nish Predecessors Dec 4, '23 Dec 11, '23 Dec 18, '23 Dec 25, '23 Jan 1, '23 Jan 8, '23 Jan 15, '23 Jan 22, '23 Jan 29, '23 Feb 5, '23 Feb 12, '23 Feb 19, '23 Feb 26, '23
Mode S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTW
1 B+G+2 RESIDENTIAL 61 days Mon 12/4/23 Mon 2/26/24
BUILDING STRUCTURAL
WORKS SCHEDULE
2 Excavation and earthwork 15 days Mon 12/4/23 Mon 12/25/23
7 Shearwall, column & Kg 2100 5 days Tue 12/12/23 Mon 6FS-7 days
Pad reinforcement 12/18/23
13 Slab and beam Kg 1900 5 days Tue 1/2/24 Mon 1/8/24 12FS-4 days
Reinforcement
17 Column, Slab and Kg 2900 7 days Wed 1/17/24 Thu 1/25/24 16FS-5 days
beam Reinforcement
21 Column, Slab and Kg 2900 7 days Thu 2/1/24 Fri 2/9/24 20FS-7 days
beam Reinforcement
25 Column and Top Kg 1100 7 days Thu 2/15/24 Fri 2/23/24 24FS-5 days
beam Reinforcement
Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: B+G+2 RESIDENTIAL B
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Wed 11/29/23
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress