YOYA 

Construction Engineering PLC.
Bosoke‐Sheto Rural Water Supply Project 

ID Task  Task Name Duration 22 Feb 5, '23 Apr 30, '23 Jul 23, '23 Oct 15, '23 Jan 7, '24 Mar 31, '24


Mode T M F T S W S T M F T S W S
1 Project:‐Bosoke Sheto  Rural Water Supply Project  291 days
Zone:‐Buno Bedele
2 Site Moblization 15 days
3 Bill No.1 Construction of Sprlng Capping 60 days
4 Excavation and Earth work 15 days
5 Masonary Work 15 days
6 Concrete work including form work 15 days
7 Reinforced Work 15 days
8 Bill No 2:‐Construction of 50m3 collection Chamber 60 days
9 Earth Work 15 days
10 Masonry Wall 15 days
11 Concrete Work 15 days
12 Miscellaneous & Finishing 15 days
13 60 days
Bill No.3 Construction of Standard Service Reservoir 50 m
14 Earth Work 15 days
15 Masonry Wall 15 days
16 Concrete Work 15 days
17 Mislaneous & Finishing 15 days
18 Bill No.4 Construction of Generator & guard house (4.5  30 days
x 6.0 m)
19 Earth work 5 days
20 Concrete Work 5 days
21 Hollow Block wall 5 days
22 Roofine 5 days
23 Doors & window(As Shown from the Drawing) 5 days
24 Fence and Miscellaneous works 5 days
25 Bill No.5 Construction of public Water Point 22 days
26 Earth work 5 days
27 Concrete Work 5 days
28 Pipework 2 days
29 Drainage 5 days
30 Fence 5 days
31 Bill No.6 Construction of River Crossing 30 days
32  Construction of River Crossing 30 days

Task Project Summary Manual Task Start-only Deadline

Project: Bedele Split Inactive Task Duration-only Finish-only Progress


Date: Sun 2/19/23 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 1
YOYA Construction Engineering PLC.
Bosoke‐Sheto Rural Water Supply Project 

ID Task  Task Name Duration 22 Feb 5, '23 Apr 30, '23 Jul 23, '23 Oct 15, '23 Jan 7, '24 Mar 31, '24


Mode T M F T S W S T M F T S W S
33 Bill No.7 Construction of Anchor Block 60 days
34 Earth work 30 days
35 Concrete work 30 days
36 Bill No.8 Construction of Valve chamber 26 days
37 Earth work 5 days
38 Masonry work 5 days
39 Concrete work 5 days
40 Formwork 1 day
41 Plastering and other finishing 5 days
42 Manhole cover made of lockable steel (1.5mm thick  5 days
steel sheet) with fram including safety lock. Price shall
include 3 coats of anti rust painting
43 Bill No.9 Installation of Pipes and Fittings For Pressure  130 days
& Distribution Systems
44 Trench excvation 0.6m x 0.8m 40 days
45 Installation of pipes and fittings 40 days
46 Back fill with good filling material 40 days
47 Water Meter 40 days
48 Bill No. TRANSPORTATION AND INSTALLATION OF  40 days
PUMPS AND GENERATORS
49 Transportation of Generators to site 10 days
50 Transportation of Pumps to site 10 days
51 Installation of Generators 10 days
52 Installation of Pumps 10 days
53 Bill No. 14 Supply of Pipes and Fittings for Pressure &  120 days
Distribution Systems
54 Supply of HDPE pipe & fittings 120 days
55 Demoblizatin 14 days

Task Project Summary Manual Task Start-only Deadline

Project: Bedele Split Inactive Task Duration-only Finish-only Progress


Date: Sun 2/19/23 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone