Construction

Logbook
A PROPOSED TWO-STOREY CONTAINER VAN OFFICE

PROJECT NAME: A PROPOSED TWO-STOREY CONTAINER VAN OFFICE


PROJECT LOCATION:

OWNER:

NOVEMBER 16, 2021


 Ground Breaking
 Site clearing
NOVEMBER 16, 17, 18, 19, 2021
 Lay out of Comfort room
 Construction of comfort room at the back.
 Cutting of Container Van
NOVEMBER 20, 22, 23, 2021
 Welding of steel frames for window opening
NOVEMBER 24, 25, 26, 27, 29, 30, 2021
 Erection of steel columns for second floor
 Installation of electrical rough ins
 Concrete pouring of floor slab on ground floor
DECEMBER 1, 2, 3, 2021
 Welding of steel beams for second floor
DECEMBER 4, 6, 7, 2021
 Welding of Steel trusses for second floor
DECEMBER 8, 9, 10, 2021
 Installation of Roof and spandrels
DECEMBER 11, 13, 14, 15, 16, 17, 18, 2021
 Construction of steel stairs
 Concrete pouring of floor slab on second floor
DECEMBER 20, 21, 22, 23, 2021
 Production and Installation of aluminum frames and glass window
DECEMBER 24-25, 2021
 Christmas Holiday
DECEMBER 27,28, 29, 30, 2021
 Construction of interior walls on ground floor
DECEMBER 31, 2021- JANUARY 1, 2022
 New Year
JANUARY 3, 4, 5, 2022
 Welding of Steel Canopy
 Construction of interior walls on ground floor
JANUARY 6, 7, 8, 2022
 Ceiling works on ground floor
 Tiling works on ground floor
 Painting Works exterior
JANUARY 10, 11, 12, 13, 14, 15, 2022
 Ceiling works on second floor
 Tiling works on second floor
 Continuation of painting works interior and exterior
 Installation of polycarbonate roof on canopy.
 Carpentry works.
JANUARY 17,18, 19, 20, 2022
 Continuation of carpentry works.
 Painting works interior and exterior final coat.
JANUARY 21 AND 22, 2022
 General cleaning.
 Retouching of Damaged Paints at Interior and Exterior.
JANUARY 24, 2022
 Turnover.