ID Task Name Duration Start November 2023 December 2023 January 2024 February 2024

23 25 27 29 31 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 2 4
1 Internal refurbishment of 45 days Mon
Building 10 at the CSIR 4/12/23
Pretoria Campus
2 DEMOLISHING & REMOVALS9 days Mon 4/12/23
64 PAINTING OF WALLS 14 days Fri 15/12/23
65 Walls 14 days Fri 15/12/23
73 Paint internal to stair cases7 days Fri 15/12/23
77 Paint to Concrete sofit 7 days Fri 15/12/23
83 Paint to Concrete sofit to 7 days Fri 15/12/23
Stairs
87 PAINT TO METAL 7 days Thu 4/1/24
88 Paint to steel door frames7 days Thu 4/1/24
89 Basement passage and Toilets
7 days Thu 4/1/24
90 Ground floor passage and 7 days
Toilets Thu 4/1/24
91 First floor passages and Toilets
7 days Thu 4/1/24
92 Paint to staircase rails 3 days Thu 4/1/24
and metal barriers
96 Paint to power skirting 3 days Tue 9/1/24
97 TIMBER 3 days Mon 15/1/24
103 FLOOR COVER 3 days Thu 18/1/24
112 KITCHENS 30 days Fri 15/12/23
216 BATHROOMS 30 days Fri 15/12/23
251 Ceilings and Partitions etc 4 days Fri 26/1/24
252 Ceiling to office 4 days Fri 26/1/24
253 Ceilings to toilets 4 days Fri 26/1/24
254 Lighting 0 days Thu 25/1/24 25/1
255 to toilets 0 days Thu 25/1/24 25/1
256 Supply and install Blinds to 6 days Fri 26/1/24
match existing Block F
257 Block B 2 days Fri 26/1/24
258 Block C 2 days Tue 30/1/24
259 Block D 2 days Thu 1/2/24
260 RUBBLE 45 days Mon 4/12/23

Task Project Summary Manual Task Start-only Deadline

Project: CSIR Split Inactive Task Duration-only Finish-only Progress


Date: Thu 26/10/23 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 1