The document outlines the activities and tasks required to rehabilitate the aqueduct system of Laguna Verde village over 127 days. It involves 29 tasks across 3 key areas: the water system intake, adduction, and storage tank. Tasks include preliminary work, camp setup, excavation, removal of moss and sediments, reconstruction of structures, piping installation, inspection and sealing of cracks, sanding, painting, and tank cleaning. Each task has a duration and identifies predecessor tasks that must be completed first.
The document outlines the activities and tasks required to rehabilitate the aqueduct system of Laguna Verde village over 127 days. It involves 29 tasks across 3 key areas: the water system intake, adduction, and storage tank. Tasks include preliminary work, camp setup, excavation, removal of moss and sediments, reconstruction of structures, piping installation, inspection and sealing of cracks, sanding, painting, and tank cleaning. Each task has a duration and identifies predecessor tasks that must be completed first.
The document outlines the activities and tasks required to rehabilitate the aqueduct system of Laguna Verde village over 127 days. It involves 29 tasks across 3 key areas: the water system intake, adduction, and storage tank. Tasks include preliminary work, camp setup, excavation, removal of moss and sediments, reconstruction of structures, piping installation, inspection and sealing of cracks, sanding, painting, and tank cleaning. Each task has a duration and identifies predecessor tasks that must be completed first.
Rehabilitation of the aqueduct system of the Laguna Verde village
WBS ID Activity/ Task Name Predecessor Duration
1 Preliminary 3 days 2 Camp layout, services and office equipment rental 3 days 3 Water system intake 16 days 4 Removal and disposal of moss and sediments 1 4 days 5 Reconstruction of masonry and concrete structures 4 2 days 6 Crack inspection and sealing 5 2 days 7 Supply and installation of piping 4 10 days 8 Sanding and painting 6;7 2 days 9 Water system sand trap 14 days 10 Removal and disposal of moss and sediments 3 4 days 11 Reconstruction of masonry and concrete structures 10 2 days 12 Crack inspection and sealing 11 2 days 13 Supply and installation of piping and fittings 10 8 days 14 Sanding and painting 12;13 2 days 15 Water system adduction 73 days 16 Excavation and filling 9 20 days 17 Removal and disposal of sediments 16 18 days 18 Reconstruction of masonry and concrete structures 17 5 days 19 Crack inspection and sealing 18 5 days 20 Supply and installation of piping and fittings 17 30 days 21 Sanding and painting 20;19 5 days 22 Water treatment plant 10 days 23 Crack inspection and sealing 15 5 days 24 Supply and installation of piping and fittings 23 3 days 25 Sanding and painting 24 2 days 26 Water system storage tank 11 days 27 Crack inspection and sealing 22 3 days 28 Sanding and painting 27 4 days 29 Tank cleaning and washing 28 4 days TOTAL 127 days
Developed and submitted by: Laura Huertas Page 1 of 1