ANNEXURE-XII

Tender Enquiry No. REC-231


Bar Chart - Construction of 220kV Sub-station Contractual completion period 18 Months
Supply Schedule
Sr Activity M-1 M-2 M-3 M-4 M-5 M-6 M-7 M-8 M-9 M-10 M-11 M-12 M-13 M-14 M-15 M-16 M-17 M-18
No
1. Foundation Bolts, Towers
& Beams

2. Equipment structures

3. Disc insulators, hardware,


clamps & connectors

4. ACSR Conductor &


Earthwire

5. Earthing mat material

6. Isolators and L&E


switches, post insulators

7. Surge Arrestors

8. CTs, PTs, CVTs, NCTs

9. Breakers

10. Control & Relay Panels

11. 11 kV VCBs

12. Battery & Battery charger

188
Sr Activity M-1 M-2 M-3 M-4 M-5 M-6 M-7 M-8 M-9 M-10 M-11 M-12 M-13 M-14 M-15 M-16 M-17 M-18
No
13. Power & control cables,
ACDB, DCDB, MKs
14. Station Transformers

15. Capacitor Banks

16. Power Transformers

17. Lighting Equipment

18. Fire Fighting equipment

189
Tender Enquiry No. REC-231Bar Chart - Construction of 220kV substation
Contractual completion period 18 months
Schedule of Civil Works
Sr Activity M-1 M-2 M-3 M-4 M-5 M-6 M-7 M-8 M-9 M-10 M-11 M-12 M-13 M-14 M-15 M-16 M-17 M-18
No
1. Handing over clear site
by HVPNL

2. Opening of site office &


site store and shifting of
T&P etc at sites

3. Land contouring, fixation


of formation levels from
civil design
4. Marking of layout of the
sub-station including
layout of trenches

5. U/C fencing of
switchyard/ construction
of boundary wall

6. Tower foundations

7. Approval of design of
transformer foundations

8. Construction of
transformer foundations

9. Equipment foundations
except breakers

10. Design of breaker


foundations

190
11. Construction of breaker
foundations
12. Construction of switch house
building
Excavation

Upto DPC level

Upto roof level

Casting of roof

Plastering

Indoor trenches

Flooring

Final finishes

13. Outdoor cable trenches

14. Construction of roads

15. Station transformer and capacitor


foundations
16. Earth filling and site surfacing

191
Tender Enquiry No. REC-231
Bar Chart - Construction of 220kV substation Contractual completion period 18 Months
Equipment Erection Schedule
Sr Activity M-1 M-2 M-3 M-4 M-5 M-6 M-7 M-8 M-9 M-10 M-11 M-12 M-13 M-14 M-15 M-16 M-17 M-18
No
1. Earthmat laying
Soil resistivity measurement

Earthing calculations &


approval
Laying of earthmat

2. Erection of towers & beam

3. Stringing of Bus bar

4. Erection of equipment
structures
5. Erection of outdoor equipment
such as breakers, isolators,
CTs, PTs, CVTs, LAs
6. Erection of power transformers

7. Erection of indoor equipment

8. Cabling

9. Pre-commissioning tests by
contractor
10. Yard lighting

11. Tests check by M&P and Chief


Electrical Inspector
12. Commissioning of sub-station

192