ID Task Name Duration Start Finish Predecessors arter 4th Quarter 1st Quarter 2nd Quarter 3rd Quarter

Start Finish Predecessors arter 4th Quarter 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
1 L-II PROJECT SHEDULE 334 days Mon 9/27/21 Thu 10/20/22
2 ORDER DATE 1 day Mon 9/27/21 Mon 9/27/21
3 BASIC ENGINEERING ELECTRICAL 82 days Sat 12/11/21 Fri 4/1/22
4 Name Plate 1 day Sat 12/11/21 Sat 12/11/21
5 Drawing Numbering System 1 day Sat 12/11/21 Sat 12/11/21
6 Master List of Drawings 1 day Mon 12/20/21 Mon 12/20/21
7 Approval of Master list of drawing 2 days Tue 12/21/21 Wed 12/22/21 6
8 Equipment List 1 day Mon 12/20/21 Mon 12/20/21
9 Approval of Equipment list 2 days Tue 12/21/21 Wed 12/22/21 8
10 L2 Network 1 day Sat 1/15/22 Sat 1/15/22
11 Approval of L2 Network 2 days Mon 1/17/22 Tue 1/18/22 10
12 QAP 1 day Mon 1/3/22 Mon 1/3/22
13 Approval of QAP 2 days Tue 1/4/22 Wed 1/5/22 12
14 Equipment Layout of Substation 17 of Wire Rod Mill. 1 day Mon 1/3/22 Mon 1/3/22
15 Approval of Equipment layout of SS17 of wire rod mill 2 days Tue 1/4/22 Wed 1/5/22 14
16 SLD of Sub-Station 17 (Wire Rod Mill) 1 day Mon 1/3/22 Mon 1/3/22
17 Approval of SLD of SS17 2 days Tue 1/4/22 Wed 1/5/22 16
18 Data Sheet of 6.6KV, 1250A VCB 1 day Mon 1/3/22 Mon 1/3/22
19 Approval of data sheet of VCB 2 days Tue 1/4/22 Wed 1/5/22 18
20 Data Sheet of 1000KVA, 6.6KV/0.433 KV Dry Type Transformer 1 day Mon 1/3/22 Mon 1/3/22
21 Approval of Data sheet of Dry type Transformer 2 days Tue 1/4/22 Wed 1/5/22 20
22 Data Sheet of Numerical Relays 1 day Mon 1/3/22 Mon 1/3/22
23 Approval of of Data sheet of Numerical Relay 2 days Tue 1/4/22 Wed 1/5/22 22
24 Data Sheet of HT & LT Cable 1 day Sat 1/15/22 Sat 1/15/22
25 Approval of data sheet of HT & LT cable 2 days Mon 1/17/22 Tue 1/18/22 24
26 Configuration diagram of SCADA System 1 day Wed 3/30/22 Wed 3/30/22
27 Approval of Configuration diagram of SCADA system 2 days Thu 3/31/22 Fri 4/1/22 26
28 DETAIL ENGINEERING ELECTRICAL 185 days Tue 1/25/22 Mon 10/10/22
29 GA, Scheme & BOM of 6.6KV, 1250A VCB Panel 15 days Tue 1/25/22 Mon 2/14/22
30 Approval of GA - VCB panel 1 day Tue 2/15/22 Tue 2/15/22 29
31 GA drawing of 1000KVA, 6.6KV/0.433 KV Dry Type Transformer 7 days Tue 2/15/22 Wed 2/23/22
32 Approval of GA - dry type Transformer 1 day Thu 2/24/22 Thu 2/24/22 31
33 GA & Data Sheet of DCDB, Battery Charger & Battery 15 days Wed 3/2/22 Tue 3/22/22
34 Approval of GA & Data Sheet of DCDB, Battery Charger & Battery 1 day Wed 3/23/22 Wed 3/23/22 33
35 GA, Scheme & BOM of PCC Panel 7 days Thu 2/24/22 Fri 3/4/22
36 Approval of GA, Scheme & BOM of PCC Panel 1 day Mon 3/7/22 Mon 3/7/22 35
37 Cable Schedule 15 days Wed 3/30/22 Tue 4/19/22
38 Design & Layout of Earthing System. 7 days Wed 3/30/22 Thu 4/7/22
39 GA & BOM of SCADA Equipment 2 days Wed 3/30/22 Thu 3/31/22
40 Approval of GA & BOM of SCADA Equipment 1 day Fri 4/1/22 Fri 4/1/22 39
41 Cable Layout of Scada System 7 days Wed 3/30/22 Thu 4/7/22
42 CIVIL Foundation drawing of VCB, Transformer & PCC panel. 7 days Thu 3/3/22 Fri 3/11/22
43 Operation, Maintenance & Erection Manual 1 day Mon 10/10/22 Mon 10/10/22
44 PROCUREMENT & SUPPLY 104 days Wed 2/16/22 Mon 7/11/22
45 TRANSFORMER 74 days Thu 2/24/22 Tue 6/7/22
46 Purchase Order Placement 1 day Thu 2/24/22 Thu 2/24/22 21,31
47 GTP Submission 1 day Fri 2/25/22 Fri 2/25/22 46
48 GTP Approval 1 day Mon 2/28/22 Mon 2/28/22 47
49 MQP Submission 7 days Tue 3/1/22 Wed 3/9/22 48
50 MQP Approval 7 days Thu 3/10/22 Fri 3/18/22 49
51 Mfg Clearance to Vendor 1 day Mon 3/21/22 Mon 3/21/22 50
52 Manufacturing 45 days Tue 3/22/22 Mon 5/23/22 51
53 Inspection / Factory acceptance Test 3 days Tue 5/24/22 Thu 5/26/22 52
54 Dispatch Clearence 1 day Fri 5/27/22 Fri 5/27/22 53
55 Delivery at Site 7 days Mon 5/30/22 Tue 6/7/22 54
56 VCB PANEL 59 days Wed 2/16/22 Mon 5/9/22
57 Purchase Order Placement 1 day Wed 2/16/22 Wed 2/16/22 19,30
58 GTP Submission 1 day Thu 2/17/22 Thu 2/17/22 57
59 GTP Approval 1 day Fri 2/18/22 Fri 2/18/22 58

