ID Task Name Duration Start Finish April May June

12/3 19/3 26/3 2/4 9/4 16/4 23/4 30/4 7/5 14/5 21/5 28/5 4/6 11/6 18/6
0 Flurotec Service Area Chilled Water Piping and HVAC Work 66 days Sat 1/4/23 Fri 16/6/23
1 Award of Project 0 days Sat 1/4/23 Sat 1/4/23 1/4
2 Chilled water Piping Installlation 25 days Sat 1/4/23 Sat 29/4/23
3 Pressure test, RT and Chemical Cleaning for Chilled water Pipe 11 days Mon 1/5/23 Fri 12/5/23
4 Electrical Works 25 days Sat 13/5/23 Sat 10/6/23
5 BMS Work 25 days Sat 13/5/23 Sat 10/6/23
6 FCU Installation and Ducting works 25 days Sat 13/5/23 Sat 10/6/23
7 Drip tray and Condensate water pipe installation 25 days Sat 13/5/23 Sat 10/6/23
8 Testing & Commissioning and Handover 5 days Mon 12/6/23 Fri 16/6/23

Task Project Summary Manual Task Start-only Deadline

Project: Flurotec Service Area C Split Inactive Task Duration-only Finish-only Progress
Date: Mon 20/3/23 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone