Task Description Plan Start Plan End

1 SITE GROUND WORKS 2/20/2021 2/27/2021


1.1 CLEARING & GRADING
1.2 TEMPORARY FENCING
1.3 CONNECTION OF TEMP. UTILITIES
2 SUB-STRUCTURE 2/20/2021 4/6/2021
2.1 STAKING
2.2 FOUNDATIONS
EXCAV
REBAR
FORMWORKS
CASTING CONCRETE
2.3 GROUND BEAM/SLABS
BACKFILLING / COMPACTION
REBARS
FORMWORKS
CASTING CONCRETE
2.4 COLUMNS
REBARS
FORMWORKS
CASTING CONCRETE
2.5 BEAMS
REBARS
FORMWORKS
CASTING CONCRETE
3 ROUGH-IN WORKS 3/27/2021 4/6/2021
3.1 PLUMBING ROUGH-IN
Plumbing rough-in
Install Fixtures
3.2 ELECTRIC ROUGH-IN
Electrical Rough-Inns
Install wirings
Install Fixtures
4 MASONRY WORKS 4/6/2021 5/1/2021
4.1 SLAB
REBARS
FORMWORKS
CASTING CONCRETE
4.2 STAIRS
REBARS
FORMWORKS
CASTING CONCRETE
4.3 WALLS
REBARS
FORMWORKS
CASTING CONCRETE
5 ROOFING WORKS 4/24/2021 5/15/2021
5.1 TRUSS
INSTALLATION OF TRUSS
5.2 ROOFING MATERIAL
INSTALLATION OF ROOFING MATERIAL
6 DOORS AND WINDOWS 4/24/2021 4/30/2021
DOORS
WINDOWS
7 CEILING WORKS 5/15/2021 5/28/2021
FRAMES
INSTALLATION OF CEILING MATERIAL
8 PAINTS 4/24/2021 5/15/2021
Prep Conrete Wall for Prime Coat
Prime Paint Conrete Wall
Prep Trim for Prime Coat
Prime Trim
Finish Coat Trim
Finish Coat Concrete Wall
Caulk Exterior Windows & Doors
9 Floor Finishes 5/1/2021 5/22/2021
Install Ceramic Tile
20-Feb 27-Feb 6-Mar 13-Mar 20-Mar 27-Mar
6-Apr 10-Apr 17-Apr 24-Apr 1-May 8-May
15-May 22-May 29-May 5-Jun 12-Jun 19-Jun
26-Jun 3-Jul 10-Jul 17-Jul 24-Jul 31-Jul 7-Aug
14-Aug 21-Aug