ISSUES/PROBLEMS AT R&M OBRA SITE

S.No. Units Party name Issues/problems

Unit 7 TG & Boiler M/s Alpha power engineering services Regarding settlement of extra work claim
of boiler with UPRVUNL
Unit # 13 Boiler M/s Arun Constructions Regarding material reconciliation at site
for contract closing.

Unit # 13 Boiler BHEL Ranipet supply of D11 actuator


Unit # 13 ESP M/s UPPL Regarding material reconciliation at site
for contract closing.

1 Unit #10 & 11 TG and it's Auxiliaries M/s S.N. Singh Contract closing

2 Unit #10 & 11 M/s M.S. Construction Pvt.Ltd. Contract closing

5 Unit #12 M/s Alpha power engineering services PG test

6 Contract closing
7 Unit #13 M/s Brother engineering erectors limited Full load

8 PG test

9 Contract closing

10 AOP Pressure issue of BFP #13 C


11 Unit #13 BHEL-HWR Cost debit acceptance of an amount of Rs.
58.0 Lacs, Rs 4.2 Lacs, Rs.9.75 Lacs & Rs.44.0
Lacs for the previous executed turbine works
at R&M TG work in Unit #13. Total amount of
Rs. 1.16 Crore

Unit #13 BHEL-HWR Balancing weight pending from BHEL-HWR


side

12 Unit #13 BHEL-HWR Unused Coupling bolts & balancing weights


left with site
13 BOP Package BOP- COOLING TOWER M/S SCT CT fan blade (01 nos.) is to be replaced by
of Unit #9 to M/s Unique. order has been placed waiting
#13 for supply of new CT fans. EDC 30.10.2022.
contract closing

14 BOP- MISC CIVIL M/S DEEN DAYAL MS liner replacement of wagon tippler no. 1
&2

15 BOP- MECHANICAL M/S SATNAM PG test & commissioning

17 BOP-COMPRESSOR M/S INDIA ENGINEERING WIP. Erection work of 4th no. receiver is
MECH under progress.
18 0.4 kV swgr M/s Siemens Replacement of isolator, CVT & CHP MCC
and contract closing

19 6.6 kV swgr M/s ABB contract closing

Overhauling of Old M/s Mechiniks Vendor is not responding


compressors

20 WTP M/s Clear Water PG Test & contract closing


MM issue MM Related issue M/s Navjeevan steels Disposal of MS collecting electrodes balance
15 MT

MM issue MM Related issue BHEL SSBG Regarding diversion of surplus materials of


Main R&M package

Insurance Insurance related issue M/s NIC Regarding settlement of claim against fire
related accident of unit no. 12 & 13

21 C&I Package of Mill - MDV M/s ASW Projects Pvt Ltd Commissioning of Mill Discharge Valve
Unit-13

Sox Analyzer M/s ASW Projects Pvt Ltd Commissioning of Sox system

APRDS Pressure M/s ASW Projects Pvt Ltd Commissioning of PCV-5


Control Valve - PCV-5

SWAS M/s ASW Projects Pvt Ltd Commissioing of SWAS System


DATE:- 08.01.2024

08.01.2024 Status

Issue not yet resolved


Final bill filed under approval and currently with GM
(Project)

??
Final bill under process and inbetween DLC pipri issued
leetter on 18.12.2023 for penalty of Rs 4.95 Lakh against
M/s UPPL.

Final Bill under process and currently file is with HQ Finance.

As per M.S Construction Legal Notice Sent to BHEL CMD and


UPRVUNL in 1st week of Oct-2022. M/s Construction filed a
case in Allahabad High Court and the case has been turned
down by court.

PG test completed on 23.11.2023.

Contractor is not responding and filed case against BHEL for its
issues. Currently case is under review in court.
Completed

Completed

??

??
Settlement done with HWR with 60:40 ( 60% HWR and 40%
PS-NR) cost incurred.

Issue Closed.

Issue Closed.
??

Shutdown awaited from customer

??

??

??

??

??

Final bill completed and payment released to contractor.


??

No development

Issue Closed.

Issue Closed.

PCV-5 received and handed over to customer. Issue closed

??
ISSUES/PROBLEMS AT
S.No. Units Party name Issues/problems

Regarding settlement of extra work claim


Unit 7 TG & Boiler M/s Alpha power engineering services
of boiler with UPRVUNL
Regarding material reconciliation at site
Unit # 13 Boiler M/s Arun Constructions
for contract closing.

Unit # 13 Boiler BHEL Ranipet supply of D11 actuator


Regarding material reconciliation at site
Unit # 13 ESP M/s UPPL
for contract closing.

1 Unit #10 & 11 M/s S.N. Singh Contract closing

2 Unit #10 & 11 M/s M.S. Construction Pvt.Ltd. Contract closing

5 PG test

Unit #12 M/s Alpha power engineering services

6 Contract closing
7 Full load

8 PG test

Unit #13 M/s Brother engineering erectors limited

9 Contract closing

10 AOP Pressure issue of BFP #13 C

TG and it's Auxiliaries


TG and it's Auxiliaries

Cost debit acceptance of an amount of Rs.


