For MNRE:-
EPC will ready the Drawings and required Bill of Material and approach to MNRE.
For submitting the Application for BOM online, all the Project Developers/ Agencies
shall follow “Guidelines for online submission of Total Bill of Material & Application”
available on MNRE‟s website. The URL address for online registration is
http://164.100.194.45/ccms for obtaining Login ID & Password. submit the hard
copy thereof in duplicate, after duly signed in ink, and also certified by the
empanelled Chartered Engineer, direct to the MNRE along with the copy of purchase
order of the item for which exemption certificate is sought.
After submission on online hardcopy and all below documents will submitting to
MNRE throe NEDCAP for verifying the Qty with reference to Plant capacity and
Drawings. The State Nodal Agency shall forward the above documents application
and Total Bill of Material to MNRE after verification.
CCDC, EDEC or both, as the case may be, shall be issued by MNRE for each Purchase
Order. The proposal for CCDC/EDEC, along with copy of Purchase Order, will be
submitted to MNRE through empanelled Chartered Engineer who shall certify the
quantity.
EPC will prepare the All Drawing up to plant side Transformers.
Plant Layout
Plant material storage area
SLD
Structural design
Foundation Coordinates
Structural DC wiring
Inverter room Design and location
DC cable Length
AC cable length
Plant earth pit layout
Power distribution Network
Switchyard Line drawing
Communication layout
Communications details.
For CEIG :-
Power Distribution Network
Substation Layout and SLD
Plant SLD and layout
Solar Plant General Procedure
Electrical /Mechanical Drawings:-
Mani SLD
Structural wiring Drawing
String DC cable length
Combiner box drawing
Plant lighting system
Power distribution for lighting poles
Plant lighting arrester arrangement
HT Panel Drawing
DC cable route
AC Cable Route
Ferrule Positive and negative harness drawings
Structure Design and Part drawings
Assemble Drawings
Electrical equipment enclose drawings
Trench layout and cross sectional
GI flat and earth pits and cross section drawing
Inverter placement layout
Stage 1:-
1. Submission of Application & ‘Total Bill of Material’ to SNA, after duly certified by the
Chartered Engineer; and then SNA shall forward it to MNRE, at least one month
prior to seeking CCDC/EDEC
2. Scrutiny and acceptance of the Application & ‘Total Bill of Material’ by the
designated officer in MNRE Or Return to SNA in case of inconsistency found out
after above scrutiny
3. Convey acceptance or return, as the case may be, of the Application & ‘Total Bill of
Material’ to the Project Developer with copy to SNA.
Stage 2:-
1. Submission of (in case of EDEC),or (in case of CCDC) or both (in case of applying for
issue of both EDEC & CCDC) after duly filled in, Part-A i.e. Project Authority’s
certificate, along with Purchase Order or Orders and specifications of Equipments
duly certified by the Chartered Engineer; to MNRE for issue of CCDC/EDEC.
Solar Plant General Procedure
2. Issue of EDEC or CCDC addressed to the concerned Asstt./Dy.Commissioner of
Central Excise or Customs, as the case may be, for availing of duty benefit.
CEIG Approval:-
EPC will Submit the initially Plant layout, SLD, Distribution network, Power evocation line ,
power injected point (GI drawing ) and Earthling Drawings, to get the initially approval.
After completion of plant excavation EPC apply the finial CEIG approval. in the time CEIG
will visit the site to check the plant and power injected point. If any punch points find out
EPC will rectified and get the final approval.