SL. SL. NO. OF Online System DESCRIPTION OF DEFECT/ BHEL REMARKS WITH STATUS
NO. ORIGINAL LIST Reference No PENDING WORK
1 41 SGDG160 HFO System Commissioning Point may be considered closed as front not provided by WBPDCL.
- A) HFO Pumps.// B) HFO HFO awaited from WBPDCL. System was made ready by BHEL long back.
Headers// C) HFO Strainers. Applied to WBPDCL for closing the point as WBPDCL not procuring HFO till date .
2 52 SGDG163 HFO System. Point may be considered closed as front not provided by WBPDCL.
Repeat of Point SL NO . 41 OF ORIGINAL AS ABOVE.
Rub back, House Load Considering no front availability by WBPDCL till 31.05.2020 , the point may be considered closed.
1 27 Operation are yet to be Unit 3 demonstartion completed long back. WBPDCL permission awaited for unit 4 .
demonstrated in Unit #4.
1.Establishment of OPC
Communication between
2 28
DCS and some BOP PLC 1. DM Plant OPC connectivity could not be established due to problems reagarding PLC in DM Plant end
systems is pending which is under L&T's scope during EDN HMI Enginner's visit.
2. Communication with AHP, ETP is still pending as front is not given till date from WBPDCL end.
Considering no front availability by WBPDCL till 31.05.2020 , the point may be considered closed.
SL. NO. OF
SL. ORIGINAL Online System DESCRIPTION OF DEFECT/
NO. LIST Reference No PENDING WORK
Testing of two nos. repaired
busbar differential relays of
400 Kv busbar differential As per TBG, Regarding faulty matl/contact of card , matter is taken with Alsthom.
Material awaited .As per MOM dt 07.03.2020 with WBPDCL shutdown required on
1 17 SGDG203 protection and receipt iof the said card which is yet to come to site. Expected completion
commissioning of 400 Kv 31.01.2021
BusBar differential
protection (Make- Alstom).