SITE PROGRESS REPORT

PROJECT NAME: GREEN VIEW VILLAS

CONTRACTOR: CONCISE PROJECTS LTD

COMPILED BY: AKULA NICHOLAS

REPORTING PERIOD: 15.01.2024 TO 22.01.2024

SUMMARY OF WORK

A) FINISHES

ITEM OF WORK LOCATION OF WORK PERCENT COMPLETE


T&G BOARDS VILLA 9, 8 & 7 back and front face. 95% complete
SCREEDIND Villa 9 GF & DSQ 1st floor, Villa 8 98%
ground floor & 1st floor.
Villa 3 roof level floor screeding.
PRECAST COPING Villa 2, 3 & 4 precast stone coping. 98%

SKIMMING Internal wall to villa 1 to 9 first, 90%


second & third coat skimming to
receive paint.
EXTERNAL WALL MASTER External, wall master paint to villa 1 98%
to 9.
DOORS & WINDOW GLAZING Aluminium doors & window frames 50%
& glazing to villa 1, 4 & 5.
FLOOR & WALL TILING Floor and wall tiling to villa 3 and 10 50%
in bedrooms, kitchen and wash
rooms.
Villa 3 floor and wall tiling in the bathroom.
Floor tiling in villa 10

Doors & Window glazing in villa 5 and T&G board.

Screeding in progress.
External Wall Master Paint.

MANPOWER REPORT

NO DESCRIPTION TOTAL TOOLS USED


WORKFORCE
1 SUPERVISERS 5
2 MASONS 13 spade
3 HELPERS 39 wheelbarrows
4 OPERATOR 1 shovel
5
6 SUB-CONTRACTOR
7 PLUMBING 3
8 ELECTRICAL WORK 3
9 WALL MASTER PAINT 3
10 INTERNAL SKIMMING 3
11 TILING 8
12 MASONS(PIECEWORK) 2