SECUENCE PROJECT ACTIVITIES


Rehabilitation of the aqueduct system of the Laguna Verde village

WBS ID Activity/ Task Name Predecessor Duration


1 Preliminary 3 days
2 Camp layout, services and office equipment rental 3 days
3 Water system intake 16 days
4 Removal and disposal of moss and sediments 1 4 days
5 Reconstruction of masonry and concrete structures 4 2 days
6 Crack inspection and sealing 5 2 days
7 Supply and installation of piping 4 10 days
8 Sanding and painting 6;7 2 days
9 Water system sand trap 14 days
10 Removal and disposal of moss and sediments 3 4 days
11 Reconstruction of masonry and concrete structures 10 2 days
12 Crack inspection and sealing 11 2 days
13 Supply and installation of piping and fittings 10 8 days
14 Sanding and painting 12;13 2 days
15 Water system adduction 73 days
16 Excavation and filling 9 20 days
17 Removal and disposal of sediments 16 18 days
18 Reconstruction of masonry and concrete structures 17 5 days
19 Crack inspection and sealing 18 5 days
20 Supply and installation of piping and fittings 17 30 days
21 Sanding and painting 20;19 5 days
22 Water treatment plant 10 days
23 Crack inspection and sealing 15 5 days
24 Supply and installation of piping and fittings 23 3 days
25 Sanding and painting 24 2 days
26 Water system storage tank 11 days
27 Crack inspection and sealing 22 3 days
28 Sanding and painting 27 4 days
29 Tank cleaning and washing 28 4 days
TOTAL 127 days

Developed and submitted by: Laura Huertas Page 1 of 1