INTERIM VALUATION SCHEDULE

SINGLE STOREY BUILDING

Construction stage % of Current stage 1st Current stage Current stage


completion Inspection 2nd Inspection 3rd Inspection
Preliminaries, sub walling and slab 15 15 15 15 15 15 15
casting
D.P.C. and G.F. walling to shuttering 20 20 20 20 20 20 20
level
Shuttering reinforcement, conduits,
slab cast parapet and finishes
material.
OR

Timber roof frames, polythene 15 0 7.5 10.5 10 10


roofed over
Ceiling brandering, door window 15 0 13.5 7 7.5 7.5
and cupboard frames and electrical
conduit fixed
Water piping fixed and plastered 5 0 5 5 5
out
Ceiling board, plumbing carpentry 10 0 0 8 5 5
septic tank, manholes and window
panes.
Electrical reticulation, electrical 5 2 2 2
fitting and main services line.
Sanitary, Kitchen fitments, filing, 8 0 0 0 3
floor finishes and skirting.
Painting weathering final touches 7 3 3 3 3.5
and access road
Certificate of occupation.

Total 100% 40% 64% 45.5% 68%

INTERIM VALUATION SCHEDULE


DOUBLE STOREY BUILDING

Construction stage % of Current stage 1st Current stage Current stage


completion Inspection 2nd Inspection 3rd Inspection
Preliminaries, sub walling and slab 15 15
casting
D.P.C. and G.F. walling to shuttering 10 10
level
Shuttering reinforcement, conduits, 5 5

Slab cast 10 10

First floor walling to plate/ring 10 10


beam.
Shuttering reinforcement, conduits,
slab cast parapet and finishes
material.
OR

Timber roof frames, polythene 15 15


roofed over
Ceiling brandering, door window 10 2.5
and cupboard frames and electrical
conduit fixed
Water piping fixed and plastered 5 0
out
Ceiling board, plumbing carpentry 5 0
septic tank, manholes and window
panes.
Electrical reticulation, electrical 5 0
fitting and main services line.
Sanitary, Kitchen fitments, filing, 5 0
floor finishes and skirting.
Painting weathering final touches 5 0
and access road
Certificate of occupation. -

Total 100% 68

INTERIM VALUATION SCHEDULE


TRIPLE STOREY BUILDING
Construction stage % of Current stage 1st Current stage Current stage
completion Inspection 2nd Inspection 3rd Inspection
Preliminaries, sub walling and slab 15 15
casting
D.P.C. and G.F. walling to shuttering 7 7
level
Shuttering reinforcement, conduits, 3 3

Slab cast 7 7

First floor walling to ring beam. 5 5

Shuttering reinforcement, conduits, 3 3

Slab cast 7 7

Second floor walling to plate 5 5


level/ring beam.
Shuttering reinforcement, with
conduits, slab cast parapet and
finishes material.
OR

Timber roof frames, polythene 18 18


roofed over
Ceiling brandering, door window 5 2.5
and cupboard frames and electrical
conduit fixed
Water piping fixed and plastered 5 2
out
Ceiling board, plumbing carpentry 5 2.5
septic tank, manholes and window
panes.
Electrical reticulation, electrical 5 4.75
fitting and main services line.
Sanitary, Kitchen fitments, filing, 5 0.25
floor finishes and skirting.
Painting weathering final touches 5 0.5
and access road
Certificate of occupation. -

Total 100% 82.5%

INTERIM VALUATION SCHEDULE


FOUR STOREY BUILDING
Construction stage % of Current stage 1st Current stage Current stage 3rd
completion Inspection 2nd Inspection Inspection
Preliminaries 2
Foundation 12
Ground floor slab 4
Ground floor walling 3
1st Floor slab 4
1st Floor walling 3
2nd Floor slab 4
2nd Floor walling 3
3rd Floor slab 4
3rd Floor walling 3
Roofing 8
Doors, Windows & Glazing
Ground floor 3
1st Floor 3
2nd Floor 3
3rd Floor 3
Floor Finishes
Ground floor 1.5
1st Floor 1.5
2nd Floor 1.5
3rd Floor 1.5
Wall Finishes
Ground floor 1.5
1st Floor 1.5
2nd Floor 1.5
3rd Floor 1.5
Ceiling
Ground floor 1.5
1st Floor 1.5
2nd Floor 1.5
3rd Floor 1.5
Painting 4
Sanitary & Other Fittings 5
Plumbing & Drainage 5
Wiring, Conduit & Installation 5
General Making Good 1
Total 100%

INTERIM VALUATION SCHEDULE


FIVE STOREY BUILDING
Construction stage % of Current stage 1st Current stage Current stage 3rd
completion Inspection 2nd Inspection Inspection
Preliminaries 2 2
Foundation 12 12
Ground floor slab 3.5 3.5
Ground floor walling 2.5 2.5
1st Floor slab 3.5 3.5
1st Floor walling 2.5
2nd Floor slab 3.5
2nd Floor walling 2.5
3rd Floor slab 3.5
3rd Floor walling 2.5
4th Floor slab 3.5
4th Floor walling 2.5
Roofing 9
Doors, Windows & Glazing
Ground floor 2.5 0.7
1st Floor 2.5
2nd Floor 2.5
3rd Floor 2.5
4th Floor 2.5
Floor Finishes
Ground floor 1 0.7
1st Floor 1
2nd Floor 1
3rd Floor 1
4th Floor 1
Wall Finishes
Ground floor 1 0.7
1st Floor 1
2nd Floor 1
3rd Floor 1
4th Floor 1
Ceiling
Ground floor 1 0.7
1st Floor 1
2nd Floor 1
3rd Floor 1
4th Floor 1
Painting 3.5
Sanitary & Other Fittings 5
Plumbing & Drainage 5 1
Wiring, Conduit & Installation 5
General Making Good 1
Total 100% 27%

INTERIM VALUATION SCHEDULE


SIX STOREY BUILDING
Construction stage % of Current stage 1st Current stage Current stage 3rd
completion Inspection 2nd Inspection Inspection
Preliminaries 2 2
Foundation 12 12
Ground floor slab 3 3
Ground floor walling 2 2
1st Floor slab 3 3
1st Floor walling 2 2
2nd Floor slab 3 3
2nd Floor walling 2 2
3rd Floor slab 3 3
3rd Floor walling 2
4th Floor slab 3
4th Floor walling 2
5th Floor slab 3
5th Floor walling 2
Roofing 9
Doors, Windows & Glazing
Ground floor 2 2
1st Floor 2 2
2nd Floor 2 2
3rd Floor 2
4th Floor 2
5th Floor 2
Floor Finishes
Ground floor 1 1
1st Floor 1 1
2nd Floor 1 1
3rd Floor 1
4th Floor 1
5th Floor 1
Wall Finishes
Ground floor 1 1
1st Floor 1 1
2nd Floor 1 1
3rd Floor 1
4th Floor 1
5th Floor 1
Ceiling
Ground floor 1 1
1st Floor 1 1
2nd Floor 1 1
3rd Floor 1
4th Floor 1
5th Floor 1
Painting 3 1.5
Sanitary & Other Fittings 4 2
Plumbing & Drainage 4 2
Wiring, Conduit & Installation 4 2
General Making Good 2 2
Total 100% 56.5