1 Water Provision in Monguno, Monguno LGA, Borno 29 days
State-NLCB029
2 Site Mobilisation 2 days
3 Site Setting Out 2 days
4 Site Clearance 1 day
5 Divisional Police Headquarters 18 days
6 Geophysical survey 1 day
7 Borehole Drilling 3 days
8 Supply and installation of 6'' (150mm) API steel casings pipe 4 days
to accommodate the proposed depth of the drilled borehole
29 Construction of soak pit and drains with steel grill cover of 3 days
criss-cross bars
30 Reticulation of the borehole to the overhead tank and from 2 days
the overhead tank to the buttress of taps and other facilities