Appendix 1: Status of Work at Nyabondo Trauma Centre

No. Original Works Status Remarks


1 Substructures COMPLETE
2 R.C Superstructures COMPLETE
3 Walling COMPLETE
4 Window COMPLETE
5 Electrical Phase 1 Works COMPLETE
6 Staircase Finishes COMPLETE
7 Remedial Works ONGOING Architect to confirm they have been done adquately.
8 Externalworks and foul water drainage PENDING RE's office/ Hillary
9 Doors ONGOING Architect to confirm they have been done adquately
10 Finishes ONGOING Architect to confirm they have been done adquately.
11 Lockers ONGOING Architect to confirm they have been done adquately
12 Plumbing and Sanitary fittings ONGOING Eng. Okubo to confirm they have been done adequately
13 Gypsum/ Acoustic Ceiling (ICU HDU THEATERS) PENDING Architect and Med Eng to confirm they have been done adquately
14 Augmentation of water supply - KIWASCO ONGOING RE's office to confirm if the connection to the tanks has been done
No. Addendum No 2 & 3 Status Completion Date Proposed by Contractor
1 Ringbeam COMPLETE
2 Roof Structure and Covering COMPLETE
3 Lift Shaft COMPLETE
4 Incinerator Building COMPLETE
5 Gate House COMPLETE
6 Incinerator Building COMPLETE
7 Masonary Boundary Wall COMPLETE
8 Oxygen Plant House COMPLETE
9 Generator House COMPLETE
10 Outdoor Lighting COMPLETE
11 Transformer House ONGOING Architect and Elec Eng to confirm the remedial works are OK
12 Electrical installations Phase 2 ONGOING Eng. Amaje to confirm is all works are complete
13 Additional electrical works ONGOING Eng. Amaje to confirm is all works are complete
14 Septic Tank PENDING RE's office to confrim that the connections have been done
15 Soak pit PENDING RE's office to confrim that the connections have been done
16 Gates 3No. PENDING RE's office to follow up with Contractor
17 Plumbing Installations Phase 2 - Solar and water heating ONGOING Eng. Okubo to confirm they have been done adequately
18 Medical Gas Pipeline ONGOING Eng. Okubo to confirm they have been done adequately
19 Air Conditioning and mechanical ventilation ONGOING Eng. Okubo to confirm they have been done adequately
20 Lift Installations PENDING Eng. Ojowi to confirm with Client if this will be done
21 External Civil Wokrs (Parking and access road) PENDING RE's office to follow up with Contractor
22 External Water Storage Tanks and base PENDING RE's office to follow up with Contractor
23 Repainting of the exsiting Building at the Trauma Centre ONGOING Architect to confirm they have been done adquately
24 Signage at the Trauma Centre PENDING Med Eng to confirm they have been done adquately
25 Physiotherapy and administraction room partitions COMPLETE
26 3 Lead Doors for the CT SCAN and X ray room ONGOING Med Eng to confirm they have been done adquately
27 Water Booster Pump and Control Panel PENDING Eng. Okubo to confirm they have been done adequately
28 Covered passage to physiotherapy room PENDING Architect to confirm they have been done adquately
29 5No. Louvred Doors over the ducts PENDING Architect to confirm they have been done adquately
No. Additional Items Status Completion Date Proposed by Contractor
1 Blocking of 4 ICU windows COMPLETE
Oxygen pipe support structure between Oxygen plant house
2 PENDING RE's office to follow up with Contractor
and hospital
3 Extension of medical gas piping to 5No. Wards PENDING Eng. Okubo to give cost estimate
4 Stormwater drainage PENDING RE's office to give Client the 2 Options discussed
5 2 Pass windows WAITING APPROVAL Waiting approval from Client
6 15 Medical oxygen cylinders WAITING APPROVAL Waiting approval from Client
7 Borehole WAITING APPROVAL Waiting approval from Client