Professional Documents
Culture Documents
PAKARTI TIRTOAGUNG
JL. RAYA TENGAH NO. 4 PASAR REBO
JAKARTA TIMUR
As built drawing
Last inspection report
Last certification document
Job Requirement Specification
Detail BOQ
Repair Drawing if any
ITP repair if any
Project Management
ENGINEERING
ERECTION
DETAIL ENGINEERING
/CONSTRUCTION
ENGINEERING
QC
PROCUREMENT
FINAL TESTING
FABRICATION &
WELDING
QUALIFICATION COMMISIONING/
START UP
RUNING WPS & PQR - 1
Qualification
WPS Welding Procedure
Qualification Record.
Welder ( PQR )
Qualification
Remarks ………….
Quality Control
Dimensional Inspection
Foundation Inspection
Location Mark Check
Fit-up Inspection
Roundness
Plumbness
Local Deviation
Quality Control
Nondestructive Examination
Visual Inspection
NDE Procedure
Radiographic Examination (RT)
Liquid Penetrant Examination (PT)
Vacuum Box Test (VBT)
Pneumatic Leak Test (LT)
Repair and Re-examination
Quality Control
Hydrostatic Test
Pre-test Check
Water Filling
Settlement Monitoring
Hydrostatic Test
QUALITY CONTROL – ITP
Vent
Vent
Project Documentation
Engineering Document
AFC drawing , Repair Procedure
Procurement Document
Material Certificate , COO , COC, test certificate, others
Fabrication Document
Fit up, Welding Traceability, Dimensional report
Erection Document
Plumpness, Roundness , Verticality, and other report.
QC Document
NDE as UT, RT, MT, PT, Fill up water, Foam test
Certification Document
commissioning and start up report
compilation all report as agreed in ITP
Project Certification
1 2 3 4 5 6 7 8 9 10 11 12 E/M
2 Heavy Equipment
5 Testing Equipment 0
6 Other
1 2 3 4 5 6 7 8 9 10 11 12 M/M
12 QA / QC Manager Person 1 1 1 1 1 1 1 1 1 1 1 1 12
20 Driver Person 5 5 5 5 5 5 5 5 5 5 5 5 60
Tahun 2019
NO. KLASIFIKASI SATUAN Bulan ke TOTAL
1 2 3 4 5 6 7 8 9 10 11 12 M/M
0
B Skill Personal 0
1 Designer Person 5 5 5 5 5 5 5 5 5 5 5 5 60
2 Drafter Person 5 5 5 5 5 5 5 5 5 5 5 5 60
3 HSE Officer Person 5 5 5 5 5 5 5 5 5 5 5 5 60
4 QA QC Inspector M Person 5 5 5 5 5 5 5 5 5 5 5 5 60
5 QA QC Inspector P Person 5 5 5 5 5 5 5 5 5 5 5 5 60
6 QA QC Inspector E Person 5 5 5 5 5 5 5 5 5 5 5 5 60
7 QA QC Inspector I Person 5 5 5 5 5 5 5 5 5 5 5 5 60
8 QA QC Inspector C Person 5 5 5 5 5 5 5 5 5 5 5 5 60
9 Spv Mechanical Person 5 5 5 5 5 5 5 5 5 5 5 5 60
10 Spv Piping Person 5 5 5 5 5 5 5 5 5 5 5 5 60
11 Spv Electrical Person 5 5 5 5 5 5 5 5 5 5 5 5 60
12 Spv Instrument Person 5 5 5 5 5 5 5 5 5 5 5 5 60
13 NDT Team 1 1 1 1 1 1 1 1 1 1 1 1 12
Tahun 2019
NO. KLASIFIKASI SATUAN Bulan ke TOTAL
1 2 3 4 5 6 7 8 9 10 11 12 M/M
0
0
C Direc Worker 0
1 Welder Person 30 30 30 30 30 30 30 30 30 30 30 30 360
2 Fitter Person 25 25 25 25 25 25 25 25 25 25 25 25 300
3 Helper Person 12 12 12 12 12 12 12 12 12 12 12 12 144
4 Electrician Person 0 0 0 0 0 4 4 4 4 4 4 4 28
5 Instrumen tech Person 0 0 0 0 0 4 4 4 4 4 4 4 28
7 Mechanic Person 4 4 4 4 4 4 4 4 4 4 4 4 48
8 Civil Work Craftman Person 20 20 20 20 20 20 20 20 20 20 20 20 240
9 Material control Person 5 5 5 5 5 5 5 5 5 5 5 5 60
10 Tools keeper Person 5 5 5 5 5 5 5 5 5 5 5 5 60
Question
1. Project permit
2. Crane provided by ?
3. Feed Doc or Engieering doc ?
4. WPS and PQR by ?
5. PQT for painting is required ?
6. Paint Material specification ?
7. Impact test is for PQR or for material ?
8. Scaffolding specification ?
9. After repair valve ? Certification ?
10. Is custody tank ?
11. Re Engineering issue regarding change the media ?
12. Quantity lot ? Little bit difficult to estimate the qty ?
13. COI or PLO ?
14. PI ?
END OF PRESENTATION
THANK YOU