18558-1002
INDEX
Sec. Rev.
Sec No. Section Description
Rev. Date
i. COVER PAGE A 03.04.19
ii. INDEX A 03.04.19
Colloide Components
1 RGF Tank 1 A 03.04.19
2 RGF Tank 2 A 03.04.19
Document No.: Rev. Eff. Date:
INSPECTION AND TEST PLAN
18558-1002 A 18/11/2019
Sec No.: Sec. Rev. Section Description:
2 A RGF Tank 1 Project: Lough Talt
Equipment Part No. : tbd Customer: Coffeys
Equipment Serial No. : tbd Unit: 00000
Sub-Vendor: tbd Sub-Vendor PO: tbd
INTERVENTION KEY CODE: INSPECTION KEY CODE:
SUB: Sub-Vendor CUST: Customer NoBo.: Notified Body SW: Spot Witness (%) inspection R: Review of Documentation T/C: Test Certificate required
COLLOIDE: COLLOIDE INSP: Thirt Party Inspector W: Witness Inspection H: Hold point
INTERVENTION COMPANY
CHARACTERISTIC TO BE VERIFIED REQ.
ACT. QUALITY REFERENCE ACCEPTANCE CERTIF
No. ACTIVITY / STAGE DOCUMENT CRITERIA . SUB' COLLOIDE Customer INSP / NoBo Remarks
1 .1 Material certificates / Spec./Dwg. Review of certificates: T/C H R R R SUB to provide all the
Identification: mill certificates for main parts and components certificates
chemical analysis and
mechanical properties
date - signature date - signature date - signature date - signature
1 .2 Compliance with Water Spec./Dwg. For Wetted products/material: Spec./Dwg. T/C H R R R SUB to provide all the
Supply (Water Quality) PO WRAS / DWI Reg.31 / BSEN number PO DWI/WRAS certificates
Regulations. WRAS / (applicable British standard / Directive). DWI Reg.31 /
(applicabe by wetted DWI Reg.31 / WRAS /
Substances and products added to or coming into contact
components, products,
with the water shall be approved for the purpose under
systems)
Regulation 31.
date - signature date - signature date - signature date - signature
1 3 Welding Procedures Review and approval of welding specs. As per selected T/C H R R R SUB to provide all the
Specification and WPS, PQR to be approved by Colloide before construction. Code WPS/PQR
Qualification Records Manufacturer shall maintain valid certification
(WPS / PQR)
date - signature date - signature date - signature date - signature
1 4 Welders and welding Spec./Dwg. Review and verification of Welders certifications. As per Spec./Dwg. T/C H R R R SUB to provide all the
operator certificates welders qualification
certificates
INTERVENTION COMPANY
CHARACTERISTIC TO BE VERIFIED REQ.
ACT. QUALITY REFERENCE ACCEPTANCE CERTIF
No. ACTIVITY / STAGE DOCUMENT CRITERIA . SUB' COLLOIDE Customer INSP / NoBo Remarks
1 8 NDE superficial: Spec./Dwg. 10% Fillet/Partial Penetration Welds. as per Spec./Dwg. T/C H /SW SW R R SUB to provide all the test
Dye Penetration testing report
INTERVENTION COMPANY
CHARACTERISTIC TO BE VERIFIED REQ.
ACT. QUALITY REFERENCE ACCEPTANCE CERTIF
No. ACTIVITY / STAGE DOCUMENT CRITERIA . SUB' COLLOIDE Customer INSP / NoBo Remarks
1 13 Final review of Spec./Dwg. Verification of correctness and completeness of required Spec./Dwg. T/C H R R R SUB to provide all the Final
documentation / Inspection P.O. documentation: P.O. Inspection Book
Book ITP - Vendor Inspection Book; ITP
- Manufacturer Test Report; SUB to provide evidence
of observance the AW and
WIMES standards:
AM600 Mechanical
Standards & WIMES.
