TIME SCHEDULE MODIFIED PP6 MACHINE

ID Task Name Early Start Finish 24 Dec '23 31 Dec '23 07 Jan '24 14 Jan '24 21 Jan '24 28 Jan '24 04 Feb '24 11 Feb '24 18 Feb '24 25 Feb '24 03 Mar '24
SMTWT F S SM TWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S S MTWT F S SMTWT F S SMTWT F S S MTW
1 ALL PROJECT Thu 04/01/24 Mon 26/02/24 04/01 26/02

2 PRODUKSI STOCK Thu 04/01/24 Thu 01/02/24

3 MECHANIC Thu 04/01/24 Thu 15/02/24

4 Modifikasi Rangka Extru D110 Thu 04/01/24 Fri 12/01/24

5 Pengadaan Material Thu 04/01/24 Mon 08/01/24

6 Rezise Frame Mesin Tue 09/01/24 Thu 11/01/24

7 Finishing Frame Mesin Fri 12/01/24 Fri 12/01/24

8 Re Install Extru D100 Thu 04/01/24 Mon 05/02/24

9 Pengadaan Material Thu 04/01/24 Mon 08/01/24

10 Reinstal Main Extruder Mesin Fri 02/02/24 Mon 05/02/24

11 Install Extru D110 Wed 07/02/24 Tue 13/02/24

12 Placement Frame Ext 110 Wed 07/02/24 Wed 07/02/24

13 Instal Main Extruder Mesin D110 Fri 09/02/24 Tue 13/02/24

14 Prepair New Utility Thu 04/01/24 Thu 15/02/24

15 Persiapan Material Utility Thu 04/01/24 Mon 08/01/24

16 Piping dan Instalasinya Thu 15/02/24 Thu 15/02/24

17 Part / Supprting mesin Extr D110 Tue 06/02/24 Thu 08/02/24

18 Pembuatan part / Flange Tue 06/02/24 Thu 08/02/24

19 ELECTRICAL Thu 15/02/24 Tue 20/02/24

20 Re Program PLC Mesin Extru D110 Thu 15/02/24 Tue 20/02/24

21 Re Program Ext D110 Thu 15/02/24 Fri 16/02/24

22 Simulasi program Mon 19/02/24 Tue 20/02/24

23 TRIAL AND COMISIONING Wed 21/02/24 Mon 26/02/24

24 Trial Run / Dry test Wed 21/02/24 Wed 21/02/24

25 Trial Produksi Thu 22/02/24 Mon 26/02/24 26/02