58.0 Lacs, Rs 4.2 Lacs, Rs.9.75 Lacs & Rs.44.0
11 Unit #13 BHEL-HWR Lacs for the previous executed turbine works
at R&M TG work in Unit #13. Total amount of
Rs. 1.16 Crore

Balancing weight pending from BHEL-HWR


Unit #13 BHEL-HWR
side

Unused Coupling bolts & balancing weights


12 Unit #13 BHEL-HWR
left with site
CT fan blade (01 nos.) is to be replaced by
M/s Unique. order has been placed waiting
13 BOP- COOLING TOWER M/S SCT
for supply of new CT fans. EDC 30.10.2022.
contract closing

MS liner replacement of wagon tippler no. 1


14 BOP- MISC CIVIL M/S DEEN DAYAL
&2

15 BOP- MECHANICAL M/S SATNAM PG test & commissioning

BOP-COMPRESSOR WIP. Erection work of 4th no. receiver is


17 M/S INDIA ENGINEERING
MECH under progress.

BOP Package Replacement of isolator, CVT & CHP MCC


18 of Unit #9 to 0.4 kV swgr M/s Siemens
and contract closing
#13

19 6.6 kV swgr M/s ABB contract closing

Overhauling of Old
M/s Mechiniks Vendor is not responding
compressors

20 WTP M/s Clear Water PG Test & contract closing


Disposal of MS collecting electrodes balance
MM issue MM Related issue M/s Navjeevan steels
15 MT

Regarding diversion of surplus materials of


MM issue MM Related issue BHEL SSBG
Main R&M package

Insurance Regarding settlement of claim against fire


Insurance related issue M/s NIC
related accident of unit no. 12 & 13

Mill - MDV M/s ASW Projects Pvt Ltd Commissioning of Mill Discharge Valve

C&I Package of
21
Unit-13 Sox Analyzer M/s ASW Projects Pvt Ltd Commissioning of Sox system

APRDS Pressure
M/s ASW Projects Pvt Ltd Commissioning of PCV-5
Control Valve - PCV-5
DATE:- 06.10.2022
ES/PROBLEMS AT R&M OBRA SITE
Current status Site comments

A meeting was held in the presence of ED/SSBG,GM/SSBG


and CM , R&M obra site and MD, UPRVUNL on 11.02.2022
in which this extra work issue was raised. Then a meeting
held on 13.04.2022 at shakti bhawan , Lucknow with
Director (Power) BHEL & Chairman UPRVUNL , MD UPRVUNL
for the settlement of issues of UNit #7 extra work and it was
Matter is still unresolved
decided that a representative of UPRVUNL will visit obra site
to resolve the issue.After the meeting of 13.04.2022, a
representative from UPRVUNL,Anpara and SSBG, Lko visited
Obra site. UPRVUNL's representative made a report and
submitted it to HQ Lucknow. We need help of BHEL SSBG to
resolve the issue.
We have requested several times to the vendor to complete
M/s Arun Construction is not taking any
the material reconciliation so that smooth contract closing
action.
can be done at site. But M/s Arun is not taking any action.

An open order was placed on BHEL Ranipet on 18.02.2022


for supply of new D11 actuators but the material is not yet
supplied. We have written emails to Ranipet and SSBG but
no response is coming.
We have requested several times to the vendor to complete
vendor is not taking any action. the material reconciliation so that smooth contract closing
can be done at site. But M/s UPPL is not taking any action.

Some documents are still pending from contractor's end for


Under progress
contract closing.

Site communicated with the vendor through e-mail,telephonically


Party not responding
for reconcillation of unit material but party is not responding.

Site approached many times but customer denied for clearance to


Still pending perform the PG test of unit 12. Customer will provide clearance
after full loading of unit #13

Contractor not responding and there are a lot of issues of workers


wage payment,court case against wage payment etc. Many
Still pending
reminders have been sent to the contractor. No response is
coming from vendor's end.
Party not responding
contractor de mobilized man power from Unit #13 in Dec. 2021 ,
Further, site continously communicated through E-
mail,telephonically for re-mobilization of man power for the
assistance in commissioning activities and for completion of
Party not responding balance work in TG unit #13 but contractor did not respond.
Further site has engaged the third party agency for the balance
work and for pending commissioning and material reconciliation
work.
Machine got synchronized on 23.07.2022 but unfortunately, a fire
accident was occurred in GT area .GT replacement work under
progress by customer. After GT replacement ,Boiler lit up is
Party not responding planned for full loading of machine

