PROJECT: MAINTENANCE AND REPAIR TANK 2 - SHAYBAH POWER PLANT

ID Task Name Duration Start 4 Mar '24 Apr '24 May '24 Jun '24 Jul '24 A
11 18 25 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28
1 SHAYBAH POWER PLANT TANK 2 145 days Fri 3/1/24
2 Site Mobilization and Preparation 14 days Fri 3/1/24
3 Material Procurement 30 days Fri 3/1/24
4 Installation of Reinforcement for Door Sheet 10 days Sun 3/10/24
5 Cutting of Door Sheet 3 days Wed 3/20/24
6 Ramp Installation 1 day Sat 3/23/24
7 Removal of Internal and External Connections 15 days Sun 3/24/24
8 Removal of Bottom Plates 30 days Sun 3/10/24
9 CP Installation (VCI) 13 days Tue 4/9/24
10 Installation of Scaffolding for External Coating 30 days Fri 3/15/24
11 Wind Girder Fabrication and Installation 35 days Sun 4/14/24
12 Sandblasting and Painting of External Roof 40 days Fri 3/15/24
13 Sandblasting and Painting of External Shell 70 days Fri 4/19/24
14 MFL Inspection for Annular Plate 10 days Mon 4/22/24
15 Annular Plate Repair 14 days Thu 5/2/24
16 Installation of New Bottom Plate 60 days Mon 4/22/24
17 Internal Sanblasting and Painting 30 days Fri 6/21/24
18 Door Sheet Reinstallation 7 days Fri 6/21/24
19 Removal of Ramp 1 day Fri 6/21/24
20 Inspection of Door Sheet RT 7 days Fri 6/21/24
21 Gasket Replacement 7 days Fri 6/21/24
22 Box Up 3 days Sun 7/21/24

Task Project Summary


Split External Tasks
Project: MAINTENANCE AND REPAIR TANK 2 - SHAYBAH POWER PLANT
Progress External Milestone
Date: Sun 2/25/24
Milestone Deadline
Summary