Project: L-II NETWORK_2851 Task Progress Summary External Tasks Deadline


Date: Tue 1/4/22 Split Milestone Project Summary External Milestone

Page 1
ID Task Name Duration Start Finish Predecessors arter 4th Quarter 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
60 MQP Submission 7 days Mon 2/21/22 Tue 3/1/22 59
61 MQP Approval 7 days Wed 3/2/22 Thu 3/10/22 60
62 Mfg Clearance to Vendor 1 day Fri 3/11/22 Fri 3/11/22 61
63 Manufacturing 30 days Mon 3/14/22 Fri 4/22/22 62
64 Inspection / Factory acceptance Test 3 days Mon 4/25/22 Wed 4/27/22 63
65 Dispatch Clearence 1 day Thu 4/28/22 Thu 4/28/22 64
66 Delivery at Site 7 days Fri 4/29/22 Mon 5/9/22 65
67 SCADA SYSTEM 59 days Mon 4/4/22 Thu 6/23/22
68 Purchase Order Placement 1 day Mon 4/4/22 Mon 4/4/22 27,40
69 GTP Submission 1 day Tue 4/5/22 Tue 4/5/22 68
70 GTP Approval 1 day Wed 4/6/22 Wed 4/6/22 69
71 MQP Submission 7 days Thu 4/7/22 Fri 4/15/22 70
72 MQP Approval 7 days Mon 4/18/22 Tue 4/26/22 71
73 Mfg Clearance to Vendor 1 day Wed 4/27/22 Wed 4/27/22 72
74 Manufacturing 30 days Thu 4/28/22 Wed 6/8/22 73
75 Inspection / Factory acceptance Test 3 days Thu 6/9/22 Mon 6/13/22 74
76 Dispatch Clearence 1 day Tue 6/14/22 Tue 6/14/22 75
77 Delivery at Site 7 days Wed 6/15/22 Thu 6/23/22 76
78 PCC PANEL 59 days Tue 3/8/22 Fri 5/27/22
79 Purchase Order Placement 1 day Tue 3/8/22 Tue 3/8/22 36
80 GTP Submission 1 day Wed 3/9/22 Wed 3/9/22 79
81 GTP Approval 1 day Thu 3/10/22 Thu 3/10/22 80
82 MQP Submission 7 days Fri 3/11/22 Mon 3/21/22 81
83 MQP Approval 7 days Tue 3/22/22 Wed 3/30/22 82
84 Mfg Clearance to Vendor 1 day Thu 3/31/22 Thu 3/31/22 83
85 Manufacturing 30 days Fri 4/1/22 Thu 5/12/22 84
86 Inspection / Factory acceptance Test 3 days Fri 5/13/22 Tue 5/17/22 85
87 Dispatch Clearence 1 day Wed 5/18/22 Wed 5/18/22 86
88 Delivery at Site 7 days Thu 5/19/22 Fri 5/27/22 87
89 HT & LT Cable 59 days Wed 4/20/22 Mon 7/11/22
90 Purchase Order Placement 1 day Wed 4/20/22 Wed 4/20/22 25,37
91 GTP Submission 1 day Thu 4/21/22 Thu 4/21/22 90
92 GTP Approval 1 day Fri 4/22/22 Fri 4/22/22 91
93 MQP Submission 7 days Mon 4/25/22 Tue 5/3/22 92
94 MQP Approval 7 days Wed 5/4/22 Thu 5/12/22 93
95 Mfg Clearance to Vendor 1 day Fri 5/13/22 Fri 5/13/22 94
96 Manufacturing 30 days Mon 5/16/22 Fri 6/24/22 95
97 Inspection / Factory acceptance Test 3 days Mon 6/27/22 Wed 6/29/22 96
98 Dispatch Clearence 1 day Thu 6/30/22 Thu 6/30/22 97
99 Delivery at Site 7 days Fri 7/1/22 Mon 7/11/22 98
100 UPS SYSTEM WITH BATTERY, BATTERY CHARGER UPS DB 59 days Thu 3/24/22 Tue 6/14/22
101 Purchase Order Placement 1 day Thu 3/24/22 Thu 3/24/22 34
102 GTP Submission 1 day Fri 3/25/22 Fri 3/25/22 101
103 GTP Approval 1 day Mon 3/28/22 Mon 3/28/22 102
104 MQP Submission 7 days Tue 3/29/22 Wed 4/6/22 103
105 MQP Approval 7 days Thu 4/7/22 Fri 4/15/22 104
106 Mfg Clearance to Vendor 1 day Mon 4/18/22 Mon 4/18/22 105
107 Manufacturing 30 days Tue 4/19/22 Mon 5/30/22 106
108 Inspection / Factory acceptance Test 3 days Tue 5/31/22 Thu 6/2/22 107
109 Dispatch Clearence 1 day Fri 6/3/22 Fri 6/3/22 108
110 Delivery at Site 7 days Mon 6/6/22 Tue 6/14/22 109
111 CABLE TRAY, TERMINATION KIT & ACCESSORIES 59 days Wed 4/20/22 Mon 7/11/22
112 Purchase Order Placement 1 day Wed 4/20/22 Wed 4/20/22 37
113 GTP Submission 1 day Thu 4/21/22 Thu 4/21/22 112
114 GTP Approval 1 day Fri 4/22/22 Fri 4/22/22 113
115 MQP Submission 7 days Mon 4/25/22 Tue 5/3/22 114
116 MQP Approval 7 days Wed 5/4/22 Thu 5/12/22 115
117 Mfg Clearance to Vendor 1 day Fri 5/13/22 Fri 5/13/22 116
118 Manufacturing 30 days Mon 5/16/22 Fri 6/24/22 117

Project: L-II NETWORK_2851 Task Progress Summary External Tasks Deadline


Date: Tue 1/4/22 Split Milestone Project Summary External Milestone

Page 2
ID Task Name Duration Start Finish Predecessors arter 4th Quarter 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
119 Inspection / Factory acceptance Test 3 days Mon 6/27/22 Wed 6/29/22 118
120 Dispatch Clearence 1 day Thu 6/30/22 Thu 6/30/22 119
121 Delivery at Site 7 days Fri 7/1/22 Mon 7/11/22 120
122 ERECTION 104 days Mon 3/14/22 Thu 8/4/22
123 CIVIL WORK 30 days Mon 3/14/22 Fri 4/22/22 42
124 TRANSFORMER 3 days Wed 6/8/22 Fri 6/10/22 55
125 VCB PANEL 5 days Tue 5/10/22 Mon 5/16/22 66
126 PCC PANEL 5 days Mon 5/30/22 Fri 6/3/22 88
127 SCADA SYSTEM 15 days Fri 6/24/22 Thu 7/14/22 77
128 UPS SYSTEM 5 days Wed 6/15/22 Tue 6/21/22 110
129 CABLE SUPPORT STRUCTURE 7 days Tue 7/12/22 Wed 7/20/22 121
130 CABLE LAYING 3 days Tue 7/12/22 Thu 7/14/22 99
131 CABLE TERMINATION 15 days Fri 7/15/22 Thu 8/4/22 121,130,124,125,126,127,128

132 SHUT DOWN 5 days Fri 8/5/22 Thu 8/11/22 131


133 CEA INSPECTION 10 days Fri 7/29/22 Thu 8/11/22 131FS-5 days
134 TESTING & COMMISSIONING 45 days Fri 8/5/22 Thu 10/6/22 131
135 HAND OVER & TRAINING SESSION TO CLIENT 10 days Fri 10/7/22 Thu 10/20/22 134

Project: L-II NETWORK_2851 Task Progress Summary External Tasks Deadline


Date: Tue 1/4/22 Split Milestone Project Summary External Milestone