PROJECT : A TWO LEVEL "A" FRAMED CABIN

LOCATION : L1, B3 P1A, 29 NORTHEAST FAIRWAY LOOP, VENERE, NUVALI


OWNER : AR. DARREN MASBATE
SUBJECT : CONSTRUCTION BAR CHART
D U R A T I O N
JULY AUGUST SEPT OCT NOV DEC JAN FEB MARCH APRIL MAY JUNE
Item no. Description 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4

1.0 LAYOUT & TEMFACIL

EXCAVATION/BACKFILLING
2.0 COMPACTION

3.0 FORMWORKS & SCAFFOLDING

4.0 REBAR WORKS

5.0 CONCRETING WORKS

6.0 MASONRY WORKS/PLASTERING

7.0 ROOF FRAMING WORKS

8.0 TINSMITHRY WORKS

9.0 CEILING WORKS

10.0 CARPENTRY WORKS

11.0 WATERPROOFING WORKS

12.0 TILING WORKS

13.0 ELECTRICAL WORKS

14.0 PLUMBING WORKS


JULY AUGUST SEPT OCT

Item no. Description 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4

15.0 PAINTING WORKS

16.0 DOORS & WINDOWS

HOULING OF DEBRIS CLEARING &


17.0 DEMOBILIZATION

LEGEND : ACTUAL ACCOMPLISHMENT

PROJECTED ACCOMPLISHMENT

PREPARED BY:

JAKE L. QUIROS
ARCHITECT-INCHARGE
CONSTRUCTION METHOLOGY
Day 1 to 3 Month
Days - LAYOUT, BOARD-UPS, INSTALL BODEGA and LATHRINE
LATRINE

After 3 days to - EXCAVATION OF LOWER GROUND FLOOR WALL and COLUMN FOOTINGS
3 weeks

3 Weeks after to - FABRICATION OF WALL and COLUMN FOOTING, RC COLUMN


1 Week REBARS, STIRRUPS, RC BEAMS, SUSPENDED SLAB REBARS,
LOWER GROUND FLOOR BEAMS, UPPER GROUND FLOOR BEAMS and ROOF
BEAMS

After 2 Weeks - CONCRETING OF WALL and COLUMN FOOTING, RC COLUMNS,


to 3 Weeks GROUND FLOOR BEAMS and SUSPENDED SLAB, SECOND
FLOOR RC COLUMNS, RC BEAMS and SUSPENDED SLAB, RC
COLUMNS TO ROOF BEAMS and ROOF BEAMS.

After 3 Weeks to - CHB LAYING and PLASTERING


4 Weeks

1 Month and 1 week after


- ROOF FRAMING WORKS
to 2 Weeks

1 Month and 3 weeks after


- TINSMITHING WORKS
to 1 Week

After 2 Months - CEILING WORKS.


to 1 Week

After 2 Months and 1 BUILT-IN CABINET


Week to 2 weeks

After 2 Months and 2 - WATERPROOFING AT LOWER GROUND FLOOR T&B


Weeks to 1 Week

After 2 Months and 2 - TILE WORKS AT UPPER GROUND LEVEL AND LOWER GROUND LEVEL
Weeks to 1 Week

After 2 Months and 2 - ELECTRICAL ROUGHING-IN TO FINISHING WORKS


Weeks to 2 Week

After 2 Months and 3 - PLUMBING ROUGHING-IN TO FINISHING WORKS


Weeks to 2 Week

After 2 Months and 3 - PAINTING WORKS START TO FINISH


Weeks to 2 Weeks

After 3 Months - INSTALLATION OF DOORS and WINDOWS


to 1 Week

After 3 Months and - HOULING OF DEBRIS, CLEANING and DEMOBILIZATION


1 Week

Prepared By,

JAKE L. QUIROS