Unit 7 TG & Boiler M/s Alpha power engineering services Regarding settlement of extra work claim
of boiler with UPRVUNL
Unit # 13 Boiler M/s Arun Constructions Regarding material reconciliation at site
for contract closing.
1 Unit #10 & 11 TG and it's Auxiliaries M/s S.N. Singh Contract closing
6 Contract closing
7 Unit #13 M/s Brother engineering erectors limited Full load
8 PG test
9 Contract closing
14 BOP- MISC CIVIL M/S DEEN DAYAL MS liner replacement of wagon tippler no. 1
&2
17 BOP-COMPRESSOR M/S INDIA ENGINEERING WIP. Erection work of 4th no. receiver is
MECH under progress.
18 0.4 kV swgr M/s Siemens Replacement of isolator, CVT & CHP MCC
and contract closing
Insurance Insurance related issue M/s NIC Regarding settlement of claim against fire
related accident of unit no. 12 & 13
21 C&I Package of Mill - MDV M/s ASW Projects Pvt Ltd Commissioning of Mill Discharge Valve
Unit-13
Sox Analyzer M/s ASW Projects Pvt Ltd Commissioning of Sox system
08.01.2024 Status
??
Final bill under process and inbetween DLC pipri issued
leetter on 18.12.2023 for penalty of Rs 4.95 Lakh against
M/s UPPL.
Contractor is not responding and filed case against BHEL for its
issues. Currently case is under review in court.
Completed
Completed
??
??
Settlement done with HWR with 60:40 ( 60% HWR and 40%
PS-NR) cost incurred.
Issue Closed.
Issue Closed.
??
??
??
??
??
??
No development
Issue Closed.
Issue Closed.
??
ISSUES/PROBLEMS AT
S.No. Units Party name Issues/problems
5 PG test
6 Contract closing
7 Full load
8 PG test
9 Contract closing
Overhauling of Old
M/s Mechiniks Vendor is not responding
compressors
Mill - MDV M/s ASW Projects Pvt Ltd Commissioning of Mill Discharge Valve
C&I Package of
21
Unit-13 Sox Analyzer M/s ASW Projects Pvt Ltd Commissioning of Sox system
APRDS Pressure
M/s ASW Projects Pvt Ltd Commissioning of PCV-5
Control Valve - PCV-5
DATE:- 06.10.2022
ES/PROBLEMS AT R&M OBRA SITE
Current status Site comments
Shut down required from UPRVUNL for wagon tippler hopper no.
Front not available from UPRVUNL's side 01 & 02 for MS liner replacement work. Shut down is expected in
dec 2022.
Waiting for commissioning of CLCT & PG test so that contract
WIP.
closing shall be done
WIP. Erection work of 4th no. receiver is shutdown required for final connection of piping. Contract to be
under progress. short closed.
The front for this work was not provided by UPRVUNL since 2010
Work stopped. Material reconciliation is to 2021. In the year 2022 UPRVUNL provided front clearance for
under progress. this work, but vendor is now not responding. We will have to get
the work done at risk and cost of M/s Mechiniks.
M/s NIC has passed Rs. 41 lakhs only against insurance claim of Rs.
6 crores. We have written letters to M/s NIC but no positive
response is coming. We have written emails to our legal cell for
the further opinin on this case. We have also written letters to
UPRVUNL for giving consent for the settlement of insurance
claims.
8 nos. 3/8" Flexible hose is still not received at site from BHEL
HERP Varanasi. We are following up HERP Varanasi to resolve the
4 out of 6 MDV commissioned
issue. We have written emails to HERP Varanasi but material is not
yet supplied at site.
Control Valve succesfully commissioned but CAR has been raised to BHEL PC Chennai to resolve the issue. CAR
unable to control pressure in desired No. CAR:22:PC:00019 dated 31.08.2022 . We are following up
operation range. with PC chennai. But no response is coming.
Remarks
As per M.S Construction Legal Notice Sent to BHEL CMD and
UPRVUNL in 1st week of Oct-2022.