BUILDING WORK UNIT RATES

Unit Rate (IDR)

Unit
No. Description Diameter/ Size Area Non Remote Remote Areas
Measurement

[k]=SUM ([c]:[j]) [l]=1.15x[k]

Building Work
Supply and Install Pressed Brick Wall Masonry
1 (half brick) with cement mortar plaster and 10 cm wall thick Sq. Meter 444.140 510.761
painting (2 sides)

Supply and Install Pressed Hollow Concrete


2 10 cm wall thick Sq. Meter 223.120 256.588
Masonry (Batako) without cement mortar plaster

Supply and Install Cement Mortar Plaster 1:4


3 15 mm thick Sq. Meter 96.310 110.757
with painting
Supply And Install Reinforced (wire mesh)
4 Concrete Curbing with emulsion Paint ; 20cm Meter 192.160 220.984
wide x 40cm tall
Supply and Install Wall Partition (Panel Board)
5 including wall paper with Galvanized Metal 11 cm thick Sq. Meter 381.060 438.219
frame
Supply and Install Partition/Window Glass
6 (Tempered-Rayban) - Fixed with Aluminum 5mm glass thickness Sq. Meter 1.376.620 1.583.113
frame
Supply and Install Partition/Window Glass
7 (Tempered-Rayban) - Sliding with Aluminum 5mm glass thickness Sq. Meter 1.484.590 1.707.279
frame completed with accesories.

Supply and Install Partition/Window Glass


8 5mm glass thickness Sq. Meter 1.025.720 1.179.578
(Tempered-Clear) - Fixed with Aluminum frame

Supply and Install Partition/Window Glass


9 (Tempered-Clear) - Sliding with Aluminum frame 5mm glass thickness Sq. Meter 1.133.690 1.303.744
completed with accesories.
Supply and Install Partition/Window Glass
10 5mm glass thickness Sq. Meter 1.457.600 1.676.240
(Tempered-Icy) - Fixed with Aluminum frame
Supply and Install Partition/Window Glass
11 5mm glass thickness Sq. Meter 1.565.570 1.800.406
(Tempered-Icy) - Sliding with Aluminum frame
Supply and Install Ceiling Multiplex Wooden
12 Structure, wooden trim edge, hanger and 6 mm thick Sq. Meter 137.190 157.769
accesories with paint finish
Supply and Install Ceiling Accoustic with
9 mm thick; 60cm x
13 Suspended Metal Structure, hanger wire 3,5mm Sq. Meter 188.630 216.925
60cm
and accesories
Supply and Install Ceiling Gypsum with
14 9 mm thick Sq. Meter 154.340 177.491
Galvanized Metal Frame Structure
Supply and Install Door Wooden Flush, 6mm Teak
10cm x 15cm door
15 wood frame 3x10cm, complete with wooden Sq. Meter 655.200 753.480
frame
door accesories
35mm thickness door
Supply and Install Door PVC (wood pattern) with
16 panel; 10cm x 15cm Sq. Meter 252.460 290.329
Alluminium Sill, complete with door accesories
frame door
Supply and Install Door Panel Nyatoh Oven with 35mm thickness door
17 Wooden Sill & Painting, complete with door panel; 10cm x 15cm Sq. Meter 1.542.980 1.774.427
accesories frame door
Supply and Install Wooden Door Frame (Nyatoh
18 10cm x 15cm Meter 190.540 219.121
Oven), paint finish
Supply and Install Glass Door with Aluminium
19 8mm glass thickness Sq. Meter 2.254.670 2.592.871
Frame, completed with door accesories
Supply and Install Steel Door Fire Proof with
20 Steel Sill & Painting, completed with steel door 35 mm thick Sq. Meter 2.535.470 2.915.791
accesories
21 Supply and Install Horizontal Blinds Sq. Meter 228.730 263.040
22 Supply and Install Vertical Blinds Sq. Meter 264.840 304.566
Supply and Install Granit Tile/ Homogenous Tile,
23 30cm X 30cm Sq. Meter 421.210 484.392
all color, 30 cm X 30 cm

Page 1 D:\PAK ISMANTO\Unit Rate.xlsx


BUILDING WORK UNIT RATES

Unit Rate (IDR)

Unit
No. Description Diameter/ Size Area Non Remote Remote Areas
Measurement

[k]=SUM ([c]:[j]) [l]=1.15x[k]

