ID Task Name Duration 31, '19 Apr 7, '19 Apr 14, '19 Apr 21, '19 Apr 28,

Duration 31, '19 Apr 7, '19 Apr 14, '19 Apr 21, '19 Apr 28, '19 May 5, '19 May 12, '19
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T
1 Water Provision in Monguno, Monguno LGA, Borno 29 days
State-NLCB029
2 Site Mobilisation 2 days
3 Site Setting Out 2 days
4 Site Clearance 1 day
5 Divisional Police Headquarters 18 days
6 Geophysical survey 1 day
7 Borehole Drilling 3 days
8 Supply and installation of 6'' (150mm) API steel casings pipe 4 days
to accommodate the proposed depth of the drilled borehole

9 Supply and Installation of casing of 2.5” (62.5mm) API steel 3 days


riser pipes
10 Borehole development and yield test 1 day
11 Construction of concrete top slab with well cap 3 days
12 Construction of soak pit and drains with steel grill cover of 3 days
criss-cross bars
13 Reticulation of the borehole to the overhead tank and from 2 days
the overhead tank to the buttress of taps and other facilities
14 Supply and instalation of approved 3HP single phase 1 day
solar-powered submersible pump
15 Supply and installation of solar panels (1000W per panel) 3 days

16 Physiochemical and bacteriological water quality analysis 2 days

17 Disinfecting borehole and sterilization of pump and 3 days


accessories
18 Fabrication and installation of steel water tank stand and 3 days
30,000 Liters steel overhead tank
19 Construction of chain link perimeter fence with steel gate 7 days

20 Gravel filling of the borehole floor area 1 day


21 Construction of two (2) buttresses of six (6) water taps 3 days

22 Federal Government Girls College 18 days


23 Geophysical survey 1 day
24 Borehole Drilling 3 days
25 Supply and installation of 6'' (150mm) API steel casings pipe 4 days
to accommodate the proposed depth of the drilled borehole

26 Supply and Installation of casing of 2.5” (62.5mm) API steel 3 days


riser pipes
27 Borehole development and yield test 1 day
28 Construction of concrete top slab with well cap 3 days

29 Construction of soak pit and drains with steel grill cover of 3 days
criss-cross bars
30 Reticulation of the borehole to the overhead tank and from 2 days
the overhead tank to the buttress of taps and other facilities

31 Supply and instalation of approved 3HP single phase 1 day


solar-powered submersible pump
32 Supply and install solar panels (1000W per panel) 3 days

33 Physiochemical and bacteriological water quality analysis 2 days

34 Disinfecting borehole and sterilization of pump and 3 days


accessories
35 Fabrication and installation of steel water tank stand and 3 days
30,000 Liters steel overhead tank
36 Construction of chain link perimeter fence with steel gate 7 days

37 Gravel filling of the borehole floor area 1 day

38 Construction of two (2) buttresses of six (6) water taps 2 days


39 Site Cleaning 2 days
40 Site Hand Over 1 day

Project: NLCB LOT 029 Task Progress Summary External Tasks Deadline
Date: Wed 4/3/19 Split Milestone Project Summary External Milestone