Area Pending Jobs Remarks / Action takem

Train 1 , MAC A and MAC A HT breaker, and exciter  LINDE intimated NSL to procure 49 defective
its electrical panne; panel not ready. electrical items. The same has been proposed to
be procured directly from market by NSL., 33
items are required as minima spares. NSL
ordered 28 items & received 6 items at site on
25/07/23 and for other 22 items yet to received .
For rest 4 items ordered to be placed
 After receiving all 33 items & Exciter panel
vendor’s ( BHEL) service person at site . This
resources required after commissioning of BAC –
Already proposal processed , PO placed on BHEL
- 25/07/23

Commissioning/ Only 3 Nos of process engineers are For O& M contract , M/s MECON floated tender and the
Operation at site for managing the 24 hours same Open on 21/07/23 , under process
Manpower operation of ASU-2. The team is also
involved in commissioning activities
resulting unattended job creating
delay. Though Linde agreed to
depute dedicated O&M team as per
settlement MOM in the month,
April, 2023, no action till now.
Readiness of Erection of cylinder It includes Civil work for cylinder cleaning and testing
Cylinder Filling testing/painting facilities are machine , drawing already made by Linde and will be
System u/p. Continuous follow up with sent MECON for approval ,
Linde
Refurbishment of M/s Linde is in contact with the Required refurbishment of all Argon pumps and cylinder
Cylinder Filling vendor M/s Indian Compressors filling pumps. Follow up with LINDE site manager on
Pumps and Spare Ltd. To be expedited by Linde. regular basis
turbine OEM has confirmed that
required spare parts are
dispatched Via courier and it is
in transit .

CCOE License of Application submitted on As per instruction with GM ( Met ) the file handed over
Argon Storage 16.06.2023 on PESO website. to Mr.Rathod ( Kirdual ) for needed support .After
tanks and Cylinder After scrutiny, a physical getting CCOE license Argon production can be taken to
Filling Station inspection done by Linde storage and once Argon pumps in order , Argon can be
consultant officials on supplied to SMS .
24/07/23 From the Site on regular basis touch with LINDE’s
consultant
Gaseous Oxygen For PRS # 1 A&B ,2 Safety Regular follow up with LINDE site Manager to
PRS sysem valve’s copper vent to be mobilizeresources on priority basis
provided

Analyser N2 ppm in Argon The PO to the OEM (Servomex) of the analyser is


already placed. The party has dispatched the spares on
21-07-23 and it is in transit.