Supply and Install Granit Tile/ Homogenous Tile,


24 40cm X 40cm Sq. Meter 421.210 484.392
all color, 40 cm X 40 cm
Supply and Install Ceramic Wall Tile, all color,
25 20cm X 25cm Sq. Meter 368.690 423.994
20 cm x 25 cm
Supply and Install Ceramics Tile, all color, 20 cm
26 20cm X 20cm Sq. Meter 295.460 339.779
x20 cm
27 Supply and Install Acrylic Emulsion Wall Paint Sq. Meter 69.870 80.351
28 Supply and Install Acrylic Gloss Enamel Paint Sq. Meter 78.250 89.988
Supply and Install Frame Steel Structure
29 Kilogram 25.410 29.222
Zincalum (faricated light steel frame building)
Supply and Install Temporary Solid Fence,
30 Meter 343.090 394.554
corrugated galvanized steel with wooden post
Supply and Install Corrugated Steel Roof Plate
31 0.60 mm thick Sq. Meter 508.100 584.315
(Colorbond)
Supply and Install Corrugated Galvanized Steel
32 Sq. Meter 216.690 249.194
Roofing BJLS
33 Supply and Install Zincalum/Galvalum Roofing Sq. Meter 508.100 584.315
34 Supply and Install Metal Roofing (clear) Sq. Meter 397.260 456.849
35 Supply and Install Metal Roofing (glazed) Sq. Meter 409.300 470.695
36 Supply and Install Alluminum Foil Insulator Sq. Meter 72.410 83.272
37 Supply and Install Fascia Wood (List plank) 3cm x 30cm Meter 260.850 299.978
Supply and Install Roof Gutter Zincalum Color
38 0.4 mm thick Meter 127.030 146.085
Bond
Sanitary and Plumbing Works
Supply and Install Toilet Eco-washer with
39 Unit 4.963.740 5.708.301
flushing tank
40 Supply and Install Jet Washer Unit 747.230 859.315
Supply and Install Urinal - Moslem Type with
41 Unit 6.746.420 7.758.383
water flushing
42 Supply and Install Toilet Partition Sq. Meter 731.660 841.409
43 Supply and Install Urinal Partition Sq. Meter 671.320 772.018
Supply and Install Pedestal Lavatory Sink (cold
44 Unit 1.257.540 1.446.171
type)
45 Supply and Install Wall Faucet (cold type) Piece 891.340 1.025.041
46 Supply and Install Mirror, wall mounted Piece 635.120 730.388
Supply and Install Drain Pipe PVC AW complete
47 3/4" Meter 74.020 85.123
with insulation
Supply and Install Polyetylene Pipe outside or
48 2" Meter 419.180 482.057
inside wall or floor
Supply and Install Polyetylene Pipe (Hot Water)
49 3/4" Meter 157.990 181.689
outside or inside wall or floor
Supply and Install Polyetylene Pipe (Hot Water)
50 1/2" Meter 144.110 165.727
outside or inside wall or floor
Supply and Install PVC Pipe outside or inside wall
51 AW 1/2" S8 Meter 63.520 73.048
or floor, including elbow, nipple, tee
Supply and Install PVC Pipe outside or inside wall
52 AW 3/4" S8 Meter 71.520 82.248
or floor, including elbow, nipple, tee
Supply and Install PVC Pipe outside or inside wall
53 AW 1 1/2" S8 Meter 84.330 96.980
or floor, including elbow, nipple, tee
Supply and Install PVC Pipe outside or inside wall
54 AW 2" S8 Meter 107.970 124.166
or floor, including elbow, nipple, tee
Supply and Install PVC Pipe outside or inside wall
55 AW 2" S16 Meter 175.070 201.331
or floor, including elbow, nipple, tee
Supply and Install PVC Pipe outside or inside wall
56 AW 6" S8 Meter 139.730 160.690
or floor, including elbow, nipple, tee
Supply and Install PVC Pipe outside or inside wall
57 AW 8" S8 Meter 158.780 182.597
or floor, including elbow, nipple, tee
Supply and Install PVC Pipe outside or inside wall
58 AW 4" S16 Meter 114.330 131.480
or floor, including elbow, nipple, tee

Page 2 D:\PAK ISMANTO\Unit Rate.xlsx


BUILDING WORK UNIT RATES

Unit Rate (IDR)

Unit
No. Description Diameter/ Size Area Non Remote Remote Areas
Measurement

[k]=SUM ([c]:[j]) [l]=1.15x[k]

