Shed for storing E&M Items at site - L&T is yet to take up the Shed construction (which
was promised to be ready by 05 Oct 2021).
Storage plan - Detailed storage & preservation plan for
Electrical/Electronic items & Instrumentation items,
mechanical items to be submitted.
Finalization & Procurement of long - Hauling in-winch, Capstan, Penstock, Fenders &
lead items Fairleads vendor not yet finalized (most of these
items lead time is about 8 to 9 months after
conformation of PO). Due to this delay, Electrical
load calculation and other deliverables are pending
and on hold. Finalization to be expedited.
- BG LETTERS
HT Switchgear- Finalization of Vendor
- Contractor informed that first set of Documents can
be provided by 06 June 2021
DSU/SSU panel- Delay in Finalization of - Engineer Approved Harold for supply of only DSU
Vendor panels.
- Engineer commented on DSC panel sent on 12 th
March 2021.