ENE51-SLDC0GROP(MISC)/66/2021-CE-01-KRS
ORDER
1. After careful examination, the APSLDC hereby accords approval for the following
process flow for charging of new intra state transmission lines (132 KV & 220KV) and
Sub Station elements in 132 KV and 220KV substations (Appended to these orders)
2. The Chief Engineers /Zones seeking permission for charging of new intra state
Transmission lines (132 kV and 220kV) and Sub Station elements of 132 kV and
220kV shall apply in the appended forms to Chief Engineer/APSLDC.
3. The Chief Engineer/APSLDC will issue certificate of concurrence for charging of
proposed elements of Substations and Intra state transmission lines.
File No.ENE51-SLDC0GROP(MISC)/66/2021-CE-01-KRS
4. These orders are available on APSLDC website and can be accessed at the address
http:www.sldc.aptransco.co.in.
(BY ORDER AND IN THE NAME OF CHAIRMAN AND MANAGING DIRECTOR
APTRANSCO)
Sd/-
To
All Functional heads / APTRANSCO/Vidyut Soudha / Vijayawada.
The Chief Engineer / APSLDC /Vidyut Soudha /Vijayawada.
The Chief Engineers /Zones /Kadapa / Vijayawada / Visakhapatnam.
All Superintending Engineers In Kadapa, Vijayawada, Visakhapatnam Zones.
Copy to
PS to the Chairman & Managing Director /APTRANSCO/Vijayawada.
PS to the Joint Managing Director (Vigilance &Security) /APTRANSCO/Vijayawada.
PS to the Joint Managing Director /APTRANSCO/Vijayawada.
PS to the Director (Finance) /APTRANSCO/Vijayawada.
PS to the Director (Grid & Transmission Management)/APTRANSCO/Vijayawada.
8
5653856/2022/CE-01-KRS-VJWD
FORM - TL1
APPLICATION FOR COMMISSIONING OF LINE
(To be furnished by CE/Zone)
13. Voice communication with SLDC control center from both ends tested & found to be in order
15. Protection System provided as per APTRANSCO Norms, Tested and found in order
I hereby certify that all the statutory pre-commissioning tests are conducted as per standards and
the test results are found to be in order. The proposed line is fit for charging.
Date:_______________
9
5653856/2022/CE-01-KRS-VJWD
FORM - TL2
SCADA COMMISSIONING CHECK LIST
SCADA .
Voice communication with SLDC control center established, Tested & Found to be in order
Date:_____________
FORM – TL3
COMPLIANCE CHECK LIST
COMPLIANCE .
Date:_____________
10
5653856/2022/CE-01-KRS-VJWD
FORM – TL4
CERTIFICATE OF CONCURRENCE
FOR CHARGING OF TRANSMISSION LINE
(To be issued by CE/SLDC)
Charging mandates: .
.
The concurrence accorded is purely technical, subject to the following conditions.
1) The Chief Engineer/Zone/______ shall arrange to maintain uninterrupted transfer of SCADA data to
SLDC control center.
2) The Chief Engineer/Zone/______ shall follow all the mandatory procedures during charging the
element.
CHIEF ENGINEER
APSLDC
To
The Chief Engineer/Zone/______
S No KV From SS To SS Ckt No
10. Voice communication with SLDC control center established, Tested & Found to be in order
13. Protection System provided as per APTRANSCO Norms, Tested and found in order
I hereby certify that all the statutory pre-commissioning tests are conducted as per standards and
the test results are found to be in order. The proposed element is fit for charging.
Date:_______________
Voice communication with SLDC control center established, Tested & Found to be in order
FORM – SS3
COMPLIANCE CHECK LIST
COMPLIANCE .
Grid SS Name:
Location of SS:
Voltage level:
Charging mandates: .
.
The concurrence accorded is purely technical, subject to the following conditions.
1) The Chief Engineer/Zone/______ shall arrange to maintain uninterrupted transfer of SCADA data to
SLDC control center.
2) The Chief Engineer/Zone/______ shall follow all the mandatory procedures during charging the
element.
CHIEF ENGINEER
APSLDC
To
The Chief Engineer/Zone/______
Copy to: