File No.

ENE51-SLDC0GROP(MISC)/66/2021-CE-01-KRS

ANDHRA PRADESH STATE LOAD DESPATCH CENTRE


VIDYUT SOUDHA : VIJAYAWADA
APSLDC - Vijayawada – Forms for charging of new Intra state transmission lines
(132 kV and 220kV) and Sub Station elements of 132 kV and 220kV sub stations
-Orders issued.
_____________________________________________________________

T.O.O (CE-SLDC) Ms No : 2795 dated : 26.04.2023


Read the following:

ORDER
1. After careful examination, the APSLDC hereby accords approval for the following
process flow for charging of new intra state transmission lines (132 KV & 220KV) and
Sub Station elements in 132 KV and 220KV substations (Appended to these orders)

Action Action by Form Time Lines


Submit application for Chief Form TL 1 7 working days
charging of intra state Engineer/ Zone Application for prior to the
transmission Lines of 132 kV charging of intra proposed date of
or 220kV. state transmission charging
Lines.
Submit application for Chief Engineer/ Form SS1 7 working days
charging of Sub Station Zone Application for prior to the
elements of 132 kV /220kV charging of Sub proposed date of
substations. Station elements. charging
SCADA commissioning Executive Form - SS2 for 2 working days
checklist Engineer /SCADA Substation and Form
/APSLDC -L2 for line
Verification of compliance Executive Engineer/ Form -TL3 for intra 3 Working days
checklist for charging of intra System Studies / state Transmission
state transmission Lines and APSLDC Lines.
Substation elements.
Form -SS 3 for Sub
Station elements.
Issue of certificate of Chief Engineer/ Form -TL4 for intra 2 working days
concurrence for charging of APSLDC state Transmission
intra state transmission Lines Lines
and Substation elements.
Form -SS 4 for Sub
Station elements.

2. The Chief Engineers /Zones seeking permission for charging of new intra state
Transmission lines (132 kV and 220kV) and Sub Station elements of 132 kV and
220kV shall apply in the appended forms to Chief Engineer/APSLDC.
3. The Chief Engineer/APSLDC will issue certificate of concurrence for charging of
proposed elements of Substations and Intra state transmission lines.
File No.ENE51-SLDC0GROP(MISC)/66/2021-CE-01-KRS

4. These orders are available on APSLDC website and can be accessed at the address
http:www.sldc.aptransco.co.in.
(BY ORDER AND IN THE NAME OF CHAIRMAN AND MANAGING DIRECTOR
APTRANSCO)

Sd/-

for CHAIRMAN AND MANAGING DIRECTOR


APTRANSCO

To
All Functional heads / APTRANSCO/Vidyut Soudha / Vijayawada.
The Chief Engineer / APSLDC /Vidyut Soudha /Vijayawada.
The Chief Engineers /Zones /Kadapa / Vijayawada / Visakhapatnam.
All Superintending Engineers In Kadapa, Vijayawada, Visakhapatnam Zones.

Copy to
PS to the Chairman & Managing Director /APTRANSCO/Vijayawada.
PS to the Joint Managing Director (Vigilance &Security) /APTRANSCO/Vijayawada.
PS to the Joint Managing Director /APTRANSCO/Vijayawada.
PS to the Director (Finance) /APTRANSCO/Vijayawada.
PS to the Director (Grid & Transmission Management)/APTRANSCO/Vijayawada.
8
5653856/2022/CE-01-KRS-VJWD
FORM - TL1
APPLICATION FOR COMMISSIONING OF LINE
(To be furnished by CE/Zone)

1. Name of the Line proposed for charging:

2. SS: From substation:

To Substation/ Bulk load:

3. Voltage Level (KV): 5. Line Length KM): 6.Tower config (DC/SC/MC):

7. Tower Type : 8. Conductor type & Code:

9. Conductor Size: 10. Sub conductors:

11. PTCC Clearance obtained and attached

12. SCADA system commissioned SCADA Validated and found to be in order

13. Voice communication with SLDC control center from both ends tested & found to be in order

14. Statutory inspection completed Statutory Inspection remarks attended

15. Protection System provided as per APTRANSCO Norms, Tested and found in order

16. Details of adopted protection system is attached

17. Energy meter details attached

18. Proposed date of charging:

I hereby certify that all the statutory pre-commissioning tests are conducted as per standards and
the test results are found to be in order. The proposed line is fit for charging.

Signature of Chief Engineer/Zone

Date:_______________
9
5653856/2022/CE-01-KRS-VJWD
FORM - TL2
SCADA COMMISSIONING CHECK LIST
SCADA .