Site is continuously following -up with BHEL-HYD & SSBG for


Reply awaited from BHEL-HYD
resolution of BFP problem
First time machine was rolled on 3000 RPM in Aug 2021 but a
vibratioon was found in pedestal no. 3 & 5 . after that , A VC was
held among BHEL-PSTS,HWR, SSBG for resolution of vibration
issue and it was decided to dismatle the IP & LP rotors for slow
speed balancing. Site complteled the assembly work after slow
speed balncing but again vibration problem persisted.
Further, ALL represenatatives (BHEL-PSTS, Haridwar, ex BHEL,
SSBG) checked the site work thoroughly and there was no
discrepencies found in site assembly work.
Still pending from BHEL-HWR side Again IP &LP rotors were sent to BHEL-HWR for tunnel balancing
and for other machining rectification work. Rotors recieved back
at site on 23.05.2022 and turbine assembly work completed in july
2022 .
Machine again synchronized on 23.07.2022 smoothly.
The dismantling and reassembly works done at site duye to
manufacturing fault of BHEL Hwr need to be adjusted. We have
written several emails to BHEL Hwr and SSBG for cost debit
acceptance of reworks done at site but no response is coming
from their's end.

Site had used 31 no's of balancing weight from customer on loan


basis on the instruction of BHEL-HWR during slow speed balncing
of rotors at site. Customer is demanding their balancing weights
Still not received from HWR unit
but HWR still not responding for the same.Site is continuously
communicating with HWR and SSBG but there is no response from
either side.

The balancing weights sent by BHEL HWR were improper sized


and were not used at site. Site is trying to send unused coupling
There is no response from BHEL-HWR bolts & balancing weights to BHEL-HWR but there is no response
from BHEL-HWR / SSBG side to take back the coupling bolts and
balancing weights.
Vendor was not responding. New agency (m/S uNIQUE) has been
finalized for balance 40% works at risk & cost of M/s SCT and
90% work has been completed. Waiting for supply of 1 no. new CT
WIP
Fan blade (expected date of supply 25.10.2022) so that final
commissioning of CLCT & PG test and contract closing can be
done.

Shut down required from UPRVUNL for wagon tippler hopper no.
Front not available from UPRVUNL's side 01 & 02 for MS liner replacement work. Shut down is expected in
dec 2022.
Waiting for commissioning of CLCT & PG test so that contract
WIP.
closing shall be done
WIP. Erection work of 4th no. receiver is shutdown required for final connection of piping. Contract to be
under progress. short closed.

Isolator replacement work is being done on phased manner as per


the availability of shutdown. Till date, 06/10 isolaters replaced.
Work in progress
Shutdown of CVT & CHP MCC still awaited from UPRVUNL. UNL
has assured to provide shutdown in Dec 2022.

M/s ABB has not attended the punch points of overheating of


Work completed. incomer breakers of 6.6 kV switchgears. contract closing shall be
done after attending the punch points.

The front for this work was not provided by UPRVUNL since 2010
Work stopped. Material reconciliation is to 2021. In the year 2022 UPRVUNL provided front clearance for
under progress. this work, but vendor is now not responding. We will have to get
the work done at risk and cost of M/s Mechiniks.

90% work completed. PG test is pending and is to be conducted


WIP aftercompletion of punch points of WTP. List has been handed
over to M/s Clear water.
Our scrap disposal division has to take suitable action as M/s
Navjeevan steel has refused to dispose the balance 15 MT ESP
electrodes.

Due to contractual ambuiguity UPRVUNL is not allowing to divert


the surplus materials of main R&M package from Obra site. We
have written several emails and discussed the issue with CGM
Obra and BHEL SSBG to give the permission for diversion of
surplus materials of R&M package, But customer is not allowing.
BHEL SSBG has to resolve the issue at the earliest.

M/s NIC has passed Rs. 41 lakhs only against insurance claim of Rs.
6 crores. We have written letters to M/s NIC but no positive
response is coming. We have written emails to our legal cell for
the further opinin on this case. We have also written letters to
UPRVUNL for giving consent for the settlement of insurance
claims.

8 nos. 3/8" Flexible hose is still not received at site from BHEL
HERP Varanasi. We are following up HERP Varanasi to resolve the
4 out of 6 MDV commissioned
issue. We have written emails to HERP Varanasi but material is not
yet supplied at site.

During the commissioning of Sox of Unit-12, some of materials


were found defective and cannibalized from the available
materials of unit-13. A email has been given to BHEL Edn on dtd
Erection completed.
29.07.2022 for replacement of defective materials with new
materials.We are following up the issue with EDN Bangalore.
Reply is still awaited.

Control Valve succesfully commissioned but CAR has been raised to BHEL PC Chennai to resolve the issue. CAR
unable to control pressure in desired No. CAR:22:PC:00019 dated 31.08.2022 . We are following up
operation range. with PC chennai. But no response is coming.
Remarks
As per M.S Construction Legal Notice Sent to BHEL CMD and
UPRVUNL in 1st week of Oct-2022.