PROJECT TITLE : ONE STOREY BUNGALOW PROJECT TIMELINE

Month 2019
Task Name Duration Jan Feb Mac Apr May June
Preliminaries 7 days
Excavation work (Kerja Pengorekan) 7 days
Construct Footing/Foundation 15 days
Construct Ground Beam 25 days
Ground Floor Slab (Lantai konkrit) 30 days
Concrete Column (Tiang Konkrit) 20 days
Brickwall work (Mengikat Bata Dinding) 30 days
Prepare door and window frame (bingkai pintu dan tingkap) 10 days
Roof beam installation (pemasangan rasuk bumbung ) 30 day
piping and electrical work (kerja memasang pipe and pendawaian electrik) 12 days
Floor Render (Lantai) 15 days
Tiles and cement screeding ( kerja memasang jubin) 25 days
Drainage work (Longkang) 7 days
Septic tank and sewerage work (pemasangan tangki najis) 10 days
Door and window Installation (Kerja memasang daun pintu dan tingkap) 5 days
Painting work(kerja mengecat) 12 days
House keeping (Kerja membersih rumah) 3 days
Estimating time to complete all 263 days /8 month 8 days