You are on page 1of 1

ID Task Task Name Unit Qty Duration Start Finish Predecessors Dec 4, '23 Dec 11, '23 Dec

nish Predecessors Dec 4, '23 Dec 11, '23 Dec 18, '23 Dec 25, '23 Jan 1, '23 Jan 8, '23 Jan 15, '23 Jan 22, '23 Jan 29, '23 Feb 5, '23 Feb 12, '23 Feb 19, '23 Feb 26, '23
Mode S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTW
1 B+G+2 RESIDENTIAL 61 days Mon 12/4/23 Mon 2/26/24
BUILDING STRUCTURAL
WORKS SCHEDULE
2 Excavation and earthwork 15 days Mon 12/4/23 Mon 12/25/23

3 Bulk excavation m³ 220 2 days Mon 12/4/23 Tue 12/5/23

4 Pit Excavation m³ 21.875 4 days Wed 12/6/23 Mon 12/11/233

5 Leanconcrete m² 45.25 1 day Wed 12/6/23 Wed 12/6/23 3

6 Shearwall, column & m² 193.545 10 days Thu 12/7/23 Wed 5


Pad formwork 12/20/23

7 Shearwall, column & Kg 2100 5 days Tue 12/12/23 Mon 6FS-7 days
Pad reinforcement 12/18/23

8 Shearwall, column & m³ 26.5925 2 days Thu 12/21/23 Fri 12/22/23 6


Pad concrete

9 <New 0 days Mon 12/25/23 Mon 8 12/25


Task>Substructure work 12/25/23
completed
10 Superstructure 46 days Mon 12/25/23 Mon 2/26/24

11 Ground floor Structural works 12 days Mon 12/25/23 Tue 1/9/24 8

12 Slab and beam formwork


m² 250 10 days Mon 12/25/23 Fri 1/5/24 8

13 Slab and beam Kg 1900 5 days Tue 1/2/24 Mon 1/8/24 12FS-4 days
Reinforcement

14 Slab and beam m³ 15 1 day Tue 1/9/24 Tue 1/9/24 13


concrete work

15 First floor structural works 13 days Wed 1/10/24 Fri 1/26/24 14

16 Column, Slab and m² 276.25 10 days Wed 1/10/24 Tue 1/23/24 14


beam formwork

17 Column, Slab and Kg 2900 7 days Wed 1/17/24 Thu 1/25/24 16FS-5 days
beam Reinforcement

18 Column, Slab and m³ 15 1 day Fri 1/26/24 Fri 1/26/24 17


beam concrete work

19 Second floor structural works 11 days Mon 1/29/24 Mon 2/12/24 18

20 Column, Slab and m² 276.25 10 days Mon 1/29/24 Fri 2/9/24 18


beam formwork

21 Column, Slab and Kg 2900 7 days Thu 2/1/24 Fri 2/9/24 20FS-7 days
beam Reinforcement

22 Column, Slab and m³ 15 1 day Mon 2/12/24 Mon 2/12/24 21


beam concrete work

23 Top floor structural works 10 days Tue 2/13/24 Mon 2/26/24 22

24 Column and Top m² 75 7 days Tue 2/13/24 Wed 2/21/24 22


beam formwork

25 Column and Top Kg 1100 7 days Thu 2/15/24 Fri 2/23/24 24FS-5 days
beam Reinforcement

26 Column and Top m³ 7 1 day Mon 2/26/24 Mon 2/26/24 25


beam concrete work

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: B+G+2 RESIDENTIAL B
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Wed 11/29/23
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

Page 1

You might also like