Total Sheet 13

Vendor’s name : The branch of Fujikin Viet Nam-VWL Ha Noi

Owner’s Name : Vietnam Nisshin Technomic

Purchaser : JGC Vietnam Co., Ltd.

Plant Location : Bien Hoa City, Dong Nai Province, Vietnam

Project Name : Vietnam Nisshin Technomic Phase 2

P / Order No. : G-V028-P-2155-508-A

Equipment/Material Name: Solid Handling Valve

Item Number : CV362, CV366, CV395, CV3A9, CV3B1, CV3B5, CV3B6

Document Title : Inspection and test plan (ITP)

Vietnam Nisshin Technomic Phase 2 Project


(JOB No.: 0-8850-20)
DOCUMENT CLASS: 1

ISSUE PURPOSE: FA

RESULT CODE: A, B, R B

NEXT STATUS: FA, FI, FC, AB FC

RESUBMISSION DATE:

NEXT SUBMISSION DATE: 30-Sep-2022

RESPONSIBLE DEPT./PERSON: MEC/ L.V.Phu

Review Date: 20-Sep-2022

A: Approved without Comment; B: Approved with Minor Comment

R: Not Approved with Comments

Approval or review hereunder shall not be construed to relieve Supplier / Subcontractor of

his responsibilities and liability under the Contract.

Purchaser ORIG. PURCHASE ORDER NO. SERIAL REV.

DOC. No. V- 2155 - 508 - A - 600 0

Reviewed by QC: Tran Van Tien


17-Aug-22
Inspection and Test plan (ITP)

Client: Fujikin Vietnam Co., Ltd Customer ID: 01 05794959


Add: Room 308A, 3rd floor, UDIC Comlex Project: Nisshin Technomic Vietnam phase 2
Building, Hoang Dao Thuy Street, Trung Hoa Reference:
ward, Cau Giay District, Hanoi
Tel: +84 (24) 3736-8587

Salesorder No: SOD021 79 Inspection date : Time:


Date: 01/06/2022 Inspect by: Nguyen Van Quang
Product: Two-way valve with flap seal DN Quantity: 02 pcs
200x2mm, symmetrical, 60°, SS304, blasted Code: BBHF000024
pneumatically operated, rotary actuator, non- Equip No.: CV362, CV3A9
spring return 5/2-way-solenoid-valve, double
acting solenoid, 24 V DC, 2 limit switches

A. Input check:

Test and Inspection / Inspected by


Record
Vendor
(Formula Purchaser Owner
# Test Items Specification
Air / (JCG) (VNT)
Fujikin) JGC

1 Material Stainless steel 304 V R R

2 Thickness T=2.0 mm V R R

3 Accessory

GD-083/09-F05/F07-V17-G
3.1 Actuator Pre-adjusted to 0° and 60°" V R R
(ref. “BAR-agturn Actuator.pdf”)
5/2-way-NAMUR-solenoid valve
NM-522-H
3.2 Solenoid valve V R R
(ref. “BAR-5_2-way NM-522-
H.pdf”)

SC-M2-S2
Double mircoswitch for bistable
3.3 Limit switches solenoid-valves V R R
(ref. “BAR-SwitchControl-SC-
M2.pdf”)
B. Fabrication check:

Test and Inspection Inspected by


Record
Vendor
Purchaser Owner
# Test Items Specification (Formula Air /
(JCG) (VNT)
Fujikin) JGC

No distorted or out of
1 Forming V R R
shape

No crack, no cold
2 Welding V R R
lapping, no defects

Bolts, nuts, washers,


3 Fasteners screws are sufficient and V R R
fastened properly

4 Dimension Comply detail drawing V R R

No scratch, clean
5 Visual V R R
surface

No missing nor
6 Name plate V R R
unmatched information

C. Operation check:

Test and Inspection Inspected by


Record
Vendor
Purchaser Owner
# Test Items Specification (Formula Air /
(JCG) (VNT)
Fujikin) JGC

Smooth rotating, no
1 Rotary stuck esp. sealing V H W
contacting area

2 Traveling time Check 1 cycle time V H W

Position Indicator working


3 V H W
indicator properly

After 30min. continuous


4 Bearing temp. operation, bearing V H W
temperature still normal

5 Noise Must be ≤ 85 Db (1 m) V H W

Check flap position when


6 Fail status V H W
de-energize
Note:

V (Implementation): Preparation for and execution of measurement, observation,


examination and /or testing and reporting.

R (Document review): Vendor shall provide Purchaser with Certificates, documents or


reports/ records as applicable for review and confirmation.

H (Hold point): Vendor shall notify Purchaser of the inspection date and time.
Vendor is not allowed to proceed with the test or inspection unless a
written release is issued by the Purchaser’s inspe ctor.

W (Witness point): Vendor shall notify Purchaser of the inspection date and time.
Vendor may proceed with the test or inspection if the Purchase r’s
inspector is not present at the appointed time.
Inspection and Test plan (ITP)

Client: Fujikin Vietnam Co., Ltd Customer ID: 01 05794959


Add: Room 308A, 3rd floor, UDIC Comlex Project: Nisshin Technomic Vietnam phase 2
Building, Hoang Dao Thuy Street, Trung Hoa Reference:
ward, Cau Giay District, Hanoi
Tel: +84 (24) 3736-8587

Salesorder No: SOD021 79 Inspection date: Time:


Date: 01/06/2022 Inspect by: Nguyen Van Quang
Product: Two-way valve with flap seal Quantity: 02 pcs
DN200x2mm, symmetrical, 60°, SS304, Code: BBHF100024
blasted pneumatically operated, rotary Equip No.: CV395, CV3B1
actuator, spring return 3/2-way-solenoid-
valve, single acting solenoid, 24 V DC,
2 limit switches

A. Input check:

Test and Inspection / Inspected by


Record
Vendor
(Formula Purchaser Owner
# Test Items Specification
Air / (JCG) (VNT)
JGC
Fujikin)
1 Material Stainless steel 304 V R R

2 Thickness T=2.0 mm V R R

3 Accessory

GS-092/09-F05/F07-V1 7-G
3.1 Actuator Pre-adjusted to 0° and 60° V R R
(ref. “BAR-agturn Actuator.pdf”)

NM-321-H
3.2 Solenoid valve (ref. “BAR-3_2-way NM-321- V R R
H.pdf”)

SC-M2-S1
Double microswitch for
3.3 Limit switches monostable solenoid-valves V R R
(ref. “BAR-SwitchControl-SC-
M2.pdf”)
B. Fabrication check:

Test and Inspection Inspected by


Record
Vendor
Purchaser Owner
# Test Items Specification (Formula Air /
(JCG) (VNT)
Fujikin) JGC

No distorted or out of
1 Forming V R R
shape

No crack, no cold
2 Welding V R R
lapping, no defects

Bolts, nuts, washers,


3 Fasteners screws are sufficient and V R R
fastened properly

4 Dimension Comply detail drawing V R R

No scratch, clean
5 Visual V R R
surface

No missing nor
6 Name plate V R R
unmatched information

C. Operation check:

Test and Inspection Inspected by


Record
Vendor
Purchaser Owner
# Test Items Specification (Formula Air /
(JCG) (VNT)
Fujikin) JGC

Smooth rotating, no
1 Rotary stuck esp. sealing V H W
contacting area

2 Traveling time Check 1 cycle time V H W

Position Indicator working


3 V H W
indicator properly

After 30min. continuous


4 Bearing temp. operation, bearing V H W
temperature still normal

5 Noise Must be ≤ 85 Db (1m) V H W

Check flap position when


6 Fail status V H W
de-energize
Note:

V (Implementation): Preparation for and execution of measurement, observation,


examination and /or testing and reporting.

R (Document review): Vendor shall provide Purchaser with Certificates, documents or


reports/ records as applicable for review and confirmation.

H (Hold point): Vendor shall notify Purchaser of the inspection date and time.
Vendor is not allowed to proceed with the test or inspection unless a
written release is issued by the Purchaser’s inspector.

W (Witness point): Vendor shall notify Purchaser of the inspection date and time.
Vendor may proceed with the test or inspection if the Purchaser’s
inspector is not present at the appointed time.
Inspection and Test plan (ITP)

Client: Fujikin Vietnam Co., Ltd Customer ID: 01 05794959


Add: Room 308A, 3rd floor, UDIC Comlex Project: Nisshin Technomic Vietnam phase 2
Building, Hoang Dao Thuy Street, Trung Hoa Reference:
ward, Cau Giay District, Hanoi
Tel: +84 (24) 3736-8587

Salesorder No: SOD021 79 Inspection date: Time:


Date: 01/06/2022 Inspect by: Nguyen Van Quang
Product: Two-way valve with flap seal Quantity: 01 pcs
DN1 00x2mm, asymmetrical, 45°, SS 304, Code: BBHJ1 00082
blasted pneumatically operated, rotary Equip No.: CV3B6
actuator, spring return 3/2-way-solenoid-
valve, single acting solenoid, 24 V DC,
2 limit switches

A. Input check:

Test and Inspection / Inspected by


Record
Vendor
(Formula Purchaser Owner
# Test Items Specification
Air / (JCG) (VNT)
Fujikin) JGC

1 Material Stainless steel 304 V R R

2 Thickness T=2.0 mm V R R

3 Accessory

GD-063/09-F05/F07-V1 4-G
3.1 Actuator Pre-adjusted to 0° and 45° V R R
(ref. “BAR-agturn Actuator.pdf”)

NM-321-H
3.2 Solenoid valve (ref. “BAR-3_2-way NM-321 - V R R
H.pdf”)

SC-M2-S1
Double microswitch for
3.3 Limit switches monostable solenoid-valves V R R
(ref. “BAR-SwitchControl-SC-
M2.pdf”)
B. Fabrication check:

