proof Plaster & Tank inside Waterproof Screed Concrete Works
33 Water Tank External 02 Coats Plaster
34 Terrace Floor Waterproof Screed Concrete work
35 Plumbing Pipes Related Pedastals Making & Finishing work
E Water Proof Works
1 Toilets Inside Dead Mortar Cleaning
2 Bore Packings with GP2
3 Applying of Brush Bond & Latex 100 Chemical
4 1st coat of Water proof plaster with Hanch Concrete finish
5 After Plumbing lines Brick Batters Laying with Water proof Cement Mortar
6 above Cement Screed Concrete as per Specification
F Tiling & Flooring Works
1 Toilets Ceramic Wall Dado with plaster laying upto 7 feet height along with utilities wall cladding
2 Toilets , Balconies & Utilities Floor laying with 03 mm Spacer joints with epoxy grouting
3 Flats inside 2'x2' Vetrified Laying with Paper Joints & grouting
4 Kitchen Platforms Granite Counters laying & Edge Polish as per Specification
5 Granite Cutting inside of Kitchen Platform & Edge finishing according to the SS Sink
6 Gas hole to be Provided
7 2' Height Kitchen Dado Ceramic tile Laying work as per Specification
8 Utilies, Balconies & Corridors Ledge wall Above Granite Laying & Finishing work as per Specification.
9 Staircase Treads, Risers, Mid Landing & Skirtings Laying & Finishing work as per Spefiction.
10 Corridors Area Granite / Anti Skid Tiles Laying & Finishing work as per Specification (Flooring Design with Granite Borders / Tiles As specified)
11 All Granite Edge finish with Half Round polish or unless otherwise specified
12 TV Panel Wall Tile Cladding as per Specification
G Painting Works
1 Internal Painting Works : 02 Coats of Putty, Papering , Primer & 02 Coats of Emulsion Paint.
2 External Painting Works : 02 Coats Putty or Texture Finish as per Specification & Primer with 02 Coats of Emulsion Paint.
3 Door Frames & Shutters : Applying of Wood Putty , Primer & 02 Coats of Enamul Painting
4 Grills & MS Gates Painting As applicable as per Specification.
5 Painting Related Wooden Scaffolding/Paranja contractors Scope Only
6 Painting Material & Emery or Disc Papers material supplied by Company & Remaing material like Brush , Rollers Contractors scope only.
H Electrical Works
1 Slab Pipe Laying (Conduiting)
2 Walls Grew Cutting
3 Walls Pipe Laying & Board Fixing
4 TV, Net, Telephone Pipe Laing(Ground)
5 Internal Wiring
6 Switch Board Fixing
7 Mains Running & DB Fixing
8 Flats Final Testing & Handing over
9 Panel Board fixing, Cable Connections, DG Cable Connections, Watchmen Room Connections,Motor Connection, Common Area Lightings, Gate Lite Fixing, All Complete
Electrical Works with Complete Labour including Tools. excavation for electric line company scope any excavation company scope
10 Complete Electrical Work would be Executed by According to Drawing only
I Plumbing Works
1 PVC & CPVC Concealed Internal Works
2 Toilets Internal Plumbing concealed work
3 Outside SWR & Water Line Works
4 Head Rooms & Water Tank Connections
5 Soil Lines & Below Ground SWR Lines, Common Areas work
6 CP & Sanitary Fixing Works
7 Final Handing over Works
8 All Plumbing Work would be Executed as per Drawing only excavation is under company scope
# Key Points
1 Measurement Should be considered Slab Surface area L*B (Physical Measurement ) , stair case slab and balcony
2

4 Alignment, lining, leveling of every work activity should be perfect and joining of bricks and filling of gaps should be done with utmost care and cleaning of cement mortar on
door frames, window frames etc. should be done immediately as and when noticed irrespective of waiting till the closure of the work for the day
5
Cleaning and maintaining the work place and keeping all materials in proper placement at the work site strictly at the end of day’s work should be done by the contractor
6 Cleaning & Handing over to Customer