Timeline

Auto Control Pump at Nilam Utara Project


PT. AKR Corporindo Tbk.
ID Task Name Duration Start Finish Mar 5, '23 Mar 12, '23 Mar 19, '23 Mar 26, '23 Apr 2, '23 Apr 9, '23 Apr 16, '23
S M TW T F S S M TW T F S S M TW T F S S M TW T F S S M TW T F S S M TW T F S S M TWT F S
1 Auto Control Pump at Nilam Utara Project
28 days Tue 3/7/23 Thu 4/13/23

2 Purchase Order (PO) 1 day Tue 3/7/23 Tue 3/7/23

3 Kick of Meeting (KOM) 1 day Wed 3/8/23 Wed 3/8/23

4 Programming 14 days Thu 3/9/23 Tue 3/28/23

5 Aprroval Design Panel & Wiring 1 day Thu 3/9/23 Thu 3/9/23

6 Built Panel & Wiring 10 days Fri 3/10/23 Thu 3/23/23

7 Install Panel 2 days Fri 3/24/23 Mon 3/27/23

8 Connecting Power & Control Cable 1 day Tue 3/28/23 Tue 3/28/23

9 Test Contiunity & Power 1 dayWed 3/29/23 Wed 3/29/23

10 Test I/O 1 day Thu 3/30/23 Thu 3/30/23

11 Test Communication Cable 2 days Fri 3/31/23 Mon 4/3/23

12 SAT 1 wk Tue 4/4/23 Mon 4/10/23

13 Commissioning 3 days Tue 4/11/23 Thu 4/13/23

Project: Auto Control Pump at Nilam Uta Task Progress Summary External Tasks Deadline
Date: Thu 3/9/23
Split Milestone Project Summary External Milestone