Supply and Install PVC Pipe outside or inside wall


59 AW 6" S16 Meter 251.510 289.237
or floor, including elbow, nipple, tee
Supply and Install PVC Pipe outside or inside wall
60 AW 8" S16 Meter 285.810 328.682
or floor, including elbow, nipple, tee
61 Supply and Install Clean Out 4" Piece 485.700 558.555
62 Supply and Install Floor Drain 2" Piece 496.380 570.837
63 Supply and Install Galvanized Pipe, SCH40 1" Meter 205.400 236.210
64 Supply and Install Galvanized Pipe, SCH40 1.5" Meter 224.170 257.796
65 Supply and Install Galvanized Pipe, SCH40 2" Meter 234.840 270.066
66 Supply and Install Galvanized Pipe, SCH40 4" Meter 384.290 441.934
67 Supply and Install Galvanized Pipe, SCH40 6" Meter 533.740 613.801
Fabricate and Install Pipe Tubing (pipe materials
68 3.5"-6" Meter 152.430 175.295
supplied by Company)
Electrical Works
Supply and Install Electrical Cable 2 cords, inside
67 Meter 27.380 31.487
or outside wall; NYA 4MM2
Supply and Install Electrical Cable 2 cords, inside
68 Meter 31.190 35.869
or outside wall; NYA 6MM2
Supply and Install Electrical Cable 3 cords, inside
69 Meter 36.340 41.791
or outside wall; NYA 4MM2
Supply and Install Electrical Cable 3 cords, inside
70 Meter 36.340 41.791
or outside wall; NYA 6MM2
71 Supply and Install Emergency Light Piece 1.251.970 1.439.766
72 Supply and Install Exhaust Fan, wall mounted Piece 1.115.300 1.282.595
73 Supply and Install Ceiling Fan; 120V, 60Hz Piece 1.432.990 1.647.939
74 Supply and Install Exit Light 1 face Piece 1.329.810 1.529.282
75 Supply and Install Exit Light 2 face Piece 1.948.860 2.241.189
76 Supply and Install Fluorescent Lamp; 2 x 40 W Piece 957.240 1.100.826
77 Supply and Install Hand Dryer Piece 2.040.570 2.346.656
78 Supply and Install Industrial Light; 100 W Piece 842.600 968.990
79 Supply and Install Industrial Light; 250 W Piece 957.240 1.100.826
80 Supply and Install Industrial Light; 400 W Piece 842.600 968.990
81 Supply and Install Downlight Piece 481.530 553.760
82 Supply and Install Lightning Arrester Unit 1.745.530 2.007.360
Supply and Install Load Center 1 PH, UP TO
83 Set 6.755.790 7.769.159
100A, 8 spaces
Supply and Install Load Center 1 PH, 100 AMP -
84 Set 25.486.590 29.309.579
225 A, 30 spaces
Supply and Install Load Center 3 PH, 125 UPTO
85 Set 32.339.710 37.190.667
150 AMP, 24 UP TO 30 spaces
Supply and Install Main Distribution Panel
86 Unit 175.225.420 201.509.233
(1200A; 600 VAC)
Supply and Install Main Distribution Panel (250A -
87 Unit 17.573.090 20.209.054
800A; 600 VAC)
Supply and Install Outdoor Termination Kit : to
88 Unit 481.530 553.760
24 KV, range cable : 25-70 mm2
Supply and Install Outdoor Termination Kit : to
89 Unit 481.530 553.760
24 KV, range cable : 95-240 mm2
Supply and Install Outdoor Termination Kit : to
90 Unit 361.150 415.323
24 KV, range cable : 150-300 mm2
Supply and Install Outdoor Termination Kit : 24
91 Unit 481.530 553.760
to 36 KV, range cable : 300-500 mm2
Supply and Install Panel Board, single phase, 100-
92 Unit 98.286.750 113.029.763
400 A
Supply and Install Panel Board, single phase, 400-
93 Unit 153.281.070 176.273.231
600 A
Supply and Install Panel Board, three phase, 100-
94 Unit 149.872.940 172.353.881
400 A
95 Supply and Install Photo Cell Piece 80.250 92.288

Page 3 D:\PAK ISMANTO\Unit Rate.xlsx


BUILDING WORK UNIT RATES

Unit Rate (IDR)

Unit
No. Description Diameter/ Size Area Non Remote Remote Areas
Measurement

[k]=SUM ([c]:[j]) [l]=1.15x[k]