Test and Inspection Inspected by


Record
Vendor
Purchaser Owner
# Test Items Specification (Formula Air /
(JCG) (VNT)
Fujikin) JGC

No distorted or out of
1 Forming V R R
shape

No crack, no cold
2 Welding V R R
lapping, no defects

Bolts, nuts, washers,


3 Fasteners screws are sufficient and V R R
fastened properly

4 Dimension Comply detail drawing V R R

No scratch, clean
5 Visual V R R
surface

No missing nor
6 Name plate V R R
unmatched information

C. Operation check:

Test and Inspection Inspected by


Record
Vendor
Purchaser Owner
# Test Items Specification (Formula Air /
(JCG) (VNT)
Fujikin) JGC

Smooth rotating, no
1 Rotary stuck esp. sealing V H W
contacting area

2 Traveling time Check 1 cycle time V H W

Position Indicator working


3
indicator properly

After 30min. continuous


4 Bearing temp. operation, bearing V H W
temperature still normal

5 Noise Must be ≤ 85 Db (1m) V H W

Check flap position when


6 Fail status V H W
de-energize
Note:

V (Implementation): Preparation for and execution of measurement, observation,


examination and /or testing and reporting.

R (Document review): Vendor shall provide Purchaser with Certificates, documents or


reports/ records as applicable for review and confirmation.

H (Hold point): Vendor shall notify Purchaser of the inspection date and time.
Vendor is not allowed to proceed with the test or inspection unless a
written release is issued by the Purchaser’s inspe ctor.

W (Witness point): Vendor shall notify Purchaser of the inspection date and time.
Vendor may proceed with the test or inspection if the Purchase r’s
inspector is not present at the appointed time.
Inspection and Test plan (ITP)

Client: Fujikin Vietnam Co., Ltd Customer ID: 01 05794959


Add: Room 308A, 3rd floor, UDIC Comlex Project: Nisshin Technomic Vietnam phase 2
Building, Hoang Dao Thuy Street, Trung Hoa Reference:
ward, Cau Giay District, Hanoi
Tel: +84 (24) 3736-8587

Salesorder No: SOD021 79 Inspection date: Time:


Date: 01/06/2022 Inspect by: Nguyen Van Quang
Product: Two-way valve with flap seal DN Quantity: 02 pcs
200x2mm, asymmetrical, 45°, SS304, blasted Code: BBHJ1 00086
pneumatically operated, rotary actuator, Equip No.: CV366, CV3B5
spring return 3/2-way-solenoid-valve, single
acting solenoid, 24 V DC, 2 limit switches

A. Input check:

Test and Inspection / Inspected by


Record
Vendor
(Formula Purchaser Owner
# Test Items Specification
Air / (JCG) (VNT)
Fujikin) JGC

1 Material Stainless steel 304 V R R

2 Thickness T=2.0 mm V R R

3 Accessory

GS-092/09-F05/F07-V1 7-G
3.1 Actuator Pre-adjusted to 0° and 45° V R R
(ref. “BAR-agturn Actuator.pdf”)

NM-321-H
3.2 Solenoid valve (ref. “BAR-3_2-way NM-321 - V R R
H.pdf”)

SC-M2-S1
Double microswitch for
3.3 Limit switches monostable solenoid-valves V R R
(ref. “BAR-SwitchControl-SC-
M2.pdf”)
B. Fabrication check:

Test and Inspection Inspected by


Record
Vendor
Purchaser Owner
# Test Items Specification (Formula Air /
(JCG) (VNT)
Fujikin) JGC

No distorted or out of
1 Forming V R R
shape

No crack, no cold
2 Welding V R R
lapping, no defects

Bolts, nuts, washers,


3 Fasteners screws are sufficient and V R R
fastened properly

4 Dimension Comply detail drawing V R R

No scratch, clean
5 Visual V R R
surface

No missing nor
6 Name plate V R R
unmatched information

C. Operation check:

Test and Inspection Inspected by


Record
Vendor
Purchaser Owner
# Test Items Specification (Formula Air /
(JCG) (VNT)
Fujikin) JGC
Smooth rotating, no
1 Rotary stuck esp. sealing V H W
contacting area

2 Traveling time Check 1 cycle time V H W

Position Indicator working


3
indicator properly

After 30min. continuous


4 Bearing temp. operation, bearing V H W
temperature still normal

5 Noise Must be ≤ 85 Db (1m) V H W

Check flap position when


6 Fail status V H W
de-energize
Note:

V (Implementation): Preparation for and execution of measurement, observation,


examination and /or testing and reporting.

R (Document review): Vendor shall provide Purchaser with Certificates, documents or


reports/ records as applicable for review and confirmation.

H (Hold point): Vendor shall notify Purchaser of the inspection date and time.
Vendor is not allowed to proceed with the test or inspection unless a
written release is issued by the Purchaser’s inspector.

W (Witness point): Vendor shall notify Purchaser of the inspection date and time.
Vendor may proceed with the test or inspection if the Purchaser’s
inspector is not present at the appointed time.