You are on page 1of 5

Document Code

Inspection Report
F-084/09

Report No: R-VM23-0012-LV-052 Rev.00

This is to notify that the components as described hereunder have been inspected:

Main Client / Owner: NIGC-Khrz


Client / Contractor: Daryasahel. Co
Project Name / Contract No.: 16” booster gas Transfer of Saleh abad - Torbat jaam
Supplier: N/A
Manufacturer / Vendor: PEPCO
Purchase Order No. / LC No. / PI No.: N/A
Place of Inspection: Mashhad -Iran
Date / Period of Inspection: 04.Nov.2023 (1 day)
Persons met: Mr. gholami
IDR / Notification No. DS-46

1. The following items were inspected:


Item no. Quantity
According to Result
PO / Row
Description Identification No.* Ordered Inspected (Based on Inspection Conclusion)
no.
1 Hydrostatic Test for Safety Relief Valve PEP012 2 2 Approved

* Identi7fication No: Heat No. / Serial No. / Batch No. / etc.

2. Brief Summary of Objections / Comments / NCR / TQ (If any):


(All of the open items shall be RE-MENTIONED)
IR / NCR / TQ Date of
Row Description Action by Status
No. Issue
Closed
1 - - - -
Open

3. Reference / Inspection Documents:


Document Name Document Number Date of Issue Rev. No. Remark
ITP N/A N/A N/A N/A
Drawing N/A N/A N/A N/A
Standard / Code IGS-M-IN-302 (2) - - -
Specification N/A N/A N/A N/A
Test Procedure N/A N/A N/A N/A
Technical Data Sheet N/A N/A N/A N/A
Others: N/A N/A N/A N/A

Page 1 of 5
Document Code
Inspection Report
F-084/09

Report No: R-VM23-0012-LV-052 Rev.00


4. Scope of Inspection:
According to: IDR / Notification / Service Order ITP Email
Material Certificate Check / Review Welder Qualification Test (WQT)
Vendor List Check Performance Test
Visual Inspection Welding Monitoring
Packing and Marking Inspection Raw Material Inspection
Internal Visual Check PQR Test
Sampling Surface Preparation
Chemical Analysis Test Painting and Coating Inspection
Mechanical Test Color Code Control
PMI Test Insulation Resistance Check
Hardness Test Pickling and Passivation
Ultrasonic Test (UT) Hydrostatic Test
RT Interpretation (RTI) Leakage Test
Magnetic Particle Test (MT) Functional Test
Liquid Penetration Test (PT) Review of Final Dossier
Dielectric Test Other:
Corrosion Tests (HIC/SSCC/CTOD) Dimensional Inspection (Result in below table)

Inspection Details:

As per client’s request and coordinating with vendor and in his factory , test was performed as below :
- According to the IGS-M-IN-302(2) standard, the hydrostatic test of 2 safety relief valves was performed at a
pressure of 150 bar and in a time of 5 minutes. No leakage or pressure drop was observed during the test.
- The increase and decrease of pressure was done gradually.
- Calibration certificates of used measuring instrument were controlled .

5. Laboratory Analysis and Testing Inspection:


Name of Laboratory: Sampling/Test Standard Used:
Number of Taken Samples: 2 Heat Numbers of Samples: PEP012
Type of Performed Test(s): Description of test:
1- Hydrostatic Test
Test results Passed Failed

6. Inspection Tools Calibration:


Row Inspection / Test Equipment or Device Serial No. Calibration Validity Date
1 Barometer 110066 1401.11.30

Page 2 of 5
Document Code
Inspection Report
F-084/09

Report No: R-VM23-0012-LV-052 Rev.00


7. Quantity, Packing and Marking Inspection:
Review of ITP Steps Before Packing: N/A
Packing List no. and Date: N/A
Packages Type: N/A
Number of Package(s):
Box Pallet Cage Bundle N/A
Total
Loose Net Weight:
Wrapped Other N/A
Total Gross Weight: N/A
Remarks:

8. Inspection of Loading / Discharge:


Means of Transport: N/A
Incoterm: N/A
Customs Tariff Number: N/A
Cargo Code: N/A
B/L Number: N/A
Date of B/L Issuance: N/A
B/L Issued by: N/A
Voyage Number: N/A
Carrier Name: N/A
Port of Loading & Country: N/A
Port of Discharge & Country: N/A
Date of Loading: N/A
Transhipment: N/A
Other Data: N/A
Packing Marking Wedging
Surveillance Operations Performed: Weighing Supervision of Loading
No Damage Damage Occurred (see remarks)
Remarks:

Page 3 of 5
Document Code
Inspection Report
F-084/09

Report No: R-VM23-0012-LV-052 Rev.00


9. Pictures (With a brief description of each picture):

Page 4 of 5
Document Code
Inspection Report
F-084/09

Report No: R-VM23-0012-LV-052 Rev.00

10. Conclusion:
There Were no Reason for Objection
Result of Inspection: With Comment, Refer to Underlined Content
With Objection, Refer to Underlined Content
Completed
Not Complete
Status of Items (According to P.O.)
Ready for Packing
Ready for Shipment
Further Inspections: Yes No
M.O.M
Certificate(s)
The Documents Which Shall Be Attached to This Report Drawing(s)
Based on Scope of Inspection: Packing List
NCR
Other:
Name of Inspector: M.R Vakili Signature and Stamp:

Date: 13.Nov.2023

Page 5 of 5