SCADA data Validated and found to be in order

Voice communication with SLDC control center established, Tested & Found to be in order

Signatures: DEE /SCADA DEE/Tele/SCADA EE/SCADA

Date:_____________

FORM – TL3
COMPLIANCE CHECK LIST
COMPLIANCE .

SCADA compliance received from SCADA wing

PTCC approval furnished by CE/Zone

Data received in full shape from CE/Zone in Form TL-1

Fitness of the proposed element for charging is certified by CE/Zone

Concurrence can be issued for charging of the proposed element

Signatures: DEE/SS EE/SS SE/Grid operation

Date:_____________
10
5653856/2022/CE-01-KRS-VJWD
FORM – TL4
CERTIFICATE OF CONCURRENCE
FOR CHARGING OF TRANSMISSION LINE
(To be issued by CE/SLDC)

Concurrence certificate No:____________ Date:_______________

Concurred line details:

Proposed date of charging:

Charging mandates: .
.
The concurrence accorded is purely technical, subject to the following conditions.

1) The Chief Engineer/Zone/______ shall arrange to maintain uninterrupted transfer of SCADA data to
SLDC control center.
2) The Chief Engineer/Zone/______ shall follow all the mandatory procedures during charging the
element.

CHIEF ENGINEER
APSLDC

To
The Chief Engineer/Zone/______

Copy to the Executive Engineer/Shift/SLDC


11
5653870/2022/CE-01-KRS-VJWD
FORM - SS1
APPLICATION FOR COMMISSIONING OF SUBSTATION ELEMENTS
(To be furnished by CE/Zone)

1. Name of the Substation :

2. Voltage Level (KV) : 400 KV / 220 KV / 132 KV / 33 KV

3. C & R panels type: SAS Conventional

4. Switchgear type: AIS Hybrid GIS

5. GPS coordinates of Sub Station Lat: Long:


(In decimal format)

6. Other end Substations :

7. Lines from proposed SS to other end SS

S No KV From SS To SS Ckt No

8. Approved Single Line Diagram attached

9. SCADA Commissioned SCADA validated and found to be in order

10. Voice communication with SLDC control center established, Tested & Found to be in order

11. Statutory Inspection completed Statutory Inspection remarks attended

12. Elements proposed for charging:

Sl. no Element Description Rated Capacity (MVA) Voltage rating(KV)

Name plate particulars of proposed elements attached

13. Protection System provided as per APTRANSCO Norms, Tested and found in order

14. Details of adopted protection system is attached

15. Energy meter details attached


12
5653870/2022/CE-01-KRS-VJWD

16. Proposed date of charging:

I hereby certify that all the statutory pre-commissioning tests are conducted as per standards and
the test results are found to be in order. The proposed element is fit for charging.

Date:_______________

Signature of Chief Engineer/Zone


13
5653870/2022/CE-01-KRS-VJWD
FORM -SS2
SCADA COMMISSIONING CHECK LIST
SCADA .

SCADA data Validated and found to be in order

Voice communication with SLDC control center established, Tested & Found to be in order

Signatures DEE /SCADA DEE/Tele/SCADA EE/SCADA


with Date

FORM – SS3
COMPLIANCE CHECK LIST
COMPLIANCE .

SCADA compliance received from SCADA wing

Data received in full shape from CE/Zone in form SS-1

Fitness of the proposed element for charging is certified by CE/Zone

Concurrence can be issued for charging of the proposed element

Signatures: DEE/SS EE/SS SE/Grid operation


14
5653870/2022/CE-01-KRS-VJWD
FORM – SS4
CERTIFICATE OF CONCURRENCE
FOR CHARGING OF SUBSTATION ELEMENTS
(To be issued by CE/SLDC)

Concurrence certificate No:____________ Date:_______________

Grid SS Name:

Location of SS:

Voltage level:

Concurred Element details:

Rated Proposed date of


Sl. no Element Description Capacity Voltage rating(KV) Charging
(MVA)

Charging mandates: .
.
The concurrence accorded is purely technical, subject to the following conditions.

1) The Chief Engineer/Zone/______ shall arrange to maintain uninterrupted transfer of SCADA data to
SLDC control center.
2) The Chief Engineer/Zone/______ shall follow all the mandatory procedures during charging the
element.

CHIEF ENGINEER
APSLDC

To
The Chief Engineer/Zone/______

Copy to:

The Executive Engineer/Shift/SLDC