Supply and Install Safety Switch 3 pole, 100 A -


96 Unit 1.578.840 1.815.666
150 A, 240 VAC
Supply and Install Safety Switch 2 pole, 30 A - 50
97 Unit 1.578.840 1.815.666
A, 240 VAC
Supply and Install Safety Switch and Transfer
98 Unit 1.578.840 1.815.666
Switch; Up to 100 Amp.
Supply and Install Security Lamp, Explosion
99 Piece 968.490 1.113.764
Proof, 25W-50W/120V/220V/60Hz
Supply and Install Security Lamp, Explosion
100 Piece 841.470 967.691
Proof, 70W-120W/120V/220V/60Hz
101 Supply and Install Security Light Piece 332.460 382.329
102 Supply and Install Single Switch set 162.520 186.898
103 Supply and Install Double Switch set 186.590 214.579
Supply and Install Split Air Conditioner 12700
104 Unit 6.351.170 7.303.846
BTUH
Supply and Install Split Air Conditioner
105 Unit 19.053.490 21.911.514
12700+12700+12700 BTUH
Supply and Install Split Air Conditioner 12700 +
106 Unit 12.702.330 14.607.680
18000 BTUH
Supply and Install Split Air Conditioner 18000
107 Unit 6.351.170 7.303.846
BTUH
Supply and Install Split Air Conditioner 18000 +
108 Unit 12.702.330 14.607.680
18000 BTUH
Supply and Install Automatic Ventilator (Roof
109 Unit 3.842.900 4.419.335
Vent)
110 Supply and Install 220V Outlet Unit 164.990 189.739
111 Supply and Install Stove Outlet Unit 515.880 593.262
Supply and Install Street Light complete with
112 Unit 19.838.750 22.814.563
Pole and Foundation
113 Supply and Install Telephone Outlet (Analog) Piece 204.650 235.348
114 Supply and Install Telephone Outlet (IP Phone) Piece 384.040 441.646
115 Supply and Install Threeway Switch set 504.410 580.072
Supply and Install TL Lamp, Explosion Proof;
116 Piece 389.780 448.247
2x40/36 W/120 V,60 Hz
117 Supply and Install Triple Switch set 213.080 245.042
118 Supply and Install Twist Plug Unit 429.900 494.385
119 Supply and Install Wire ground BC; 35 mm Meter 484.260 556.899
120 Supply and Install Receptacle ; 220 VAC set 144.460 166.129
Supply and Install Receptacle Explosion Proof,
121 Unit 854.490 982.664
125V/20A
Supply and Install Receptacle Explosion Proof,
122 Unit 739.850 850.828
250V/20A

123 Supply and Install Receptacle Twist Lock; 220 V Unit 435.630 500.975

124 Supply and Install Receptacle, Duplex; 110VAC Set 288.920 332.258
125 Supply and Install Pull Chain Porcelein Socket Piece 102.320 117.668
126 Supply and Install Indicator Lamp Piece 251.510 289.237
127 Supply and Install Isolator Module (IM) Piece 244.920 281.658

128 Supply and Install Fire Extinguisher; 4.5 Kg- 6 Kg Unit 957.030 1.100.585

Supply and Install Control Panel Fire Alarm


129 Piece 17.709.600 20.366.040
(CPFA)
Supply and Install Conventional Fixed Rate Heat
130 Piece 212.090 243.904
Detector
Supply and Install Conventional Photo Smoke
131 Piece 235.010 270.262
Detector
132 Supply and Install Manual Pull Station Piece 1.046.120 1.203.038
133 Supply and Install Monitor Module (MM) Piece 1.441.090 1.657.254

Page 4 D:\PAK ISMANTO\Unit Rate.xlsx


BUILDING WORK UNIT RATES

Unit Rate (IDR)

Unit
No. Description Diameter/ Size Area Non Remote Remote Areas
Measurement

[k]=SUM ([c]:[j]) [l]=1.15x[k]

134 Supply and Install Smoke Detector, Stand Alone Piece 401.240 461.426

135 Supply and Install Zone Module (ZM) Piece 315.260 362.549
Removal/Demolishing Work
Removal/Demolishing Works - Building (include
136 Sq. Meter 286.740 329.751
burial & grading)

Page 5 D:\PAK ISMANTO\Unit Rate.xlsx


EARTHWORK & CIVIL WORK UNIT RATES
Unit Rate (IDR)
No. Description Unit Measurement Area Non Remote Remote Areas
[k]=SUM ([c]:[j]) [l]=1.15x[k]
Earthworks
Earthworks Fill from Company Designated Location, Haul &
1 Cu. Meter 37.930 43.620
Compacted, Balanced Cut/Fill (with hauling distance < 0.5 KM)
Earthworks Fill from Company Designated Location, Haul &
2 Cu. Meter 91.480 105.202
Compacted (with hauling distance from 0.5 KM to 15 KM)
Earthworks Fill from Company Designated Location, Haul &
3 Cu. Meter/KM 5.320 6.118
Compacted, Additional Cost per KM Above 15 KM Hauling Distance
Earthworks Fill, Haul & Compacted, Additional Cost for Contractor
4 Cu. Meter 9.530 10.960
Provided Fill
5 Earthworks Cut/Excavation Cu. Meter 12.020 13.823
6 Earthworks Compaction Sq. Meter 2.910 3.347
7 Earthworks Clearing & Grubbing Sq. Meter 2.540 2.921
Manual Excavation, Backfill & Compaction Using Stamper (no testing
8 Cu. Meter 254.110 292.227
required)
9 Mud Pit Excavation/Construction Cu. Meter 34.480 39.652
10 Mud Pit Closing, Exclude Additional Dirt Fill Cu. Meter 29.460 33.879
11 Excavation, Back fill and Compaction for Underground Facility Cu. Meter 392.290 451.134
12 Dress-up Road & Well Pad Sq. Meter 6.860 7.889
13 Soil/Dirt Hauling, distance 0-10 KM (without compaction) Cu. Meter 53.700 61.755
14 Soil/Dirt Hauling, distance 10-15 km (without compaction) Cu. Meter 80.500 92.575
Soil/Dirt Hauling, Additional Cost per KM Above 15 KM Hauling
15 Cu. Meter/KM 5.320 6.118
Distance (without compaction)
Canal Works
16 Cleaning Silt and Weeds from Pond & Water Ways (≤ 5 M width) Cu. Meter 61.150 70.323
17 Cleaning Silt and Weeds from Pond & Water Ways (> 5 M width) Cu. Meter 116.790 134.309
18 Canal Maintenance (≤ 5 M width) Meter 79.470 91.391
19 Canal Maintenance (5-10 M width) Meter 296.900 341.435
20 Canal Maintenance (> 10 M width) Meter 395.060 454.319
21 Remove Stumps, Tress, Wooden Log and the like Cu. Meter 101.750 117.013
22 Construct New Canal (width ≤ 5 M) Cu. Meter 13.510 15.537
23 Construct New Canal (width > 5 M) Cu. Meter 13.510 15.537
Concrete Works for Off Plot
24 Supply and Install Sand Bedding Cu. Meter 266.820 306.843
25 Supply and Install Lean Concrete Cu. Meter 1.342.590 1.543.979
26 Supply and Pouring Concrete - K175 Cu. Meter 1.342.590 1.543.979
27 Supply and Pouring Concrete - K225 Cu. Meter 1.520.210 1.748.242
28 Supply and Pouring Concrete - K250 Cu. Meter 1.549.560 1.781.994
29 Supply and Pouring Concrete - K275 Cu. Meter 1.637.610 1.883.252
30 Supply and Pouring Concrete - K300 Cu. Meter 1.725.660 1.984.509
31 Supply and Pouring Concrete - K400 Cu. Meter 1.960.460 2.254.529
32 Concrete Formwork Sq. Meter 1.038.950 1.194.793
33 Supply, Fabricate and Install Concrete Reinforcement Steel Bar Kilogram 13.690 15.744
34 Install Pre Cast Concrete Box Culvert Cu. Meter 8.647.780 9.944.947
35 Supply and Install Pre Cast Concrete Box Culvert Cu. Meter 16.677.730 19.179.390
36 Install Precast Concrete Pipe Culvert size 24" diameter & above Meter 437.680 503.332
37 Install Precast Concrete Pipe Culvert size below 24" diameter Meter 437.680 503.332
38 Supply and Install Anchor Bolt Kilogram 40.750 46.863
39 Supply, Fabricate & Install Concrete Cable Marker Each 73.610 84.652
40 Supply, Fabricate & Install Concrete Cable Tile Each 254.110 292.227
41 Fabricate & Install Boundary Marker Each 127.060 146.119
42 Supply and Install Grouting Non Shrinkage Cu. Meter 9.900.300 11.385.345
Concrete Works for On Plot
43 Supply and Install Sand Bedding Cu. Meter 328.440 377.706
44 Supply and Install Lean Concrete Cu. Meter 1.342.590 1.543.979
45 Supply and Pouring Concrete - K175 Cu. Meter 1.342.590 1.543.979
46 Supply and Pouring Concrete - K225 Cu. Meter 1.520.210 1.748.242
47 Supply and Pouring Concrete - K250 Cu. Meter 1.549.560 1.781.994
48 Supply and Pouring Concrete - K275 Cu. Meter 1.637.610 1.883.252
49 Supply and Pouring Concrete - K300 Cu. Meter 1.725.660 1.984.509
50 Supply and Pouring Concrete - K400 Cu. Meter 1.960.460 2.254.529
51 Concrete Formwork Sq. Meter 1.085.660 1.248.509
52 Supply, Fabricate and Install Concrete Reinforcement Steel Bar Kilogram 13.690 15.744

