MARCH 23,2021-AUGUST 7,2021

PROJECT NAME: PROPOSED BUNGALOW RESIDENTIAL


PROJECT LOCATION: BIGAIN 2ND, SAN JOSE, BATANGAS

OWNER: MR. CONRADO B. MENDOZA

Duration : MARCH 22 ,2021


1. Ground Breaking.

Duration : March 23-25, 2021


1. Site clearing.

2. Installation of temporary water and power supply

3. Construction of Barracks.

Duration : March 26-31, 2021


1. Excavation of Column Footing.
2. Fabrication of column and footing rebars.

Duration : April 1-3,2021


NO WORK ( HOLY WEEK )
Duration : April 5-9, 2021
1. Concrete pouring of footing
2. Fabrication and installation of column formworks

Duration : April 10, 2021


Concrete pouring of column

Duration : April 12-16, 2021


1. Excavation of wall footings

2. Continuation of fabrication of column rebars

Duration : April 17-22, 2021


1. concrete pouring of wall footing

2. chb laying.
Duration : April 23-28,2021
1. Continuation of chb laying
2. Fabrication of beam rebars

Duration : April 29,2021-May 6,2021


1. Continuation of chb laying
2. Fabrication of beam formworks
3. Preparation of beam supports

Duration : May 7- May 10, 2021


1. Installation of beam rebars.

2. installation of beam formworks

3. Installlation of beam supports.

Duration : May 11,2021


1.Concrete pouring of beams

Duration : May 12-18,2021


1. plastering of walls.

2. roughing of waterline lyout.

Duration : May 19- 22, 2021


1. plastering of walls.

Duration : May 24-28, 2021


1. Continuation of CHB laying.

2. Installation of Beam Rebars.

Duration : May 29, 2021


1. Concrete pouring of Beams.

Duration : May 31- June 7, 2021


1. Installation and Fabrication of steel trusses.

2. Continuation of CHB laying.

3. Plastering of walls.

Duration : June 8- 16, 2021


1. Installation of Roof.

2. Continuation of Plastering.
3. Installation of Door Jambs.

Duration : June 17-25, 2021


1. Roughing-in of electrical Raceway.

2. Installation of electrical outlet and switches.

3. Application of concrete neutralizer @ walls.

4. Ceiling works.

6. CHB laying and plastering of Septic tank.

Duration : June 26-July 1, 2021


1. Application of primer paint (Flat white).

2. Roughing of plumbing lines (Waterline, Gray waterline, Sanitary line)

3. Tiling works.

4. Installation of Door and windows.

Duration : July 2-17, 2021


1. Application of Topcoat paint.

2. Installation of Plumbing Fixtures.

Duration : July 19- August 6, 2021


1. Application of final topcoat paint.

2. Installation of electrical fixtures.

3. Application of Tile Grout.

4 Installation of Downspouts.

5. Installation of grills.

Duration : August 7, 2021


1. Turnover.

Prepared by:

AR. REYNAN JAY V. LIMBO


UAP., NAMPAP., COSH., BOSH., AMO
Construction
Logbook

MR. CONRADO B. MENDOZA


PROPOSED BUNGALOW RESIDENTIAL
Brgy. Bigain 2nd, San Jose Batangas