ID Task

Task Name Duration Start Finish Predecessors


Mode
May 21, '23 May 28, '23 Jun 4, '23
T W T F S S M T W T F S S M T W T F S S
1 MGPLS-Shaukat Khanam Cancer 20 days Thu 5/18/23 Sat 6/3/23
Hospital Lahore
2 Tile work,Equipment delivery 2 days Thu 5/18/23 Fri 5/19/23
3 Copper Pipe assembling 2 days Fri 5/19/23 Sat 5/20/23 2
4 Brazing work 1 day Sat 5/20/23 Mon 5/22/23 3
5 New compressor 1 installation 1 day Mon 5/22/23 Tue 5/23/23 4
6 Old compressor 1 dismantling (after 1 day Tue 5/23/23 Tue 5/23/23 5
confirmation from client)
7 Electric connection (Client end) 1 day Tue 5/23/23 Tue 5/23/23 5
8 Tank Plinth work 3 days Tue 5/23/23 Fri 5/26/23 6
9 Tank installation 1 day Fri 5/26/23 Fri 5/26/23 8
10 Leak test of copper pipe 1 day Fri 5/26/23 Sat 5/27/23 9
11 New refregrent dryer installation 1 day Sat 5/27/23 Mon 5/29/23 10
12 Electric connection (Client end) 1 day Mon 5/29/23 Mon 5/29/23 11
13 Old compressor 2 dismantling (after 1 day Mon 5/29/23 Mon 5/29/23 11
confirmation from client)
14 New Compressor 2 installation 1 day Mon 5/29/23 Tue 5/30/23 13
15 Electric connection (Client end) 1 day Tue 5/30/23 Wed 5/31/23 14
16 Old compressor 3 dismantling (after 1 day Tue 5/30/23 Wed 5/31/23 14
confirmation from client)
17 New Compressor 3 installation 1 day Wed 5/31/23 Wed 5/31/23 16
18 Electric connection (Client end) 1 day Wed 5/31/23 Thu 6/1/23 17
19 Old compressor 4 dismantling (after 1 day Wed 5/31/23 Thu 6/1/23 17
confirmation from client)
20 New Compressor 4 installation 1 day Thu 6/1/23 Fri 6/2/23 19
21 Electric connection (Client end) 1 day Fri 6/2/23 Sat 6/3/23 20
22 Connection with main line 1 day Fri 6/2/23 Sat 6/3/23 20

Task Project Summary Manual Task Start-only Deadline

Project: RYK-MGPLS Split Inactive Task Duration-only Finish-only Progress


Date: Mon 5/22/23 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 1