Page 1 D:\PAK ISMANTO\Unit Rate.xlsx


EARTHWORK & CIVIL WORK UNIT RATES
Unit Rate (IDR)
No. Description Unit Measurement Area Non Remote Remote Areas
[k]=SUM ([c]:[j]) [l]=1.15x[k]
Structural Steel Works
Fabricate & Install Fencing - Galvanized Chain Link Standard 2.1
53 Meter 476.460 547.929
Meter Fence Height (with galvanized barbed wire)
Fabricate & Install Fencing - Galvanized Chain Link Standard 2.1
54 Meter 476.460 547.929
Meter Fence Height (without galvanized barbed wire)
Supply, Fabricate & Install Fencing - Galvanized Chain Link Standard
55 Meter 1.750.245 2.012.782
2.1 Meter Fence Height (with galvanized barbed wire)

Supply, Fabricate & Install Fencing - Galvanized Chain Link Standard


56 Meter 1.124.961 1.293.706
2.1 Meter Fence Height (without galvanized barbed wire)

Fabricate & Install Galvanized Chain Link Single Gate ≤ 4 Meter


57 Each 1.429.370 1.643.776
Width
Supply, Fabricate & Install Galvanized Chain Link Single Gate ≤ 4
58 Each 7.146.830 8.218.855
Meter Width
Fabricate & Install Galvanized Chain Link Double Gate ≤ 8 Meter
59 Each 2.858.740 3.287.551
Width
Supply, Fabricate & Install Galvanized Chain Link Double Gate ≤ 8
60 Each 14.293.660 16.437.709
Meter Width
Fabricate & Install Galvanized Chain Link Single Man Gate ≤ 1.2
61 Each 714.690 821.894
Meter Width
Supply, Fabricate & Install Galvanized Chain Link Single Man Gate ≤
62 Each 2.233.750 2.568.813
1.2 Meter Width
Fabricate & Install Galvanized Expanded Metal Standard 2.1 Meter
63 Meter 1.397.610 1.607.252
Fence Height (with galvanized barbed wire)
Fabricate & Install Galvanized Expanded Metal Standard 2.1 Meter
64 Meter 1.397.610 1.607.252
Fence Height (without galvanized barbed wire)
Supply, Fabricate & Install Galvanized Expanded Metal Standard 2.1
65 Meter 2.935.240 3.375.526
Meter Fence Height (with galvanized barbed wire)
Supply, Fabricate & Install Galvanized Expanded Metal Standard 2.1
66 Meter 2.808.190 3.229.419
Meter Fence Height (without galvanized barbed wire)
Fabricate & Install Galvanized Expanded Metal Single Gate ≤ 4 Meter
67 Each 5.590.410 6.428.972
Width
Supply, Fabricate & Install Galvanized Expanded Metal Single Gate ≤
68 Each 11.740.960 13.502.104
4 Meter Width
Fabricate & Install Galvanized Expanded Metal Double Gate ≤ 8 Meter
69 Each 11.180.820 12.857.943
Width
Supply, Fabricate & Install Galvanized Expanded Metal Double Gate ≤
70 Each 23.481.920 27.004.208
8 Meter Width
Fabricate & Install Galvanized Expanded Metal Single Man Gate ≤ 1.2
71 Each 1.677.130 1.928.700
Meter Width
Supply, Fabricate & Install Galvanized Expanded Metal Single Man
72 Each 3.522.290 4.050.634
Gate ≤ 1.2 Meter Width
73 Install Steel Pipe Culvert size ≥ 24" diameter Meter 437.680 503.332
74 Install Steel Pipe Culvert size < 24" diameter Meter 393.910 452.997
Fabricate & Install Corrugated Steel Culvert (with bolting) size ≥ 24"
75 Meter 218.840 251.666
diameter
Fabricate & Install Corrugated Steel Culvert (with bolting) size < 24"
76 Meter 196.960 226.504
diameter
77 Fabricate and Install Structural Steel Kilogram 11.120 12.788
78 Supply, Fabricate & Install Structural Steel Kilogram 30.180 34.707

