T4 Emery EPCM schedule 230811

ID WBS Task Name Duration Start Actual Start Finish 2024


2022 2023 2024 2025
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
1 1 EMERY Oleochemicals EPCM 122.4 wks Mon 2/13/23 Mon 2/13/23 Tue 6/17/25 EMERY Oleochemicals EPCM 6/17
2 1.1 Project Milestones 122.4 wks Mon 2/13/23 Mon 2/13/23 Tue 6/17/25 Project Milestones 6/17

3 1.1.1 Start Project 0.2 wks Mon 2/13/23 Mon 2/13/23 Mon 2/13/23 1.1.1
4 1.1.2 Completion eBEP (extended 8.8 wks Wed 5/31/23 Wed 5/31/23 Mon 7/31/23 n eBEP (extended Basic Engineering Package) 7/31
Basic Engineering Package)

5 1.1.2.1 Cost Estimation 15% 0.2 wks Wed 5/31/23 Wed 5/31/23 Wed 5/31/23 1.1.2.1
6 1.1.2.2 Cost Estimation 5% 0 wks Mon 7/31/23 NA Mon 7/31/23 Cost Estimation 5% 7/31
7 1.1.2.3 ITB/MRQ/RFQ for EPCM contrac0 wks Mon 7/31/23 NA Mon 7/31/23 ITB/MRQ/RFQ for EPCM contract 7/31
8 1.1.2.4 ITB/MRQ/RFQ for Civil 0 wks Mon 7/31/23 NA Mon 7/31/23 ITB/MRQ/RFQ for Civil Structure Architecture 7/31
Structure Architecture

9 1.1.2.5 ITB/MRQ/RFQ for long delivery 0 wks Mon 7/31/23 NA Mon 7/31/23 ITB/MRQ/RFQ for long delivery equipment 7/31
equipment

10 1.1.3 Completion Detailed Design EPC0 wks Tue 2/27/24 NA Tue 2/27/24 Completion Detailed Design EPCM 2/27
11 1.1.4 Completion EPCM Contractor 0 wks Fri 11/24/23 NA Fri 11/24/23 Completion EPCM Contractor Tender Process 11/24
Tender Process

12 1.1.5 Final Investment Decision 0 wks Wed 11/29/23 NA Wed 11/29/23 Final Investment Decision 11/29
13 1.1.6 EPCM Contractor contract 1 wk Wed 11/29/23 NA Tue 12/5/23 1.1.6
agreement

14 1.1.7 Completion Procurement EPCM 0 wks Tue 4/23/24 NA Tue 4/23/24 Completion Procurement EPCM 4/23
15 1.1.8 Start Construction 0 wks Wed 12/6/23 NA Wed 12/6/23 Start Construction 12/6
16 1.1.9 Project Handover / Finish Project0 wks Tue 6/17/25 NA Tue 6/17/25 Project Handover / Finish Project 6/17
17 1.2 EPCM Contractor Tender Process 16 wks Mon 8/7/23 NA Fri 11/24/23 EPCM Contractor Tender Process 11/24
18 1.2.1 Share RFQ to EPCM Contractors 1 wk Mon 8/7/23 NA Fri 8/11/23 0%
19 1.2.2 Tender Clarification 10 wks Mon 8/14/23 NA Fri 10/20/23 0%
20 1.2.3 Tender Submission 2 wks Mon 10/23/23 NA Fri 11/3/23 1.2.3
21 1.2.4 Tender Evaluation 3 wks Mon 11/6/23 NA Fri 11/24/23 1.2.4
22 1.3 Engineering 54.4 wks Mon 2/13/23 NA Tue 2/27/24 Engineering 2/27

23 1.3.1 eBEP (extended Basic 25 wks Mon 2/13/23 NA Fri 8/4/23 xtended Basic Engineering Package) 8/4
Engineering Package)

24 1.3.1.1 Basic Design 15.6 wks Mon 2/13/23 NA Wed 5/31/23 1.3.1.1
25 1.3.1.2 BD Cost Estimate (15%) 2 wks Thu 5/18/23 NA Wed 5/31/23 1.3.1.2

Critical Progress Start-only Baseline Summary Inactive Task


Task Finish-only Baseline Split Manual Summary Inactive Milestone
Split Duration-only Baseline Milestone Project Summary Inactive Summary
Task Progress Critical Milestone External Tasks Deadline
Manual Task Critical Split Summary Progress External Milestone

Page 1
T4 Emery EPCM schedule 230811
ID WBS Task Name Duration Start Actual Start Finish 2024
2022 2023 2024 2025
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
26 1.3.1.3 BD Update Comments / Value 1.4 wks Thu 6/1/23 NA Fri 6/9/23 1.3.1.3
Engineering Review

27 1.3.1.4 Extended Basic Design 43 days Thu 6/1/23 NA Mon 7/31/23 1.3.1.4
28 1.3.1.5 Extended BD Cost Estimation (5 2 wks Tue 7/18/23 NA Mon 7/31/23 1.3.1.5
29 1.3.1.6 Final Approval 0.8 wks Tue 8/1/23 NA Fri 8/4/23 1.3.1.6
30 1.3.2 Detailed Design Stage (DD) EPCM12 wks Wed 12/6/23 NA Tue 2/27/24 Detailed Design Stage (DD) EPCM 2/27
31 1.3.2.1 Detailed Design 10 wks Wed 12/6/23 NA Tue 2/13/24 1.3.2.1
32 1.3.2.2 90% Review (By Client) 5 days Wed 2/14/24 NA Tue 2/20/24 90% Review (By Client) 2/20
33 1.3.2.3 DD Update Comments / Value 1 wk Wed 2/14/24 NA Tue 2/20/24 1.3.2.3
Engineering Review

34 1.3.2.4 DD Cost Estimate 2 wks Wed 1/31/24 NA Tue 2/13/24 1.3.2.4


35 1.3.2.5 DD Report submission 1 day Wed 2/21/24 NA Wed 2/21/24 1.3.2.5
36 1.3.2.6 DD Final Review Approval (by 0.8 wks Thu 2/22/24 NA Tue 2/27/24 1.3.2.6
Client)

37 1.4 Procurement for Vendor/Contractor20 wks Wed 12/6/23 NA Tue 4/23/24 Procurement for Vendor/Contractor 4/23

38 1.4.1 Pre-tendering 12 wks Wed 12/6/23 NA Tue 2/27/24 Pre-tendering 2/27


39 1.4.1.1 Project Procurement Plan 2 wks Wed 12/6/23 NA Tue 12/19/23 1.4.1.1
40 1.4.1.2 Prepration of Tender Document 2 wks Wed 12/20/23 NA Tue 1/2/24 1.4.1.2
41 1.4.1.3 Pre-Qualification 2 wks Wed 2/14/24 NA Tue 2/27/24 1.4.1.3
42 1.4.2 Tendering Process 20 wks Wed 12/6/23 NA Tue 4/23/24 Tendering Process 4/23
43 1.4.2.1 CSA Building Services & 2 mons Wed 2/28/24 NA Tue 4/23/24 1.4.2.1
Infrastructure

44 1.4.2.2 Mechanical Electrical 2 mons Wed 2/28/24 NA Tue 4/23/24 1.4.2.2


Instrumentation

45 1.4.2.3 Beading Tower (Chant Oil) 2 wks Wed 12/6/23 NA Tue 12/19/23 1.4.2.3
46 1.4.2.4 Mechanical Packages and Long 2 mons Wed 12/6/23 NA Tue 1/30/24 1.4.2.4
Lead Items

47 1.5 Construction 80 wks Wed 12/6/23 NA Tue 6/17/25 Construction 6/17

48 1.5.1 Construction Works 68 wks Wed 12/6/23 NA Tue 3/25/25 Construction Works 3/25
49 1.5.1.1 Site Preparation (By Kinra) 26 wks Wed 12/6/23 NA Tue 6/4/24 Site Preparation (By Kinra) 6/4
50 1.5.1.1.1 Tender Preparation 1 wk Wed 12/6/23 NA Tue 12/12/23 1.5.1.1.1

Critical Progress Start-only Baseline Summary Inactive Task


Task Finish-only Baseline Split Manual Summary Inactive Milestone
Split Duration-only Baseline Milestone Project Summary Inactive Summary
Task Progress Critical Milestone External Tasks Deadline
Manual Task Critical Split Summary Progress External Milestone

