Professional Documents
Culture Documents
2. Equipment structures
7. Surge Arrestors
9. Breakers
11. 11 kV VCBs
188
Sr Activity M-1 M-2 M-3 M-4 M-5 M-6 M-7 M-8 M-9 M-10 M-11 M-12 M-13 M-14 M-15 M-16 M-17 M-18
No
13. Power & control cables,
ACDB, DCDB, MKs
14. Station Transformers
189
Tender Enquiry No. REC-231Bar Chart - Construction of 220kV substation
Contractual completion period 18 months
Schedule of Civil Works
Sr Activity M-1 M-2 M-3 M-4 M-5 M-6 M-7 M-8 M-9 M-10 M-11 M-12 M-13 M-14 M-15 M-16 M-17 M-18
No
1. Handing over clear site
by HVPNL
5. U/C fencing of
switchyard/ construction
of boundary wall
6. Tower foundations
7. Approval of design of
transformer foundations
8. Construction of
transformer foundations
9. Equipment foundations
except breakers
190
11. Construction of breaker
foundations
12. Construction of switch house
building
Excavation
Casting of roof
Plastering
Indoor trenches
Flooring
Final finishes
191
Tender Enquiry No. REC-231
Bar Chart - Construction of 220kV substation Contractual completion period 18 Months
Equipment Erection Schedule
Sr Activity M-1 M-2 M-3 M-4 M-5 M-6 M-7 M-8 M-9 M-10 M-11 M-12 M-13 M-14 M-15 M-16 M-17 M-18
No
1. Earthmat laying
Soil resistivity measurement
4. Erection of equipment
structures
5. Erection of outdoor equipment
such as breakers, isolators,
CTs, PTs, CVTs, LAs
6. Erection of power transformers
8. Cabling
9. Pre-commissioning tests by
contractor
10. Yard lighting
192