79 Install Corrugated Steel Sheet Pile - U Type (size 400 x 125 x 13) mm Meter 1.058.770 1.217.586

Install Corrugated Steel Sheet Pile - U Type (size 400 x 170 x 15.5
80 Meter 1.281.120 1.473.288
mm)
Supply and Install Corrugated Prestressed Concrete Sheet Piles (CPC
81 Meter 5.148.660 5.920.959
Sheet Piles), Type W-325-A-1000
Supply and Install Corrugated Prestressed Concrete Sheet Piles (CPC
82 Meter 5.290.960 6.084.604
Sheet Piles), Type W-325-B-1000
Supply and Install Corrugated Prestressed Concrete Sheet Piles (CPC
83 Meter 5.550.160 6.382.684
Sheet Piles), Type W-350-A-1000
Supply and Install Corrugated Prestressed Concrete Sheet Piles (CPC
84 Meter 5.687.370 6.540.476
Sheet Piles), Type W-350-B-1000
85 Fabricate and Install Hot Dip Galvanized Steel Grating Kilogram 25.420 29.233
86 Supply, Fabricate and Install Hot Dip Galvanized Steel Grating Kilogram 64.820 74.543
87 Fabricate Steel Cellar Box Each 6.352.740 7.305.651
88 Supply and Install Wooden Cellar Box Each 4.444.570 5.111.256
89 Install Steel/Wooden Cellar Box Each 3.722.990 4.281.439
90 Dismantle Steel/Wooden Cellar Box Each 3.360.690 3.864.794
91 Supply and Apply Painting for Steel Structure Sq. Meter 27.140 31.211

Page 2 D:\PAK ISMANTO\Unit Rate.xlsx


EARTHWORK & CIVIL WORK UNIT RATES
Unit Rate (IDR)
No. Description Unit Measurement Area Non Remote Remote Areas
[k]=SUM ([c]:[j]) [l]=1.15x[k]
Road Improvement
92 Dirt Road Repair, Dress up and Compaction-average width 7 M Kilometer 14.768.190 16.983.419
93 Rough Shaping of Existing Road Base Sq. Meter 20.280 23.322
94 Supply and Install Compacted Agregate Class A and Class B Cu. Meter 900.240 1.035.276
95 Supply and Install Compacted Agregate Class C Cu. Meter 541.940 623.231
96 Supply and Install Compacted Sand/Filler Material Cu. Meter 442.840 509.266
97 Supply and Install Single Chip Seal Cu. Meter 1.398.110 1.607.827
98 Supply and Install Tack Coat Sq. Meter 24.800 28.520
99 Supply and Install Prime Coat Sq. Meter 22.870 26.301
100 Supply and Install Dust Stone Cu. Meter 731.840 841.616
101 Supply and Install Rock Base Course Cu. Meter 508.220 584.453
102 Supply Cement for Road Work Stabilization Tonne 2.286.990 2.630.039
103 Apply Soil Cement Stabilization Cu. Meter 320.400 368.460
104 Supply and Install Sand Course Cu. Meter 731.840 841.616
105 Supply and Install Grader Placed Cold Mix Cu. Meter 6.289.210 7.232.592
106 Supply and Install CSS 1 Stabilization Cu. Meter 1.106.320 1.272.268
107 Supply and Install Hot Mix - ATB Cu. Meter 6.085.930 6.998.820
108 Supply and Install Asphalt Emulsion CMS-2 Cu. Meter 9.147.940 10.520.131
109 Supply and Install Asphalt Emulsion CSS-1 Cu. Meter 18.402.410 21.162.772
110 Supply and Install Non-Standard Stabilization, Lime Stabilizer Tonne 5.393.330 6.202.330
111 Supply and Install Non-Standard Stabilization, Polymer Stabilizer Tonne 16.713.900 19.220.985
112 Supply and Install Pavement Marking Sq. Meter 258.130 296.850
113 Supply and Install Sand Bag (Sand mixed with cement) Each 49.720 57.178
114 Supply and Install Soil Cement Bag (Soil mixed with cement) Each 64.150 73.773
115 Supply and Install Gabion Boxes Cu. Meter 1.168.910 1.344.247
116 Supply, Fabricate and Install Traffic Sign, Single Post Pipe Each 2.858.740 3.287.551
117 Fabricate and Install Traffic Sign, Single Post Pipe Each 1.079.310 1.241.207
118 Supply and Install Steel Guard Rails Meter 1.270.550 1.461.133
Environmental Works
Environmental Works - Oil Contaminated Waste Hauling, Hauling
119 Cu. Meter 76.300 87.745
distance 0-10 km (using KLH/BLH's certified truck)
Environmental Works - Oil Contaminated Waste Hauling, Hauling
120 Cu. Meter 91.310 105.007
distance 10-15 km (using KLH/BLH's certified truck)
Environmental Works - Oil Contaminated Waste Hauling, Additional
121 Cost per KM Above 15 KM Hauling Distance (using KLH/BLH's certified Cu. Meter/KM 6.070 6.981
truck)
122 Excavation of Unsuitable Soil Material Cu. Meter 12.780 14.697
Miscellaneous Works
123 Install Conductor Pipe 24" Point 3.494.010 4.018.112
124 Supply and Install Geo-Textile Sq. Meter 34.430 39.595
125 Install HDPE Geomembrane Sq. Meter 12.710 14.617
Install and Dismantle Crane Mats (Wooden or Concrete or Steel or
126 Sq. Meter 379.730 436.690
Other) Foundation
127 Rental, Install and Dismantle Vinyl Matting Board Sq. Meter/Day 1.270.550 1.461.133
128 Rental, Install and Dismantle Wooden Matting Board Sq. Meter/Day 1.270.550 1.461.133
129 Rental, Install and Dismantle Concrete Matting Board Sq. Meter/Day 1.877.200 2.158.780
130 Regreening for Work related with Surface Facility Sq. Meter 34.300 39.445
131 Supply and Install Heavy Duty Paving Block Sq. Meter 173.800 199.870
132 Install Rig Substructure Foundation Each 10.391.290 11.949.984
133 Dismantle Rig Substructure Foundation Each 5.195.650 5.974.998
134 Install Geocomposite Drainage Layer, thickness 5mm Sq. Meter 28.350 32.603
135 Supply and Install Poly Ethylene Liner Sq. Meter 13.230 15.215
136 Monitoring Well diameter 6" - 8" Meter Depth 2.704.100 3.109.715
Removal/Demolish Works
137 Removal/Demolish Steel Structure Kilogram 10.170 11.696
138 Removal/Demolish Unreinforced concrete Cu. Meter 508.220 584.453
139 Removal/Demolish Reinforced concrete Cu. Meter 635.280 730.572
140 Removal/Demolish Fencing Meter 143.630 165.175
141 Removal/Demolish/Patching Asphalt Concrete (AC) Cu. Meter 2.512.410 2.889.272
Screw Pile
Supply, Fabricate and Install Helix/Screw Pile, new pipe max 8 m
142 Each 8.985.310 10.333.107
length (pipe by Company)
Fabricate and Install Helix/Screw Pile, extention up to 4-5 meter per
143 Each 2.941.320 3.382.518
pile
Install Helix/Screw Pile, Reusable max 8 meter pipe length (screw
144 Each 5.483.690 6.306.244
up, mobilization & screw down)

Page 3 D:\PAK ISMANTO\Unit Rate.xlsx


MECHANICAL UNIT RATES
Unit Rate (IDR)
Unit
No. Description Area Non Remote Remote Areas
Measurement
[k]=SUM ([c]:[j]) [l]=1.15x[k]
Coating & Painting Work for Mechanical Equipment
1 Supply and Apply Coating for Mechanical Equipment, External Coating Sq.Ft 191.670 220.421
Supply and Apply Painting for Mechanical Equipment, External Painting,
2 Sq.Ft 113.870 130.951
without abrasive blasting

Page 1 D:\PAK ISMANTO\Unit Rate - Copy.xlsx