ESTIMATION FOR PROPOSED BUILDING

TYPE OF STRUCTURE- FULLY FRAMED (RESIDENTIAL)

1. AREA OF GROUND FLOOR BUILDING : 1300 SFT

RATE/SFT : RS. 2250.00

AMOUNT : RS. 29,25,000

2. UG SEPTIC TANK : 6000 LTRS

RATE/LT : RS. 15.00

AMOUNT : RS.90,000

3. UG SUMP : 4000 LTRS

RATE/LT : RS. 15.00

AMOUNT : RS.60,000

TOTAL AMOUNT : Rs.30,75,000

1
WORK SPECIFICATION FOR FINALIZED PLAN
1. Column Size : 1’0” x 0’9”, 0’9” x 0’9”
2. Plinth Beam : 0’9” x 0’9”, 0’9” x 1’0”, 0’9” x 1’3”
3. Lintel Beam : 0’9” x 0’6”, 0’9” x 0’9”
4. Roof Slab : 0’4 ½” Thickness
5. Concrete Mix : M20 Grade
6. Mortar : 1:5 (Brick Work), 1:4 (Plaster)
7. Reinforcement : As Per Reinforced Design
(ABOVE MENTIONED DETAILS MAY CHANGE DUE TO SITE CONDITIONS)
8. Basement Height : 4’0” From Existing Ground Level
9. Ceiling Height : 10’2” From Flooring
10.Loft : Any One length Will Be Given
11.Low Roof : One unit per Floor
12.Shelves : 4’0” x 7’0” per Bed & Kitchen (Kadapa)
13.Flooring : Vitrified Tiles ( 4’x 2’)(2’x2’)
14.Kitchen Table Top : Granite with SS Sink
15.Kitchen and Toilet Wall : Glazzed Tiles upto Lintel Height
16.Wood Front Door : Maindoor Teak Wood Frame with
Teak Door
17.Wood Windows : Teak Wood Frame with Shutter
18.Inner Door : Frame – Teak Wood
Shutter – Readymade Flush Shutter
19.Toilet Door : PVC Door
20.Parapet Wall : 3’ Height and 4.5” Brick wall
21.Painting : For Exterior - 1 coat Primer, 2 Coat Emulsion
Asian Paints – ACE Advanced & APEX
For Interior - 2 coat Putty, 1 coat Primer,
2 coat Emulsion (Tractor Shyne & Apcolite)
Joinery: One coat Primer and Two Coat
Enamel (Asian Paints)
22.Electrical : Basic Points & AC Points For Bedrooms
2
23. Bath Fittings : CP Fittings & EWC Closet
24.Plumbing : PVC- AvonPlast, UPVC – Trubore
CPVC- Finolex
25.Terrace Finish : Plaster & Water Proofing With Damp Proof
26. Hardware : Mortice Lock For Bedrooms, Bullet Lock
For Main Door & I-Max Hinges for Windows

EXCLUDING OF THIS SPECIFICATION


1. Septic Tank, UG Sump & Over Head tanks
2. Fan and Light Fittings
3. Inner Stairs
4. Elevation Work (Architect Level)
5. Outer Flooring
6. Compound Wall and Gates
7. Demolition
8. Pile Foundation
9. Bore well & EB
10.Approval & Blue Print
11.Interior Works (False Ceiling, Wood & PVC Works)
12.Old Building Repair Works
➢ Above works will be claimed from Client

3
MATERIALS TO BE USED
1. Sand – M-Sand & P-Sand
2. Brick – Chamber brick / Fly-Ash Brick (for Basement)
3. Cement – Chettinad / Ramco Super Plast / UltraTech
4. Steel – Fe 550D TMT Bars PULKIT
5. Window Grill – 12mm Square Rod (Ladder Design)
6. Window & Door – Teak Wood / UPVC (Client’s Choice)
7. Maindoor – Teak Shutter
8. Bedroom Doors – Readymade Skin Doors
9. Hand Rail – Stainless Steel Tubes (ISI/ISO)- JINDAL Brand
10.Chemicals – Dr. Fixit, Bostik, Building Doctor
11.Pest Protector – Terminator (For Basement & Wooden Joineries)
12.Terrace – Professional Water Proofing (Asian Paints)
13. Tiles – KAG, Millenium (55/Sft)
14. Paints – Asian Paints
15. Plumbing – Avon Plast, Aashirvad, Trubore, Finolex
16. Electrical – Finolex Pipes & GM Metal Concealed Box
17.Wires – RR / Kundan
18.Switches – Legrand / GM / Lisha (Modular)
19.MCB – Legrand, Crompton
20. Closet – Parryware / Jaquar
21.Bath Fitting – Johnson Pedder / Jaquar (Modular)
22. Kitchen Table – Table Top Granite
23. Sink – Prayag (Stainless Steel)
24.Lock (Main door) – Godrej / Europa
25.Lock (Bedrooms) – Millarco Mortice Lock
26.Window Lock – L Shaped Tower bolt Lock
27.Window Glass – White Pin-Head Glass Or Clear Glass
28. Screw And Bolts – ISI/ISO Branded
29.Stainless Steel – Jindal 304 Grade

4
ASSUMED MATERIAL RATE FOR THIS SPECIFICATION on (24/2/23)
1. Sand : Rs. 4000 /Unit
2. Cement : Rs. 410 / Bag
3. ¾ Metal : Rs. 30 / Cft
4. Steel : Rs. 75 / Kg
5. Wires : Rs. 1200/Box (1 sq.mm Coil)
6. Switches : Rs. 20/No
7. PVC Pipes : Rs. 19 /kg
8. Brick : Rs. 8.50 / No
9. Wall Tiles : Rs. 40 / Sft
10.Floor Tile : Rs. 55 / Sft
11.Granite : Rs. 130/ sft

• If there is any increase in material cost more than 5%, excess cost
will be claimed from the party.
• Any local taxes and other taxes like GST, which are liable are of
client’s scope.

For MANCHESTER CONSTRUCTIONS