date - signature date - signature date - signature date - signature
1 14 Preparation for shipment Spec./Dwg. - Check of integrity (no damages); As per Spec./Dwg. T/C H H R R SUB to provide the PL
SUB standards - Check of completion of int/ext installation (if any) SUB standards
PO - Check packing and marking; PO
- Check of availability / correctness of the final Detail
Packing List;
date - signature date - signature date - signature
Document No.: Rev. Eff. Date:
INSPECTION AND TEST PLAN
18558-1002 A 18/11/2019
Sec No.: Sec. Rev. Section Description:
2 A RGF Tank 2 Project: Lough Talt
Equipment Part No. : tbd Customer: Coffeys
Equipment Serial No. : tbd Unit: 00000
Sub-Vendor: tbd Sub-Vendor PO: tbd
INTERVENTION KEY CODE: INSPECTION KEY CODE:
SUB: Sub-Vendor CUST: Customer NoBo.: Notified Body SW: Spot Witness (%) inspection R: Review of Documentation T/C: Test Certificate required
COLLOIDE: COLLOIDE INSP: Thirt Party Inspector W: Witness Inspection H: Hold point
INTERVENTION COMPANY
CHARACTERISTIC TO BE VERIFIED REQ.
ACT. QUALITY REFERENCE ACCEPTANCE CERTIF
No. ACTIVITY / STAGE DOCUMENT CRITERIA . SUB' COLLOIDE Customer INSP / NoBo Remarks
1 .1 Material certificates / Spec./Dwg. Review of certificates: T/C H R R R SUB to provide all the
Identification: mill certificates for main parts and components certificates
chemical analysis and
mechanical properties
date - signature date - signature date - signature date - signature
1 .2 Compliance with Water Spec./Dwg. For Wetted products/material: Spec./Dwg. T/C H R R R SUB to provide all the
Supply (Water Quality) PO WRAS / DWI Reg.31 / BSEN number PO DWI/WRAS certificates
Regulations. WRAS / (applicable British standard / Directive). DWI Reg.31 /
(applicabe by wetted DWI Reg.31 / WRAS /
Substances and products added to or coming into contact
components, products,
with the water shall be approved for the purpose under
systems)
Regulation 31.
date - signature date - signature date - signature date - signature
1 3 Welding Procedures Review and approval of welding specs. As per selected T/C H R R R SUB to provide all the
Specification and WPS, PQR to be approved by Colloide before construction. Code WPS/PQR
Qualification Records Manufacturer shall maintain valid certification
(WPS / PQR)
date - signature date - signature date - signature date - signature
1 4 Welders and welding Spec./Dwg. Review and verification of Welders certifications. As per Spec./Dwg. T/C H R R R SUB to provide all the
operator certificates welders qualification
certificates
INTERVENTION COMPANY
CHARACTERISTIC TO BE VERIFIED REQ.
ACT. QUALITY REFERENCE ACCEPTANCE CERTIF
No. ACTIVITY / STAGE DOCUMENT CRITERIA . SUB' COLLOIDE Customer INSP / NoBo Remarks
1 8 NDE superficial: Spec./Dwg. 10% Fillet/Partial Penetration Welds. as per Spec./Dwg. T/C H /SW SW R R SUB to provide all the test
Dye Penetration testing report
INTERVENTION COMPANY
CHARACTERISTIC TO BE VERIFIED REQ.
ACT. QUALITY REFERENCE ACCEPTANCE CERTIF
No. ACTIVITY / STAGE DOCUMENT CRITERIA . SUB' COLLOIDE Customer INSP / NoBo Remarks
1 13 Final review of Spec./Dwg. Verification of correctness and completeness of required Spec./Dwg. T/C H R R R SUB to provide all the Final
documentation / Inspection P.O. documentation: P.O. Inspection Book
Book ITP - Vendor Inspection Book; ITP
- Manufacturer Test Report; SUB to provide evidence
of observance the AW and
WIMES standards:
AM600 Mechanical
Standards & WIMES.
date - signature date - signature date - signature date - signature
1 14 Preparation for shipment Spec./Dwg. - Check of integrity (no damages); As per Spec./Dwg. T/C H H R R SUB to provide the PL
SUB standards - Check of completion of int/ext installation (if any) SUB standards
PO - Check packing and marking; PO
- Check of availability / correctness of the final Detail
Packing List;
date - signature date - signature date - signature