You are on page 1of 2

MLVC E&C Inc.

DESIGNERS ● CONSULTANTS ● PROJECT MANAGERS

Project : GO HOTEL TUGUEGARAO

Location : Brgy. Tanza, Tuguegarao City

Subject : Construction Coordination Meeting

Date/Time : October 22, 2018

AGENDA

ITEM PARTICULARS REMARKS

A. Walk Thru Issues

1 Heat Pump Location.


2 Provision of a Mezzanine Floor at BOH.

3 Sidewall at Drop off Canopy.

Adjustment of the sidewalk to compensate


4
the column cladding at drop off canopy.
Relocation of the exhaust fan for the
5
Preparation Area.
Removal of the Roof Gutter for the Side
6
Canopy.

7 Relocation of the ACCU at Left Side.

Relocate the pipes going through Server


8
Room.

Relocate drains located above the Cistern


9
Tank esp. along Garbage Room.

Cladding for the Floor Control Valves for


10
Fire Protection at Common Stair.

11 Demolition of the Zocalo at Unit Toilets

Additional Roofing at Fire Exits Deck Level


12
for Door Protection.

___________________________________________________________________________________
MLVC E&C Inc.
DESIGNERS ● CONSULTANTS ● PROJECT MANAGERS

B. Operations

1. Project Timeline

Status for the awarding of Fit Out


2.
Contractor.

3. Final Reflected Ceiling Plan (all levels)

4. Final Interior Design

a. Common Toilets

b. Elevator Cladding

5. Final EIFS Color

6. Final Tile Pattern

7. Status of the delivery of Tiles.

Treatment for the glass door jamb at


8.
shower.

Hold order on the stiffener column at unit


9.
toilets.

ACCU pads at Second Floor Deck (RFA-ME-


10.
02)

RFI-ME-01 Mech. Plan with conflict to Latest


11.
RCP.

12. Final Plan for the Power Center.

13. Location for the Additional AVR.

14. Service Entrance.