Predecessors Mar 30, '24 Apr 6, '24 Apr 13, '24 Apr 20, '24 Apr 27, '24 May 4, '24 May 11, '24 May 18, '24 May 25, '24 Jun 1, '24 Jun 8, '24 Jun 15, '24 Jun 22, '24 Jun 29, '24 Jul 6, '24 Jul 13, '24 Jul 20, '24 Jul 27, '24 Aug 3, '24 Aug 10, '24 Aug 17, '24 Aug 24, '24 Aug 31, '24 Sep 7, '24 Sep 14, '24
Mode S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTW
1 MTD ADMIN BUILDING 136 days? Mon 4/1/24 Sun 9/15/24

2 REMOVAL OF EXISTING WATERPROOF43 days Mon 4/1/24 Sat 5/25/24

3 Mobilization of scaffolding material 2 days Mon 4/1/24 Tue 4/2/24


from triangular area to site location

4 Erection for stair scaffolding 4nos at 4 days Wed 4/3/24 Sun 4/7/24 3
periphery of buiding to access men
and material

5 Inspection of erected scaffolding and 1 day Mon 4/8/24 Mon 4/8/24 4


getting approval with inspector

6 Removal of aggregate from right part 10 days Tue 4/9/24 Wed 4/24/24 5
of building from roof to ground by
means of chute(PART-1)

7 Removal of aggregate from left part 10 days Tue 4/9/24 Wed 4/24/24 5
of building from roof to ground by
means of chute(PART-2)

8 Removal of waterproofing membrane 7 days Sat 4/20/24 Sat 4/27/24 6FS-5 days
from right part of building from roof
to ground(PART-1)

9 Removal of waterproofing membrane 7 days Sun 5/12/24 Sun 5/19/24 8FS+12 days
from left part of building from roof to
ground(PART-2)

10 Shifting of aggregate and water proof 35 days Mon 4/15/24 Sat 5/25/24 8FS-11 days
membrane from ground level to
dump truck using loader

11 WATERPROOFING 122 days? Mon 4/22/24 Sun 9/15/24

12 Shifting of construction materials 91 days Mon 4/22/24 Sat 8/10/24 8FS-5 days
from MTD store to site location

13 Providing Haunch -PART-1 4 days Mon 4/22/24 Thu 4/25/24 8FS-5 days

14 Apply water proofing primer 10 days Sat 4/27/24 Tue 5/7/24 13


BITUMAT BITUPRIME of two
coat(PART-1)

15 Laying of water proofing sheets 10 days Tue 4/30/24 Sat 5/11/24 14FS-7 days
BITUMAT POLYFLAME(PART-1)

16 Filling water test for 48 hours and 5 days Sun 5/12/24 Thu 5/16/24 15
remove water after
inspection(PART-1)

17 Providing Haunch-PART-2 4 days Mon 5/13/24 Thu 5/16/24 9FS-6 days

18 Apply water proofing primer 10 days Sat 5/18/24 Tue 5/28/24 17


BITUMAT BITUPRIME of two coat
(PART-2)
19 Laying of water proofing sheets 10 days Tue 5/21/24 Sat 6/1/24 18FS-7 days
BITUMAT POLYFLAME(PART-2)

20 Filling water test for 48 hours and 5 days Sun 6/2/24 Thu 6/6/24 19
remove water after
inspection(PART-2)
21 Laying of polystyrene board 15 days Sat 5/18/24 Thu 6/20/24 16

22 Bull mark for water slope to the 10 days Sun 5/26/24 Wed 6/26/24 21
existing drain

23 Laying of cement tiles 400X400X40MM40 days Sat 6/1/24 Sun 7/21/24 22FS-5 days

24 Grouting of tile joints 20 days Sat 7/20/24 Sun 8/11/24 23FS-7 days

25 Apply water proofing top 2 coat paint 30 days Wed 7/31/24 Tue 9/3/24 24FS-10 days
JOTA ROOF over PRIMERED cement
tiles
26 Fixing of Aluminium wall trim with 15 days Thu 8/29/24 Sun 9/15/24 25FS-5 days
elastometric sealant

Project: MTD ADMIN Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Date: Sat 3/30/24 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress