2954 Penry Street

Construction Programme Rev C- 04-10-23


ID Task Task Name Start Finish Late Start Late Finish Free Slack Qtr 4, 2021 Qtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024
1 233-247 Old Kent Road project - Thu 2/7/19 Fri 12/15/23 Thu 2/7/19 Tue 1/2/24 5 days?
Construction Programme
12 Pre-construction stage Wed 10/6/21 Mon 8/29/22Wed 10/6/21Mon 8/29/22 0 days
14 Technical Design - RIBA Stage 4 Mon 11/1/21 Mon 8/29/22Mon 11/1/21Mon 8/29/22 0 days
84 Discharge pre-commencement Wed Tue Wed Tue 5 days
planning conditions 10/6/21 1/11/22 10/6/21 1/18/22
136 Pre-construction services Tue 11/9/21 Fri 2/18/22Tue 11/9/21 Fri 2/18/22 0 days
160 Construction Stage Mon 9/27/21 Tue 1/2/24Mon 9/27/21 Tue 1/2/24 0 days?
161 Construction Stage - tender package Wed Thu 11/3/22 Wed Thu 0 days
procurement 3/23/22 3/23/22 11/3/22
203 Structure (Zone 1 & 2) Thu 6/16/22 Tue 1/2/24Thu 6/16/22 Tue 1/2/24 0 days?
207 Temporay Pedestrian walkway in Wed 5/3/23 Mon Wed 5/3/23 Mon 10/30/23 0 days
Operation Deliveries only 10/30/23
230 External mastic to Balconies Wed 4/26/23Tue 10/24/23Wed 4/26/23
Tue 10/24/23 0 days
233 Core A watertight, Riser to be done, Fri 6/30/23 Wed Fri 6/30/23 Tue 0 days
roof to be installed at the top of the 12/13/23 10/24/23
riser, onsite awaiting e&d to install

234 Private Amenity Roof Terrace Wed 5/31/23 Fri 11/17/23Wed 5/31/23Fri 11/17/23 0 days
235 Install rainwater goods Wed 5/31/23 Fri 11/17/23Wed 5/31/23Fri 11/17/23 0 days
237 Standing seem / Copings Wed 5/31/23 Fri 12/8/23Wed 5/31/23 Fri 12/8/23 0 wks
238 Install AOV - roof hatches Wed 6/28/23 Fri 11/10/23Wed 6/28/23Fri 11/10/23 0 days
240 Terrace balustrade installation (Core Wed Mon 10/2/23 Wed Mon 0 days
B) 7/12/23 7/12/23 10/2/23
242 Lightning protection Wed 7/12/23 Fri 11/17/23Wed 7/12/23Fri 11/17/23 0 days
244 Fit Curtain walling & external doors Mon 7/17/23 Fri 7/28/23 Mon Fri 7/28/23 0 days
GFL - TBC 7/17/23
245 Lift installation [Core A & B Lifts] Fri 7/21/23Mon 12/18/23 Fri 7/21/23
Mon 12/18/23 0 days
246 External inspections - snag & de-snagMon 7/17/23Mon 11/20/23Mon 7/17/23
Mon 11/20/23 0 days
249 Internal staircase handrails and Fri 7/21/23 Thu Fri 7/21/23 Thu 0 wks
Ballustrades 11/30/23 11/30/23
250 Core A Mon 2/6/23Mon 12/11/23 Mon 2/6/23
Thu 12/21/23 8 days
251 Internal fitout Zone 1 - [11 No Mon 2/6/23 Mon Mon 2/6/23 Tue 1 day
flats] 12/11/23 12/12/23
252 Flat 1 - GF - 2B4P(W) Private Mon 2/6/23 Tue Mon 2/6/23 Tue 0 days
(85.6 m²) 10/24/23 10/24/23
297 Flat 4 - level 1 - 2B4P Private Mon 2/6/23 Fri 11/17/23 Mon 2/6/23 Fri 0 days
(74.4m²) - Show Flat / 11/17/23
Benchmark

Task External Tasks Duration-only External Tasks Deadline

Project: 2954 Penry Street Split External Milestone Manual Summary Rollup External Milestone
Date:17//07/2023 Milestone Inactive Milestone Manual Summary Critical
Revision B
Summary Inactive Summary Start-only Critical Split
Project Summary Manual Task Finish-only Progress

Page 1
2954 Penry Street
Construction Programme Rev C- 04-10-23
ID Task Task Name Start Finish Late Start Late Finish Free Slack Qtr 4, 2021 Qtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024
657 Flat 23 - level 04- 2B4P Private Wed Fri 11/17/23 Wed Fri 0 days
(80.8m²) 2/22/23 2/22/23 11/17/23
702 Flat 24 - level 04- 2B4P Private Wed Fri 11/17/23 Wed Fri 0 days
(71.9m²) 2/22/23 2/22/23 11/17/23
747 Commercial area 1 class A1/A2 Fri 7/21/23 Fri 11/10/23 Fri 7/21/23 Fri 0 days
Retail unit - (56.7m²) [Marketing 11/10/23
Suite - Show Room]

777 Communal area circulation Thu 7/13/23 Fri 11/10/23 Thu Tue 0 days
Core A Hallway & stair 7/13/23 12/12/23
807 Bicycle stores x 2 no,. (7.m² & Fri 7/21/23 Tue Fri 7/21/23 Tue 0 days
31.9m²] 12/12/23 12/12/23
810 LV room [6.7m²] Mon 7/24/23 Fri 11/17/23Mon 7/24/23Fri 11/17/23 0 days
812 Core A - Completion dates Fri 12/15/23 Fri 12/15/23Fri 12/15/23
Thu 12/21/23 4 days
816 Core B Fri 12/15/23 Fri 12/15/23Fri 12/15/23Fri 12/15/23 0 days
817 Internal fitout Zone 2 - [13 No. Fri 12/15/23 Fri 12/15/23 Fri Fri 0 days
flats] 12/15/23 12/15/23
818 Flat 2 - GF - 2B4P(W) Social Tue Tue Tue Tue 0 days 10/17
rented flat (89.6m²) 10/17/23 10/17/23 10/17/23 10/17/23
863 Flat 3 - GF - 1B2P(W) Social Fri 10/20/23 Tue Fri Tue 0 days
rented flat (65.7m²) 10/24/23 10/20/23 10/24/23
908 Flat 7 - level 01 - 2B4P Social Fri 10/27/23 Mon 11/6/23 Fri Thu 2.5 days
rented flat (75.2m²) 10/27/23 11/9/23
953 Flat 8 - level 01 - 1B2P Social Fri 2/17/23 Mon 11/6/23 Fri 2/17/23 Mon 0 days
rented flat (51.7 m²) 11/6/23
998 Flat 9 - level 01 - 1B2P Social Fri 2/17/23 Mon 11/6/23 Fri 2/17/23 Mon 0 days
rented flat (50.8m²) 11/6/23
1043 Flat 10 - level 01 -2B4P Social Thu 2/23/23 Mon 11/6/23 Thu Mon 0 days
rented flat (76.1m²) 2/23/23 11/6/23
1088 Flat 14 - level 02 - 2B4P Social Thu 2/23/23 Mon Thu Mon 0 days
rented flat (75.2m²) 11/20/23 2/23/23 11/20/23
1133 Flat 15 - level 02 - 1B2P Social Thu 2/23/23 Mon Thu Mon 0 days
rented flat (51.1m²) 11/20/23 2/23/23 11/20/23
1178 Flat 16 - level 02 - 1B2P Social Wed 3/1/23 Mon Wed 3/1/23 Mon 0 days
rented flat (50.8m²) 11/20/23 11/20/23
1223 Flat 17- level 02 - 2B4P Social Wed 3/1/23 Mon Wed 3/1/23 Mon 0 days
rented flat (76.1m²) 11/20/23 11/20/23
1268 Flat 20 - level 03 - 2B3P Social Tue 3/7/23 Wed Tue 3/7/23 Wed 0 days
rented flat (65.4m²) 12/6/23 12/6/23
1313 Flat 21 - level 03 - 1B2P Social Tue 3/7/23 Wed Tue 3/7/23 Wed 0 days
rented flat (50.9m²) 12/6/23 12/6/23

Task External Tasks Duration-only External Tasks Deadline

Project: 2954 Penry Street Split External Milestone Manual Summary Rollup External Milestone
Date:17//07/2023 Milestone Inactive Milestone Manual Summary Critical
Revision B
Summary Inactive Summary Start-only Critical Split
Project Summary Manual Task Finish-only Progress

Page 2
2954 Penry Street
Construction Programme Rev C- 04-10-23
ID Task Task Name Start Finish Late Start Late Finish Free Slack Qtr 4, 2021 Qtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024
1358 Flat 22 - level 03 - 2B4PSocial Tue 3/7/23 Wed Tue 3/7/23 Wed 0 days
rented flat (75.3m²) 12/6/23 12/6/23
1403 Communal area circulation Mon 2/6/23 Fri 12/15/23 Mon 2/6/23 Fri 0 days
Core B Hallway & stair 12/15/23
1433 GF corridor delayed due to rear Tue 5/23/23 Fri 12/15/23 Tue 5/23/23 Thu 12/21/23 4 days
wall remedial works
1513 Section 4 - External works amenity Tue Fri 12/15/23 Tue Tue 1/2/24 5 days?
area 10/24/23 10/24/23
1514 Rear wall remedial works Mon 5/22/23 Fri 12/15/23 Mon 5/22/23 Fri 12/15/23 0 days
1515 Render repairs to rear boundary Mon 5/22/23 Fri 12/15/23 Mon 5/22/23 Fri 12/15/23 0 days
wall
1516 Works placed on hold due to Fri 6/2/23 Fri 12/15/23 Fri 6/2/23 Fri 12/15/23 0 days
stability issues
1521 Client instruction works - Date Fri 12/15/23 Fri 12/15/23 Fri 12/15/23 Fri 12/15/23 0 days 12/15
TBC
1525 remedial works to wall Mon 12/18/23 Tue 1/2/24 Thu 9/28/23 Wed 10/4/23 0 wks
1526 External works - hard Thu 8/31/23 Mon Thu Mon 0 days
landscaping 12/4/23 8/31/23 12/4/23
1531 Build up & pave hard Mon 11/6/23 Wed Mon Wed 0 days
landscaping area permeable 11/15/23 11/6/23 11/15/23
surfacing
1532 Install external lighting& bollardsThu 11/16/23Mon 11/20/23
Thu 11/16/23
Mon 11/20/23 0 days
1533 Install external street furniture Tue 11/21/23 Fri 11/24/23
Tue 11/21/23Fri 11/24/23 0 days
1534 Install private amenity fencing Mon 11/27/23Thu 11/30/23
Mon 11/27/23
Thu 11/30/23 0 days
1535 External inspections - snag& Fri 12/1/23 Mon 12/4/23 Fri 12/1/23 Mon 0 days
de-snag 12/4/23
1536 Handover Mon 12/4/23 Mon 12/4/23Mon 12/4/23Mon 12/4/23 0 days 12/4
1537 External works - soft Mon Fri 12/15/23 Mon Fri 0 days?
landscaping 10/23/23 10/23/23 12/15/23
1538 Reduced level dig Mon 10/23/23 Fri 10/27/23
Mon 10/23/23Fri 10/27/23 0 days
1539 Excavate soft landscaping Mon Fri 11/3/23 Mon Fri 11/3/23 0 days
areas to formation level 10/30/23 10/30/23
1540 Remove excavated soil from siteMon 10/30/23 Fri 11/3/23
Mon 10/30/23 Fri 11/3/23 0 days
1542 Thu 11/16/23Mon 11/27/23
Thu 11/16/23
Mon 11/27/23 0 days
1543 Install children’s play area Tue Fri 12/8/23 Tue Fri 12/8/23 0 days
equipment 11/28/23 11/28/23
1544 External inspections – snag & Mon Fri 12/15/23 Mon Fri 0 days
de-snag 12/11/23 12/11/23 12/15/23
1545 Handover Fri 12/15/23 Fri 12/15/23Fri 12/15/23Fri 12/15/23 0 days 12/15
1546 <New Task> Mon 10/23/23 Mon 10/23/23 Fri 12/15/23 Fri 12/15/23 39 days?

Task External Tasks Duration-only External Tasks Deadline

Project: 2954 Penry Street Split External Milestone Manual Summary Rollup External Milestone
Date:17//07/2023 Milestone Inactive Milestone Manual Summary Critical
Revision B
Summary Inactive Summary Start-only Critical Split
Project Summary Manual Task Finish-only Progress

Page 3
2954 Penry Street
Construction Programme Rev C- 04-10-23
ID Task Task Name Start Finish Late Start Late Finish Free Slack Qtr 4, 2021 Qtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024
1547 Section 278 works - extent Mon Fri 11/3/23 Mon Fri 30 days
TBC 10/24/22 10/24/22 12/15/23
1548 Submit details to Highways / Mon Mon Mon Mon 0 days
TFL 10/24/22 10/24/22 10/24/22 10/24/22
1554 Erection & Mon 10/9/23 Fri 11/3/23 Mon 10/9/23 Fri 11/3/23 0 days
removalTemporary Fencing
1555 Zone 4 - Completion dates Mon 12/4/23 Fri 12/15/23Mon 12/4/23Fri 12/15/23 0 days
1556 External works Complete Mon 12/4/23 Mon 12/4/23Mon 12/4/23Mon 12/4/23 0 days 12/4
1557 Handover Fri 12/15/23 Fri 12/15/23Fri 12/15/23Fri 12/15/23 0 days 12/15
1559 Utilities installation Fri 6/30/23Thu 11/16/23 Fri 6/30/23
Thu 11/16/23 0 days
1560 Thames water connection Fri 10/27/23 Thu Fri Thu 0 wks
(testing& commissioning - 18 11/16/23 10/27/23 11/16/23
days)
1562 BT connection (testing& Fri 10/13/23 Fri 10/27/23 Fri Fri 0 days
commissioning - 10 days) 10/13/23 10/27/23
1563 Virgin Media (testing& Fri 10/27/23 Fri 11/10/23 Fri Fri 0 days
commissioning - 10 days) 10/27/23 11/10/23
1564 Electric power connection Fri 10/6/23 Thu Fri 10/6/23 Thu 0 wks
(consumer unit power up - 12 10/26/23 10/26/23
days)

1566 Handover dates Fri 9/29/23Thu 12/21/23 Fri 9/29/23


Thu 12/21/23 0 days
1567 Completion of external works Fri 12/15/23 Fri 12/15/23Fri 12/15/23Fri 12/15/23 0 days 12/15
1568 Provisional notice of completion& client Fri 9/29/23 Fri 9/29/23 Fri 9/29/23 Fri 9/29/23 0 days 9/29
inspections [12 weeks prior to
completion]

1569 Provisional notice of completion& client Fri 10/27/23 Fri 10/27/23 Fri Fri 0 days 10/27
inspections [8 weeks prior to 10/27/23 10/27/23
completion]

1570 Firm notice of completion [4 weeks Fri 11/24/23 Fri 11/24/23 Fri Fri 0 days 11/24
notification prior to completion for 11/24/23 11/24/23
clients snagging]

1571 Arrangement for client viewings of each Fri 12/8/23 Fri 12/8/23 Fri 12/8/23 Fri 12/8/23 0 days 12/8
flat type [2 weeks prior to completion]
1572 Practical Completion Handover Thu 12/21/23Thu 12/21/23
Thu 12/21/23
Thu 12/21/23 0 days 12/21
1575 Client instructions Thu 2/7/19 Wed 7/5/23 Thu 2/7/19Wed 7/19/23 10 days
1626 <New Milestone> Thu 2/7/19 Thu 2/7/19 Thu 2/7/19 Thu 2/7/19 0 days
1627 <New Summary Task> Thu 2/7/19 Thu 2/7/19 Thu 2/7/19 Thu 2/7/19 0 days?
1628 <New Task> Thu 2/7/19 Thu 2/7/19 Thu 2/7/19 Thu 2/7/19 0 days?
1629 <New Task> Thu 2/7/19 Thu 2/7/19 Thu 2/7/19 Thu 2/7/19 0 days?

Task External Tasks Duration-only External Tasks Deadline

Project: 2954 Penry Street Split External Milestone Manual Summary Rollup External Milestone
Date:17//07/2023 Milestone Inactive Milestone Manual Summary Critical
Revision B
Summary Inactive Summary Start-only Critical Split
Project Summary Manual Task Finish-only Progress

Page 4