ACTIVITY TIME IN WEEK DURATION PER ACTIVITY

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
01. Building Permit 2 WEEKS
02.Lyout Design Plans on Site 1 WEEK & 3 DAYS
03.Walls and Footing Excavation 2 WEEKS
04.Plumbing Layout 2 WEEKS
05. Erection of CHB walls, footing and columns 3 WEEKS
06. Erecton of Columns wood forms 3 WEEKS
07. Pouring of footing and columns 3 WEEKS
08. Backfilling 3 DAYS
9. Compaction 1 WEEK
10. Pouring of floor slabs REBARS 2 WEEKS
11. Erection of roof beams rebars 2 WEEKS AND 3 DAYS
12. Erection of Roof Beams wood forms WOOD FORMS 2 WEEKS
13. Pouring of Roof Beams 2 WEEKS
14.Erection of Ceiling Board 2 WEEKS
15.Electrical Layout 1 WEEK AND 3 DAYS
16.Roof Fraing and Roofing 2 WEEKS
17.Finishing Works 2 WEEKS AND 3 DAYS
18. Painting ERECTION OF SCAFFOLDING 1 WEEK AND 3 DAYS
19.Clearing Formworks and Scaffolding 1 WEEK AND 3 DAYS
20.Preparationof submission of the Project 1 WEEK AND 3 DAYS
5 CE 1 GROUP 1
COMIA, GERALDINE
COMETA, MATTHEW
BETAÑA, NHELJANE