d. Fabrication Procedure P R No R
f. Welding Map * P R No R
h. Welder List * P R No No
i. Welder Certificate * P R No No
j. NDT MAP * P R No R
a Material Specification * M R No R
a. Material Check M R No R
c. Calibration Test * M R No R
f. Pressure Test * M R No R
g. Connection Check M R No R
c Function Test * M R No R
5.0 Cables
a. Test Report * M R No R
6.0 Panel
b. Function Test * M R No R
2 of 4
e As Build Drawing * M R No R
NOTES :
The ABBREVIATION used throughout this list shall have the meaning denoted :
P Vendor shall provide within 4 weeks after receive purchase order and specify in vendor print check schedule
M Vendor Inspection/Test, the inspection or/and test that performed by the vendor at their workshop
I Vendor Inspection/Test Record to be submitted only for Information and no need approval
Spot Witness (item or quantities to be witnessed shall be decided at Pre-inspection Meeting by the
SW
CONTRACTOR/OWNER
H Hold point
If specified Test/Inspection shall be carried out if specified in the applicable requisition or specification.
Project Requirement
Application for Inspection (AFI) by Inspection Management System (IMS) shall be submitted 14 days before
Inspection (Local Inspection) and 30 days for overseas. IMS is PT Rekayasa Industri’s web based software
√
which can be used freely by Vendor. IMS Manual for Vendor shall be submitted by CONTRACTOR to
VENDOR in Kick Off Meeting (KOM)
Sample of ITP form attached. Vendor shall develop detail ITP which is mention activity, control documents,
√
Acceptance Criteria, verifying document and responsible party.
WPS, PQR and Welder certificate shall be valid and approved by DEPNAKER. The code shall be consistent:
√
For Structural using AWS D1.1, For piping and Pressure Vessel using ASME IX
For Overseas fabricator, Depnaker requirement can be substituted by recognition international standard and
√
subject to Approval.
√ NDE Procedure shall be approved by ASNT NDT level III, All NDE personnel shall be certified by ASNT.
All requirements stated in this document are the minimum requirements. Manufacturer have to follow all the
√
requirements stated in related codes, standards and project specifications. .