Ground Floor
Repair and paint walls, Offices, Passages, Bathrooms, Laundry, Canteen etc.
Entrance to Warehouse at Hand Wash Area (358 M2) m2 358 180 R 64,440.00
Remove damaged tiles (18) 18 55 R 990.00
Replace and paint damaged Ceiling m2 20 4500 R 90,000.00
Replace and seal Saligna Wooden Door at Warehouse Entrance from Offices item 1 3248.7 R 3,248.70
Replace and paint Hollowcore Door at Gents and laundry item 2 624 R 1,248.00
Bathroom Kitchen Cupboard in Office item 1 2100 R 2,100.00
Replace clips refit and silicone Sink item 1 1500 R 1,500.00
Replace Sink Cupboard Shelve and service Doors item 1 1500 R 1,500.00
1st Floor
Remove Drywalls and make good (38 M2) m2 38 100 R 3,800.00
Remove Glass Panels and make good item 1 1500 R 1,500.00
Repair and paint walls, Offices, Boardroom, Passage, Staircase etc. (294 M2) m2 294 180 R 52,920.00
Remove rubble item 1 1500 R 1,500.00
Server room door item 1 624 R 624.00
Production / Warehouse
Remove Wooden Deckings (208 M2) m2 208 65 R 13,520.00
Remove Epoxy from floor surfaces with Floor Grinder (98 M2) m2 98 80 R 7,840.00
Repair floor surfaces where damaged item 1 2000 R 2,000.00
Close all screw holes where Racking and Cages get removed item 1 1500 R 1,500.00
Repair chipped and dirty Pillars item 1 1500 R 1,500.00
Demolish Bund Walls and Floors (246 M2) m2 246 100 R 24,600.00
Reinstall Drains after floors been Demolished (8 ) 8 200 R 1,600.00
QC Lab 1 Remove damaged Sink Cabinet and install new Sink Cabinet, fit and seal Top item 1 4500 R 4,500.00
Repair Tiles at Door Entrance item 1 350 R 350.00
Repair and paint walls (34 M2) m2 34 180 R 6,120.00
Repair and paint Storeroom walls (36 M2) m2 36 180 R 6,480.00
R 181,000.00