Page 2
T4 Emery EPCM schedule 230811
ID WBS Task Name Duration Start Actual Start Finish 2024
2022 2023 2024 2025
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
51 1.5.1.1.2 Tendering Process 2 mons Wed 12/13/23 NA Tue 2/6/24 1.5.1.1.2
52 1.5.1.1.3 Site Preparation Construction 4 mons Wed 2/7/24 NA Tue 5/28/24 1.5.1.1.3
53 1.5.1.1.4 Handover site 1 wk Wed 5/29/24 NA Tue 6/4/24 1.5.1.1.4
54 1.5.1.2 CSA Building Services & 47 wks Wed 4/24/24 NA Tue 3/18/25 CSA Building Services & Infrastructure 3/18
Infrastructure

55 1.5.1.2.1 Contract Agreement 1 wk Wed 4/24/24 NA Tue 4/30/24 1.5.1.2.1


56 1.5.1.2.2 Manufacturing 8 wks Wed 5/1/24 NA Tue 6/25/24 1.5.1.2.2
57 1.5.1.2.3 Mobilization 1 wk Wed 6/5/24 NA Tue 6/11/24 1.5.1.2.3
58 1.5.1.2.4 CSA Building Services & 10 mons Wed 6/12/24 NA Tue 3/18/25 1.5.1.2.4
Infrastructure Works

59 1.5.1.2.5 Infrastructure (road, drainage, 7 mons Wed 6/12/24 NA Tue 12/24/24 1.5.1.2.5
60 1.5.1.3 Mechanical Electrical 48 wks Wed 4/24/24 NA Tue 3/25/25 Mechanical Electrical Instrumentation 3/25
Instrumentation

61 1.5.1.3.1 Contract Agreement 1 wk Wed 4/24/24 NA Tue 4/30/24 1.5.1.3.1


62 1.5.1.3.2 Manufacturing 14 wks Wed 5/1/24 NA Tue 8/6/24 1.5.1.3.2
63 1.5.1.3.3 Mobilization 1 wk Wed 9/4/24 NA Tue 9/10/24 1.5.1.3.3
64 1.5.1.3.4 Mechanical Electrical 7 mons Wed 9/11/24 NA Tue 3/25/25 1.5.1.3.4
Instrumentation Works

65 1.5.1.4 Mechanical Package 62 wks Wed 12/20/23 NA Tue 2/25/25 Mechanical Package 2/25
66 1.5.1.4.1 Beading Tower (Chant Oil) 60 wks Wed 12/20/23 NA Tue 2/11/25 Beading Tower (Chant Oil) 2/11
67 1.5.1.4.1. Fabrication and Delivery 9 mons Wed 12/20/23 NA Tue 8/27/24 1.5.1.4.1.1
68 1.5.1.4.1. Installation 6 mons Wed 8/28/24 NA Tue 2/11/25 1.5.1.4.1.2
69 1.5.1.4.2 Mechanical Packages and 56 wks Wed 1/31/24 NA Tue 2/25/25 Mechanical Packages and Long Lead Items 2/25
Long Lead Items

70 1.5.1.4.2. Fabrication and Delivery 13 mons Wed 1/31/24 NA Tue 1/28/25 1.5.1.4.2.1
71 1.5.1.4.2. Installation 4 mons Wed 11/6/24 NA Tue 2/25/25 1.5.1.4.2.2
72 1.5.2 Commissioning 6 mons Wed 12/4/24 NA Tue 5/20/25 1.5.2
73 1.5.3 Customer Acceptances 2 wks Wed 5/21/25 NA Tue 6/3/25 1.5.3
74 1.5.4 Start up 2 wks Wed 6/4/25 NA Tue 6/17/25 1.5.4

Critical Progress Start-only Baseline Summary Inactive Task


Task Finish-only Baseline Split Manual Summary Inactive Milestone
Split Duration-only Baseline Milestone Project Summary Inactive Summary
Task Progress Critical Milestone External Tasks Deadline
Manual Task Critical Split Summary Progress External Milestone